This is an action by the appellee against the, appellant, for damages for the breach of a contract, by which the defendant undertook and agreed to furnish material and build two houses in accordance with the contract set out in the record.
There was no error in either action of the court. The contract sued on is set out in the complaint, and it states distinctly thаt it is between W. A. Shriner and John Craft. The fact that Mary R. Shriner’s name appears a,t the end of the contract with W. A. Shriner does not make it her contract. The statute is clear on the right of amendment by striking out parties, and our decisions are uniform to the effect that the striking out of an improper party does not work a discontinuance of the case. It cannot be material how the fact comes to the knowledge of the court that such person is an improper party; whether it appears upon the face of the pleаding, and is brought to the attention of the court, by demurrer or is subsequently made to appear in the evidence. Section 5367, Code of 1907, and cases cited.
A number of the assignments of error are grouped by the appellant in his brief, being questions raised on sustaining motions to strike and demurrers to pleas, which set up a modification of the contract. The first proposition is correct, to wit, that the parties to a written contract may, by mutual parol agreement, modify the contract; but the second proposition, to wit, that said modification is binding withоut any new consideration, is not so clear. While there are some expressions in the cases which seem to dispense with the necessity of
Where a teacher, who had been employed at an annual salary, agreed to give up his definite contract and to serve during the рleasure of the board, it was held that the change in the terms of the teachers’ service, furnished a sufficient consideration for the promise of' increased compensation.—Hildreth v. Pinkerton Academy, 29 N. H. 227, 235.
Where an agreement to do blasting on certain terms-was made upon the representations of the defendant as to the quality of the rock to be blasted, and it was-found that the rock was much harder, and useless to the party blasting, in place of being useful, as represented, a new agreement to pay more for the work was supported by the additional work which the other- party agreed to perform.—Osborne v. O’Reilly, 42 N. J. Eq. 468, 475,
There is a class of cases, in which the original contract had been abandoned, and the parties afterwards entered into a new parol contract for the performance of the same work on different terms, and the contraсt was held to be valid. The theory of these cases seems to be that either party may abandon the contract and subject himself to the penalty or liability therefor, and then the parties are at liberty, to make another contract, in which the-original work, stipulatеd for in the
Other cases have gonе a. step further, and have held that, if one party finds himself in such a position that he cannot carry out the contract on the terms provided, and notifies the other party that he will abandon the contract unless different terms are granted, said second party has the option either to let the contract be abandoned, and depend on his action for damages, or to make the new agreement, the consideration being that he considers it worth more to him to have the benefits of the new agreement, than to recover his damages for the breach of the original contract.—Bishop v. Busse et al.,
It seems to this court that this latter class of cases has reached a dangerous limit in permitting one party to be bound by his promise to another, who has promised nothing but what he was already under contract obligation to perform, which is no consideration at all.—Koerper v. Royal Inv. Co.,
Where, upon the mere statement of the defendant that the drilling of the well would be very expensive, plaintiffs agreed to reduce the price of drilling, it was held no modification of the contract (Wendling v. Snyder et al.,
In our early case of Young v. Fuller,
In the case of Thomason v. Dill,
In the case of Johnson’s Adm’r v. Sellers,
In the case of Burkham v. Mastin.
In the case of Hall & Long v. Jones,
In the case of Cooper v. McIlwain,
In the case of Robinson v. Bullock,
The case of Badders & Britt v. Davis,
In the case of Clark & Wadsworth v. Jones,
The theory of Cornish et al. v. Suydam,
In the case of Pioneer Savings & Loan Co. v. Nonnemacher,
It is manifest that, in order for there to be a mutual assent, there must be something to be assented and agreed to on each side. Where the parties agree to rescind the contract, each one gives up the provisions for his benefit, the mutual assent is complete, and the parties are then competent to make any new сontract that may suit them. Where one piece of work is substituted
There was no error in sustaining the demurrer to the ninth plea. Said plea alleges that the ordinance in question was not passed until two weeks after the time when defendant was to commence work on the houses according to the contract, and the contract is set out in the complaint, and does not fix any time when work was to be commenced. Moreover, the plea does not show whether the agreement to have the ordinance passed was made at the time of the original contract or after, nor whether there was any consideration for it. It does not set up any supposed invalidity in the agreement.
There was no error in admitting the certificate of the architect. The contract (section 5) particularly provided for thе certificate and authorized the plaintiff to act on it. The admission of the paper does not necessarily make it conclusive evidence of the facts recited. That matter could be brought up by the offer to controvert it.
The certificate of the architect (Exhibit E) is also provided for by section 5 of the contract and was therefore admissible. The certificate states that the architect had audited the expense incurred, etc., in accordance with the provisions of the contract. The exceрtion to the introduction of this certificate did not suggest that there had been anything wrong about the manner m
Article 5 of the contract provides that the certificate of the architect as to the expenses incurred by the owner and the damages incurred through default “shall be audited аnd certified by the architect, whose certificate thereof shall be conclusive upon the parties.” The architect’s certificate was made out in accordance with the contract and certified that the amount due plaintiff is $1,035.34, and the court, on request of the plaintiff, instructed the jury if they believed the evidence to find for the plaintiff for that amount.
Where a building contract specially provides that the certificate of the architect shall be final and conclusive, it is conclusive and binding" in its legal operation and effect on the parties to the contract, and can be impeached only for fraud, or such gross mistakes as would imply bad faith or a failure to exercise an honest judgment.—6 Cyc. pp. 40-45, and notes; Tally v. Parsons,
There was no error in giving said general charge, and, that being the case, it is unnecessai’y to discuss other charges and points on evidence raising the same question.
The judgment of the court is affirmed.
Affirmed.
