MEMORANDUM DECISION ON MECHANIC’S LIEN CLAIMANT’S MOTION FOR SUMMARY JUDGMENT
On January 24, 2003, this court held a hearing on the motion for summary judgment (“MSJ”) filed by Defendant Killarney Construction Company, Inc. (“Killarney”). Defendant Primecore Mortgage Trust, Inc. (“Primecore”) filed an opposition to the MSJ. For the reasons stated below, the court will grant summary judgment in part and deny summary judgment in part. 1
I. Relevant Undisputed Facts
Killarney was the general contractor for the construction of live-work lofts for Showplace Square Loft Company, LLC (“Debtor”). Primecore was the initial lender for the project and recorded its deed of trust on March 16, 2000.
As of February 29, 2000, trenches had been dug at the construction site and stakes indicated the outline of the building to be constructed there.
2
In addition, on
Even though Killarney issued a stop work notice to all subcontractors and suppliers on May 4, 2001, work was performed between May 4, 2001, and July 5, 2001 (when Killarney was paid in full for its work through that date). In particular, one of Killarney’s subcontractors — Anvil Iron Works (“Anvil”) — installed ground floor exterior guard rails and interior handrails between May 9, 2001, and May 18, 2001.
Debtor recorded a Notice of Completion on December 20, 2001; the Notice indicated that work was completed on November 8, 2001. On February 26, 2002, Killarney recorded its mechanic’s lien in the amount of $488,347.60 plus interest. Killarney filed an amended mechanic’s lien on February 27, 2002, to correct the zip code of Debtor.
The City and County of San Francisco issued a Certificate of Final Completion and Occupancy for the project on November 8, 2001. The certificate stated: “To the best of our knowledge, the construction described above has been completed and, effective as of the date the building permit application was filed, conforms both to the Ordinance of the City and County of San Francisco and to the Laws of the State of California.” In addition, Killarney sent memoranda dated November 13 and November 14 to certain subcontractors noting that it “will be off’ the site or job on November 16, 2001.
On December 18, 2001, Killarney faxed to its primary subcontractors a punch list of items which needed to be completed. While many of these tasks were de mini-mus (i.e., clean kitchen counter, clean lower bath mirror and glass shelves, etc.), the punch list also directed subcontractors to,
II. Procedural History
On November 1, 2002, this court held a status conference in the above-captioned adversary proceeding. At that time, counsel for Killarney announced that she would shortly be filing the MSJ. The court and the parties discussed possible hearing dates and the need to take discovery prior to the hearing. The court tentatively scheduled the hearing for December 27, 2002, and counsel for Primecore indicated that he would file a Rule 56(f) declaration if the hearing were held so quickly. Counsel for Primecore requested that the hearing be held on January 17, 2002.
The parties agreed to work out an arrangement for rescheduling the hearing and for conducting discovery. On December 27, 2002, Killarney filed its MSJ and set it for hearing on January 24, 2002. 3
III. Discussion
A. Standard for Summary Judgment
Federal Rule of Civil Procedure 56(c) (“Rule 56”) (incorporated by Federal Rule of Bankruptcy Procedure 7056 (“Bankruptcy Rule 7056”)), provides that summary judgment “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.”
“The proponent of a summary judgment motion bears a heavy burden to show that there are no disputed facts warranting disposition of the case on the law without trial.”
Younie v. Gonya (In re Younie),
All reasonable doubt as to the existence of genuine issues of material fact must be resolved against the moving party.
Anderson v. Liberty Lobby, Inc.,
B. General Principles of California Mechanic’s Lien Law
A general contractor is entitled to a lien on a construction project as security for payment of the labor and materials furnished to the project. Cal. Civ.Code § 3110. The mechanic’s lien is entitled to “off-record priority;” in other words, it has priority over any lien, mortgage or deed of trust recorded subsequent to commencement of work, even when the mechanic’s lien claim is recorded after the other lien, mortgage or deed of trust. Cal. Civ.Code § 3134.
A general (or original) contractor, in order to enforce a lien, “must record his claim of lien after he completes his contract and before the expiration of (a) 90 days after the completion of the work of improvement ... if no notice of completion or notice of cessation has been recorded, or (b) 60 days after recordation of a notice of completion or notice of cessation.” Cal. Civ.Code § 3115. In addition, when work ceases completely on an uncompleted project for sixty days but resumes thereafter, “a new date for priorities also begins with the commencement of the new work.” Miller & Starr, California Real Estate 3d ed., § 11:127 (2000) (“Miller & StarT’); Cal. Civ.Code § 3086. In other words, the “off-record” priority of the mechanic’s lien will relate back only to the re-commencement of work.
C. Application of Law to Undisputed Facts
1. Work Commenced Prior to March 16, 2000
A mechanic’s lien acquires off-record priority upon “commencement of the work of improvement.” Cal. Civ.Code § 3134. “ “Work of improvement’ includes but is not restricted to the construction, alteration, addition to, or repair, in whole or in part, of any building, wharf, bridge, ditch, flume, aqueduct, well, tunnel, fence, machinery, railroad, or road, the seeding, sodding, or planting of any lot or tract of land for landscaping purposes, the filling, leveling, or grading of any lot or tract of land, the demolition of buildings and the removal of buildings.” Cal. Civ.Code § 3106 (emphasis added).
“For purposes of establishing the priority of mechanics’ lien claimants who perform work or supply materials for the construction of an improvement, the work is not considered as having ‘commenced’ until there is some physical work on the property that is apparent and visible, and the work must be of a permanent nature.”
Miller & Starr
§ 11:125 (citing various California cases);
see also Simons Brick Co. v. Hetzel,
In
Simons,
the holder of an unrecorded mortgage testified that, when he went upon the premises for the purpose of ascertaining if any construction was being
Here, Primecore’s own witness took pictures prior to March 16, 2000, showing that trenches had been built on the property, stakes had been placed, and that construction equipment was present. Primecore’s own witness testified that he saw “evidence of construction going on” at the site prior to March 16. In particular, he saw people working on the site, equipment being operated on the site, and trenches on the site. Furthermore, Primecore has not refuted that soil compaction occurred prior to March 16, 2000. The foregoing work is undisputed. Under Simons and English, because the effects of this work are apparent and visible and of a permanent nature, construction commenced for the purposes of California Civil Code section 3134. Primecore has not introduced evidence that this work did not occur, so summary judgment in favor of Killarney is appropriate as to this issue. 4
2. Work Did Not Cease In April 2001
Primecore contends that Killarney lost any off-record priority over Prime-core’s recorded lien because of a “cessation of labor ... for a continuous period of 60 days.” Cal. Civ.Code § 3086(c). In particular, Primecore contends that labor ceased from May 4, 2001, through July 6, 2001. Killarney, however, introduced undisputed evidence that Anvil was on the site installing ground floor exterior guard rails and interior handrails between May 9, 2001, and May 18, 2001. Therefore, labor did not cease completely and continuously for a sixty-day period.
W.F. Hayward Co. v. Transamerica Ins. Co.,
Debtor recorded a Notice of Completion on December 20, 2001; the Notice indicated that work was completed on November 8, 2001. Debtor therefore did not record its notice of completion within ten days of the purported date of completion as required by California Civil Code section 3093(e), which provides that the “the notice of completion shall be recorded in the office of the county recorder of the county in which the site is located, within 10 days after such completion.” Consequently, the notice of completion was invalid.
Fontana Paving, Inc. v. Hedley Bros., Inc.,
Killarney recorded its mechanic’s lien on February 26, 2002. If the Notice of Completion had been valid, Killarney would have been required to record its lien within 60 days of December 20, 2001 (or no later than February 18, 2002). Cal. Civ. Code § 3115. Because the Notice of Completion was untimely and invalid, however, Killarney had 90 days after the completion of the work of improvement in which to record its hen.
Id.; Fontana Paving, Inc.,
Killarney requests that this court enter summary judgment that it filed its lien within 90 days of completion. The court cannot do so, because a material fact dispute as to the date of completion. Prime-core contends that completion occurred on November 8, 2001 (as set forth in the Notice of Completion) or November 16, 2001 (the date that Killarney should have been off the site according to notices it provided to subcontractors) while Killar-ney contends that work was not completed until mid-January 2002.
Although section 3115 does not define “completion” as “substantial completion,” cases interpreting California’s mechanic’s lien laws have held that “substantial completion” triggers the 90-day time period.
Mott v. Wright,
Here, a material factual issue exists as to whether the project was substantially completed more than 90 days before February 26, 2002. Primecore has produced sufficient evidence (the Notice of Comple
In addition, without knowing what was involved to complete the tasks contained on the punch-list, this court cannot conclude as a matter of undisputed fact that such tasks were not trivial. Accordingly, summary judgment is denied as to this issue.
D. Primecore’s Informal Rule 56(f) Request
For the reasons set forth in footnote 3, the court is denying Primecore’s informal Rule 56(f) request for further discovery. Nonetheless, to the extent that the question of whether Killarney timely filed its lien is still unresolved, discovery may proceed on that issue.
IV. Disposition
Counsel for Killarney should submit an order consistent with this memorandum decision. In doing so, counsel should comply with B.L.R. 9021-1 and B.L.R. 9022-1. The court will hold a further status conference in this matter on February 28, 2003 at 1:30 p.m.
Notes
. The following discussion constitutes the court’s findings of fact and conclusions of law. Fed. R. Bankr.P. 7052(a).
. Primecore does not dispute that this work was done before March 16, 2000. In fact, Primecore’s own witness, Frank Torrente, took photographs of the site on March 13, 2000, which showed the existence of the trenches. As admitted by Primecore on page 5 of its memorandum of points and authorities in opposition to the MSJ, the "photographs evidenced the work at the site that constituted soil compaction.” At his deposition, Mr. Torrente testified that on March 13,
Instead of disputing that the trenches had been dug and the soil compaction had been performed prior to March 16, Primecore attempts to argue (1) that construction had not “commenced” because certain computer software showed the start date as March 20, 2000, (2) that certain other tasks (such as storage of lumber and paint and the installation of casing) were performed on other phases of the project; and (3) that any work performed prior to that date was not performed pursuant to Killarney's prime contract with Debtor. The first two contentions are irrelevant (for the reasons discussed later); assuming that Primecore's contentions are true, they do not change or alter the material fact that soil-testing, soil-compacting and trench-digging occurred prior to March 16, 2000.
Anderson
v.
Liberty Lobby, Inc., 477
U.S. 242, 247-48,
. In his declaration in opposition to the MSJ, counsel for Primecore indicates that he had reached an agreement with Killarney’s counsel to limit discovery to issues pertaining to priority of Killarney's lien. Killarney's counsel disputes this. References in memoranda and declarations to a need for further discovery do not qualify as motions required by Federal Rule of Civil Procedure 56(f).
Brae Transportation, Inc.
v.
Coopers & Lybrand, 790
F.2d 1439, 1443 (9th Cir.1986). Nonetheless, the court is denying summary judgment as to the issue on which Primecore is requesting further discovery, so even if the request had been in proper form, it is moot. With respect to the priority issue, the matter is determinable on the papers presented, so further discovery would be futile.
Mullis v. U.S. Bankruptcy Court,
. As discussed in footnote 2, Primecore has raised extraneous and irrelevant purported factual disputes in an effort to prevent summary judgment that construction commenced prior to March 16, 2001. These arguments are either irrelevant or not supported by facts or evidence.
. Primecore argues that the work performed by Anvil was tardy and that Killarney had issued a stop work notice for the relevant time period. Neither of these arguments refutes the simple and relevant fact that Anvil did do original installation work from May 9 through May 18, 2001. Primecore cannot defeat summary judgment by manufacturing irrelevant factual disputes.
Liberty Lobby, 477
U.S. at 247-48,