Lead Opinion
¶ 1. This case arises from the June 2008 floods in Oshkosh. Mark Showers and his businesses, Showers Appraisals, LLC, and Real Marketing, LLC, sued Musson Bros., Inc. and the City of Oshkosh for damages suffered in those floods. At the time of the storm, Musson was working as a private contractor for the State of Wisconsin to replace the storm sewer in front of Showers' building. Musson claimed, and the trial court agreed, that it is entitled to governmental immunity under Estate of Lyons v. CNA Ins. Cos.,
BACKGROUND
¶ 2. We begin with an overview of the magnitude of the June 2008 storms in Oshkosh.
¶ 3. Next, we outline the relationships between Musson, the department of transportation (DOT) and the City regarding the construction project that was in process outside Showers' property when the storms hit. Musson signed a "contract for highway work" on January 9, 2008, which was later approved by the governor of Wisconsin and a DOT representative. The contract was for a project to replace sanitary and sewer mains in an area that included Showers' property. Plans and specifications for the project were incorporated into the contract by the DOT. Musson was "solely responsible for the means, methods, techniques, sequences, and procedures of construction."
¶ 5. The City maintains that there was a prior unwritten understanding between the City, Musson and the DOT to go block-by-block. After the City discovered that Musson had disconnected a larger portion, it complained to the DOT, but was told that the decision was a means and methods decision within Musson's discretion. Ultimately, even with the decision to disconnect an entire road, Schanhofer and the DOT project manager assigned to the project testified that Musson met the contract specifications, particularly those related to drainage. Schanhofer additionally explained that if there had been a problem with contract compliance and he was aware of it, he would have had the power and responsibility to intervene to ensure that the contractor came into compliance with the contract.
¶ 6. After the first wave of rain on June 8, 2008, and warnings of more to come, Musson worked with the City and the DOT to formulate a plan to handle the rain
¶ 7. Showers sued Musson and the City, alleging that his property was damaged as a result of their negligence on the project. The City and Musson each filed cross-claims against each other for indemnification, and they each filed motions for summary judgment against all of Showers' claims. The trial court granted summary judgment, reasoning that governmental immunity applied to both the City and Musson. Showers appeals as to Musson, and Musson has filed a cross-appeal against the City.
DISCUSSION
¶ 8. Before we get into the specific issues raised by Showers, we will provide a brief overview of governmental immunity law that is relevant to this case. Wisconsin Stat. § 893.80(4) (2009-10)
*631 No suit may be brought against any .. . governmental subdivision or any agency thereof for the intentional torts of its officers, officials, agents or employees nor may any suit be brought against such . . . subdivision or agency... or against its officers, officials, agents or employees for acts done in the exercise of legislative, quasi-legislative, judicial or quasi-judicial functions.
In Lyons, we elaborated on the meaning of "agent" as used in § 893.80(4). See Estate of Lyons,
(1) the governmental authority approved reasonably precise specifications;
(2) the contractor's actions conformed to those specifications; and
(3) the contractor warned the supervising governmental authority about the possible dangers associated with those specifications that were known to the contractor but not to the governmental officials.
Id.
¶ 9. The analysis does not end even with a determination that the contractor is entitled to governmental immunity under Lyons. For example, our case law applying Wis. Stat. § 893.80(4) has differentiated between the government's discretionary acts and its ministerial duties. Willow Creek Ranch, LLC v. Town of Shelby,
¶ 10. In this appeal, Showers claims that Musson is not entitled to governmental immunity as an agent under Lyons, and that even if Musson meets the Lyons test, it is still not protected by governmental immunity because it had a ministerial duty to maintain drainage at the construction site, which it did not do. Alternatively, Showers argues that the June 8 rains created a situation where there was a known and compelling danger that gave rise to a ministerial duty. Thus, he argues that summary judgment should not have been granted as to Musson. Musson cross-appeals as to the City, arguing that if summary judgment is reversed as to Musson, it should be reversed as to the City as well. As we said at the outset, since we affirm summary judgment as to Musson, we need not address its cross-appeal.
¶ 11. We review summary judgments de novo, using the same methodology as the trial court. Green Spring Farms v. Kersten,
Independent contractor immunity — reasonably precise specifications
¶ 12. We first address whether Musson meets the Lyons immunity test. Showers focuses primarily on the first two prongs of the Lyons test — whether there were reasonably precise specifications and whether Musson followed them.
¶ 13. The contract provisions which Showers believes to be problematic are as follows:
(1) "The contractor is solely responsible for the means, methods, techniques, sequences, and procedures of construction."
(2) "Before suspending the work, take the necessary precautions to prevent damage to the project, prevent traffic accidents, and provide for normal drainage."
(3) "The contractor shall... [clonduct operations and maintain the work so that adequate drainage is provided at all times."
(4) "If it is necessary in the prosecution of the work to interrupt existing surface drainage, sewers, or under drainage, provide temporary drainage until completing permanent drainage work."
(5) "If storing salvaged topsoil on the right-of-way during construction operations, stockpile it to preclude interference with or obstruction of surface drainage."
(6) "Preserve, protect and maintain all existing tile drains, sewers, and other subsurface drains, or parts thereof, that the engineer judges should continue in service without change."
(7) "If the contractor damages or interrupts services, the contractor shall notify the utility promptly."
*635 (8) "Notify, in writing, all public and private property owners whose property interferes with the work. Advise them of the nature of the interference, and arrange with them for the disposition of the property."
(9) "Use every reasonable precaution to prevent damage to all property including... all underground structures including water or gas shut-off boxes, water meters, pipes, conduits, etc.; within or outside the right-of-way."
¶ 14. We begin by analyzing whether these provisions are "specifications" as that term is used in Lyons. One definition of "specification" is found in Black's Law Dictionary 1434 (8th ed. 2004): "[t]he act of making a detailed statement, especially] of the measurements, quality, materials, or other items to be provided under a contract." If we were to use this definition, it would auger in Showers' favor because it implies something more specific than the provisions at issue in this case. However, we did not use the term "specifications" in a vacuum when we wrote Lyons. Instead, we used a modifier to precede the word "specifications"—the term "reasonably precise." Estate of Lyons,
¶ 15. Indeed, some flexibility in contract specifications is necessary and even desirable. In construction, for example, not everything can be foreseen and put into a contract that will define exactly how a contractor must respond to every situation. Instead, the owner of the project outlines certain bottom-line expectations that the contractor must make sure to adhere to. Those expectations create a framework through which everyone can operate when unexpected situations—such as
¶ 16. Based on Lyons' implicit recognition of the need for some flexibility in contract specifications, we think the definition in Webster's more accurately captures what we said in Lyons. See Webster's Third New International Dictionary 2187 (1993). A "specification" is "a detailed, precise, explicit presentation (as by enumeration, description, or working drawing) of something or a plan or proposal for something." Id. (emphasis added). And when we view specifications in the Webster's sense of the term — as "a plan or proposal for something" — then there is no question that the contract provisions highlighted by Showers are indeed specifications.
¶ 17. Thus, the only remaining issue is whether the standard specifications were reasonably precise. On that point, we agree with Showers to this extent: if a contractor is given so much discretion that it is not acting as an agent of the State but as a free agent acting without direction from the government, the first prong of Lyons would not be met. But we disagree with the principle that just because the contractor has some discretion in how to meet a desired specification outlined in the contract, Lyons immunity is lost as to that decision.
¶ 19. Based on the reasoning in Bronfeld, in a case such as this one, where the contractor and the government had to rely on general specifications because aspects of the more specific plan were not working, the focus of our inquiry is whether the government had genuine oversight of the project despite the contractor's apparent discretion. If the only specifications curtailing Musson's discretion in this case were the written specifications highlighted by Showers, Showers would have a much stronger argument. However, in addition to the written plans and specifications, the DOT was involved with the project on an ongoing basis with regular opportunities to give input and be involved in the decision-making process. And Schanhofer testified that if contract compliance had been at issue, he would have had to intervene. In addition to that testimony, the DOT's
¶ 20. In other words, the DOT always had the power and responsibility to intervene if compliance with the contract was at issue. In this case, the standard specifications that applied to Musson's allegedly negligent methods, combined with the DOT'S oversight of those methods, curtailed Musson's discretion. See id., ¶¶ 28-29. It is that combination that convinces us that Musson was subject to reasonably precise specifications that satisfy the first prong of Lyons.
Independent contractor immunity — conformity with the. government's reasonably precise specifications
¶ 21. Showers spent the bulk of his brief addressing whether Musson met the DOT standard specifications we enumerated above. Much of Showers' argument on this issue involves general provisions — for example, to provide "adequate" drainage at all times, take "necessary" precautions to prevent damage and provide for "normal" drainage, and use "reasonable" precautions to prevent damage to property.
¶ 22. Our analysis of whether Musson met the DOT's reasonably precise specifications is framed by the purpose of that prong of the Lyons test — to "ensure that the challenged design is within the class of official
¶ 23. Thus, we again look to the DOT's level of ongoing oversight and involvement in dealing with an evolving situation. The bottom line is that the DOT was regularly on site and kept a close eye on Musson's activities. Both Schanhofer and the DOT project manager, as well as Musson's own project manager, stated under oath that the contract specifications, including the maintenance of adequate drainage and other provisions cited by Showers, were followed. Showers' expert does not counter that testimony and therefore does not create a genuine issue of material fact as to whether the reasonably precise specifications were followed.
¶ 24. Showers next argues that affidavits from people who were near his property on June 12 stating
¶ 25. Finally, Showers briefly alleges that there is a genuine issue of material fact as to whether block-by-block storm sewer disconnection was an agreed upon method of construction that became a reasonably precise specification Musson had to follow. We see no problem here. Although there is conflicting testimony as to whether the parties agreed at the beginning of the project to a block-by-block disconnection plan, it is undisputed that once Musson decided to do otherwise, the DOT stood by Musson's decision. It obviously did not believe Musson to be acting out of conformity with the contract because, not only did it not exercise its right to intercept such conduct, it told the City that the City had no power to act in this area.
¶ 26. We now move to the remaining, more concrete standard specifications that Showers alleges were
¶ 27. Showers also contends that Musson failed to "[n]otify in writing, all public and private property owners whose property interferes with the work [and to a]dvise them of the nature of the interference, and arrange with them for the disposition of the property." Showers argues that Musson failed to meet this specification when it did not notify Showers that the storm sewer servicing his property had been disconnected. We do not read this specification to require that action, however. There is no contention that Showers' property in any way interfered with the project such that the contractor needed to arrange for the disposition of his property in light of the interference. We do not see how this specification applies with regard to Showers' property.
¶ 28. We next address Showers' claim that even if the Lyons test is met, Musson is not entitled to immunity because it had a ministerial duty to maintain a system of drainage, which is something it did not do. To support that argument, Showers relies on Menick v. City of Menasha,
¶ 29. Menick is totally inapplicable to this case. Menick explained how there was a difference between designing and building a public works system according to the design on the one hand, and maintaining the system once it was built. Id. Immunity is granted to the municipality for the former, but not the latter. Id. Since Musson was not involved in "maintaining" an existing system, but in building a new system, this is not a Menick case.
¶ 30. Lastly, we address Showers' related argument that the June 8 rains created a situation where there was a known and present danger that created a ministerial duty to act. In Lodi, our supreme court explained:
To pierce immunity pursuant to this exception, we must be able to conclude that the circumstances were sufficiently dangerous so as to give rise to a ministerial*644 duty — not merely a generalized 'duty to act' in some unspecified way, but a duty to perform the particular act upon which liability is premised ....
Lodl,
¶ 31. Because we affirm summary judgment and need not address the cross-appeal, costs may be allowed against Showers under Wis. Stat. Rule 809.25(l)(a).
By the Court. — Judgment affirmed.
Notes
In his reply brief, Showers asserts that Musson did not raise the June 2008 rains as an affirmative defense in its answer to the complaint. He claims that "[s]ince Musson does not make a concise reference to these defenses, as a matter of law, the court must bar Musson's arguments regarding storm sewer drainage capacity in Oshkosh, 75-year event, and Acts of God." We disagree with that contention. Musson listed, as an affirma
All references to the Wisconsin Statutes are to the 2009-10 version unless otherwise noted.
Showers also argues briefly that the third factor of the test set forth in Estate of Lyons v. CNA Ins. Cos.,
We suspect Showers withdrew his concession because our notice of oral argument contained questions that cast the issues in a different light from the briefs.
More specifically, we are referring to the following specifications: (1) Conduct operations and maintain the work so that adequate drainage is provided at all times; (2) Take the necessary precautions to prevent damage to the project, prevent traffic accidents, and provide for normal drainage; (3) Use every reasonable precaution to prevent damage to all property including all underground structures including water or gas shut-off
Of those, only the fifth — regarding stockpiling salvaged topsoil to preclude interference with surface drainage — is arguably concrete enough to lend itself to outside expert testimony that it was objectively not met. On that point, Showers' expert referred to a photograph taken June 13, 2008, and stated that "if it was [Musson's] intention to pump the water along Ohio Street for purposes of drainage ... those piles will clearly stop the flow of water." However, the relevance of that opinion to determine whether the specification was met is premised on the assumption that to be successful, Musson had to stockpile any topsoil to preclude interference with drainage from the seventy-five-year rain that occurred on June 12. We simply do not believe that is the case, as we explain in the body of the opinion.
Dissenting Opinion
¶ 32. (dissenting). This case is not about rain that fell in June 2008. This case is about Lyons being expanded to provide blanket immunity to all government contractors. Lyons properly held that government contractors are entitled to immunity for "certain tasks" for which they were given "reasonably precise specifications"; i.e., where the contractor lacks discretion in the performance of "certain tasks." See Estate of Lyons,
¶ 33. Musson requested immunity. As noted by the majority, case law dictates that when a party seeks immunity we assume for purposes of summary judgment that the party seeking immunity was negligent. See Majority op., ¶ 22. Musson bid and was awarded a $4.3 million contract to reconstruct Wisconsin and Ohio
¶ 34. The majority acknowledged that the State, the City of Oshkosh, and Musson all had an "unwritten understanding" that Musson would disconnect the storm sewer on a block-by-block basis. Id., ¶ 5. Musson later decided to rip out the entire storm sewer all at once rather than the agreed upon block-by-block method. The DOT conceded that Musson had the right to change the method of construction, as it fell within the means and methods clause of the contract. Id. We also know that the State did not dictate how the storm sewer was to be removed, how many pumps Musson needed to have on hand, or where those pumps were to be located. Given that summary judgment was granted, we do not know why Musson deviated from the unwritten agreement regarding removal. Perhaps Musson saved costs by removing the entire storm sewer all at once. Musson may have decided to risk removal of the entire storm sewer against the risk that it might rain. Whatever the reason, Musson retained the contractual right — the means and methods — to gamble on the method of removal of the storm sewer. Musson remained, however, contractually obligated should its gamble fail. Until now.
¶ 35. I suspect the rationale for expanding immunity to the discretionary acts of government contractors is to obtain the lowest possible bids from contractors bidding for public works projects. The temporary bargain gained by lower bids from private contractors is
¶ 36. The policy question presented by this case is whether immunity for a private contractor's discretionary acts is wise. I believe it is poor public policy to insulate (through immunity) government contractors from sloppy, negligent work. Musson should not be entitled to immunity as Musson was not restricted in its performance of the contract by a government imposed obligation to perform a certain task according to reasonably precise specifications — the situation Lyons is meant to apply to. Quite the opposite, Musson is being granted immunity in this case because Musson alone decided how a certain task was to be performed. While the means and methods provision in the contract grants Musson the right to perform in the manner it choses, it also requires Musson to be responsible for damages caused by its negligent performance.
¶ 37. As I believe the majority has erred in its conclusion that discretionary acts of government contractors are entitled to immunity under Lyons, and as I believe the public policy of granting immunity to government contractors for their discretionary acts is counterproductive and will have severe and adverse consequences, I respectfully dissent. I would reverse and
