*312 Affirmed by published opinion. Judge WILKINSON wrote the opinion, in which Judge DUNCAN and Judge AGEE joined.
OPINION
In this case, a subcontractor to a subcontractor to a prime contractor with a federal agency brought a procedural due process claim against that agency and tort actions against a separate contractor for allegedly causing the termination of his at-will consulting agreement. Following discovery, the district court granted summary judgment to the defendants. Because permitting these claims to go forward would reward artful pleading and impermissibly constitutionalize state tort law, we affirm the district court.
I.
A.
This case arose out of the United States Coast Guard’s Deepwater Acquisition Project, a collection of acquisition programs undertaken to modernize the Coast Guard’s deep-water ships and aircraft. Given the scope and complexity of the Deepwater Project, this ease boasts a large cast of characters, and we shall do our best to assist the reader in keeping them straight. In March 2008, Adam Shirvinski, a retired United States Coast Guard Captain, entered into a private at-will consulting agreement with Mohawk Information Systems and Consulting, Inc. (“MISC”). According to the contract, Shirvinski promised to provide consulting services regarding Configuration Management (“CM”) and Quality Assurance (“QA”) issues to the Coast Guard regarding the Deepwater Project. Under its terms, either party could unilaterally terminate the contract by giving thirty days written notice.
MISC, in turn, was a subcontractor to SFA, Inc. (“SFA”), which had a prime contract with the Coast Guard to work on the Deepwater Project. The Coast Guard had also hired Booz Allen Hamilton, Inc. (“Booz Allen”) to work on Deepwater through a separate contract.
Shirvinski began his stint as a private consultant in March 2008 at a Coast Guard facility in Rosslyn, Virginia. Over the next few months, tensions in the workplace arose between Shirvinski and a number of Coast Guard and Booz Allen employees. For example, Shirvinski admitted he told Booz Allen personnel on March 13 that he “was taking over CM functions” and that all CM issues should be brought “to [his] attention.” In addition, Shirvinski criticized a CM plan developed by Booz Allen and Stephen Hoshowsky, a civilian Coаst Guard employee, and recommended that a Booz Allen employee, Vik Singh, be removed from CM functions on the Deepwater Project. Commander Richard Fontana, the Deputy Project Manager, also began to “receive[] multiple complaints” about Shirvinski’s “conduct and the way he interacted with people,” including charges that he was “brusque and abrasive.” After hearing concerns over Shirvinski’s behavior, Commander Fontana instructed Hoshowsky to bring any complaints about Shirvinski to his attention.
In accordance with this directive, Hoshowsky sent an email containing a list of issues regarding Shirvinski to Fontana and several other Coast Guard officials on August 6, 2008. Hoshowsky copied several Booz Allen employees, including Singh, on this email as well. Included in this list of complaints was the charge that Shirvinski “has introduced himself as the CG-933 CM/QA Division Head reporting directly to [the Project Manager] at every meeting and telecom I have attended with him.” *313 Several days later, on August 11, Hoshowsky forwarded a copy of this email to Lieutenant Christopher Armstrong. The next day, Lieutenant Armstrong called the office of Lieutenant Commander Michael Gero, the Contracting Officer’s Technical Representative, to request Shirvinski’s removal from the Deepwater Project. On the morning of August 13, Armstrong forwarded Hoshowsky’s email to Gero’s deputy in support of his request.
After receiving Hoshowsky’s email, Gero passed it along to another Coast Guard official, Contract Specialist Gwendolyn Scott, who was the assistant to Coast Guard Contracting Officer Cheryl Ellis. Gero, Ellis, and Scott then convened to discuss the request to remove Shirvinski from Deepwater. Following their meeting, Scott notified SFA by email that
It has come to our attention that Adam Shirvinski, a subcontractor on HSCG2305-F-TTV002 has violated Sections 1.3.3 and 1.3.4 of the Task Order Performance Work Statement on a number of occasions. We have received reports Mr. Shirvinski has improperly introduced himself as the CG-933 CM/QA Division Head and failed to adhere to the task order requirement to properly identify himself as a contractor.... We ask[] that you take corrective action immediately and update us regarding the outcome of this matter. Please cоntact us if you have any questions.
SFA’s Vice President of Business Administration, Shirley Place, responded, “I am immediately looking into this, and I will be back with you shortly. We apologize in advance, we will perform an investigation, and we will rectify the situation asap!”
Later that day, SFA sent a letter to MISC stating that because the “Coast Guard has advised us that Mr. Shirvinski ... has violated Coast Guard policy,” he “should be terminated immediately and will no longer be allowed to perform on any [SFA] contract or subcontract.” That evening, MISC’s Operations Vice President, Captain Joseph Ryan, informed Shirvinski that “SFA directed MISC to terminate your services” on the Deepwater Project and that “[i]n accordance with SFA’s direction, your services are terminated on that task.”
B.
On August 11, 2009, Shirvinski filed a complaint in federal court against Hoshowsky, the Coast Guard, Booz Allen, and SFA’s successor, Global Strategies Group (North America), Inc., containing state law claims of defamation, conspiracy, and tortious interference. His sole cause of action against the Coast Guard was a defamation claim seeking a declaratory judgment ordering it to amend its records to show that the allegations against him were false.
The district court permitted the United States to substitute itself for Hoshowsky under the Federal Employees Liability Reform and Tort Compensation Act, see 28 U.S.C. § 2679(d), and then dismissed Shirvinski’s claims against the United States because he had failed to pursue administrative remedies as required by the Federal Tоrt Claims Act (“FTCA”). See id. § 2675(a). The court also dismissed his defamation claim against the Coast Guard because it lacked jurisdiction under the FTCA to hear common law tort suits for equitable relief, see id. § 1346(b)(1), and his claims against SFA’s successor because his allegations were either legally insufficient or barred by Virginia’s statute of limitations.
After the bulk of his original claims had been rejected by the district court, Shirvinski decided to pursue a new strategy. To that end, he filed a second amended *314 complaint on March 30, 2010. * This time, he brought a federal procedural due process claim against the Coast Guard seeking similar equitable relief and state tort claims against Booz Allen for damages. Following discovery, both defendants moved for summary judgment.
The district court granted their motions on all counts. It dismissed Shirvinski’s procedural due process claim against the Coast Guard because it found that he was unable to show a constitutional injury. With regard to Booz Allen, the court dismissed Shirvinski’s common law and statutory conspiracy claims because he could not show that Booz Allen conspired to remove him from Deepwater “through unlawful means.” It also dismissed his tortious interference with contract claim because this cause of action did not extend to an at-will contract and his claim for tortious interference with prospective economic advantage because it found that Booz Allen did not employ any improper methods.
Shirvinski appeals the district court’s ruling on all counts except for his tortious interference with contract claim. We review a grant of summary judgment
de novo
and apply the same standards as the district court.
Nader v. Blair,
II.
We first address Shirvinski’s procedural due process claim against the Coast Guard. In order to prevail, appellant must show “(1) a cognizable liberty or property interest; (2) the deprivation of that interest by some form of state action; and (3) that the procedures employed were constitutionally inadequate.”
Kendall v. Balcerzak,
A.
The first problem with Shirvinski’s argument is that even if the Coast Guard did request his removal from the Deep-water Project, he has not suffered a constitutionally cognizable injury. Appellant assumes that he “need only show ... removal from [a] contract” accompanied by “an untrue government statement about him alleging serious character defect” to demonstrate a deprivation of a protected liberty interest. Id. at 44. However, a government’s allegedly “defamatory” request that its prime contractor no longer assign one of its subcontractors to a particular government contract fails to rise to the level of a constitutional injury.
The Suрreme Court’s consistent guidance in this area counsels against finding constitutional injury here. Since
Paul v. Davis,
In the context of public employment, this change in status occurs when the government acting as an employer discharges one of its employees.
See id.
at 705,
To be sure, the Coast Guard’s action may have affected Shirvinski’s
private
employment prospects with SFA and MISC. But unlike the loss of a government job, that injury does not work a change in legal status. Once again,
Paul v. Davis
is instructive. The plaintiff in that case was a private employee who was reprimanded by his supervisor after local police departments published a list of shoplifters that included his name.
Like the published list of shoplifters at issue in
Paul,
the Coast Guard’s concerns may have restricted Shirvinski’s private employment opportunities by causing MISC to terminate his consulting agreement and SFA to refuse to work with him again. But even if the Coast Guard’s concerns “undoubtedly ... impaired] his future employment prospects,” that fact alone does not amount to a
constitutional
injury.
See Siegert,
Diluting the requirement of a change in legal status would needlessly court conflict with a sister circuit as well. The District of Columbia Circuit has made clear that the removal of a subcontractor from a particular government contract need not be an injury of constitutional magnitude. In
Kartseva v. Department of State,
Shirvinski cannot meet this demanding test. Rather than being “foreclosed from reentering the field,” he has “merely lost one position in [his] profession.”
See Kartseva,
The facts of this case also make clear that allowing Shirvinski’s constitutional claim to go forward would do exactly what the Supreme Court has warned us not to do: transform the Fifth Amendment’s Due Process Clause into “a font of tort law” in the field of government contracts.
See Paul,
After learning that the FTCA barred him from pursuing this common law defamation action, Shirvinski repackaged his case against the Coast Guard as a procedural due process suit. This overlooks the fact that “[o]ur Constitution deals with the large concerns of the governors and the governed.”
Daniels,
Alowing this claim to proceed would only reward artful pleading to the detriment of public-private partnerships. The government “has a legitimate interest in promoting efficiency and integrity in the discharge of official duties, and in maintaining proper discipline in the public service,”
Engquist v. Or. Dep’t of Agric.,
The imposition of needless burdens on communication necessary for the functioning of government is what the FTCA’s defamation exception was designed to prevent. That exception was added to the FTCA to ensure “that government officials should not be hampered in their writing and speaking by the possibility that their actions would give rise to government liability.”
Quinones v. United States,
B.
Shirvinski has not only failed to allege a constitutionally cognizable injury. His claim also fails because the Coast Guard did not deprive him of a liberty interest without providing due process. Instead, SFA — a private entity — instructed MISC — another private entity — that Shirvinski “should be terminated immediately” and MISC complied by promptly ending his consulting agreement. This absence of state action is fatal to his constitutional claim. For “[u]nless there has been a ‘deprivation’ by ‘state action,’ the question of what process is required and whether any provided could be adequate in the particular factual context is irrelevant.”
See Stone v. Univ. of Md. Med. Sys. Corp.,
To surmount this hurdle, Shirvinski сontends that the Coast Guard requested his immediate removal from the Deepwater Project and is therefore responsible for the termination of his contract. But assigning constitutional liability to government agencies for the conduct of private parties is not something we do lightly. The government “normally can be held responsible for a private decision only when it has exercised coercive power or has provided such significant encourage
*318
ment, either overt or covert, that the choice must in law be deemed to be that of the State.”
Blum v. Yaretsky,
Shirvinski cannot make this showing. As the district court noted, there is no admissible evidence that “shows an actual request or directive from the Coast Guard to SFA that Shirvinski bе removed.” Instead, the record indicates that the Coast Guard expected SFA to conduct an investigation into the allegations against him before taking action. According to Gwendolyn Scott, the assistant to Contracting Officer Ellis, she did not contact Shirvinski upon learning of the allegations because he “wasn’t an employee of the Coast Guard and we did not have a direct contractual relationship with [him].” As she pointed out, the Coast Guard “paid SFA to manage their employees and subcontractors, and it was their job to investigate these allegations and let us know what they were going to do to correct them if they were true, or tell us if they weren’t true.”
The Coast Guard’s contractually-based expeсtation that SFA would provide some procedural safeguards before terminating Shirvinski was hardly unreasonable. After Scott informed SFA of the allegations against Shirvinski and asked it to “take corrective action,” SFA’s Vice President of Business Administration, Shirley Place, promised to “perform an investigation.” And once Contracting Officer Ellis learned of SFA’s decision, she sent an email to Place to “confirm[ ]” that Place had “indicated that [she] understood that the government did not direct the removal of SFA’s employee” and that SFA had performed its “own investigation and determined that removal was appropriate.” The Coast Guard thus had every reason to believe that SFA provided Shirvinski with adequate procedures beforе removing him from the Deepwater Project.
In fact, this was appellant’s consistent position until the district court dismissed SFA’s successor from the suit. In his initial complaint, Shirvinski alleged that there “was no doubt ... that SFA was the ultimate decision maker, whereas the Coast Guard had merely requested some form of unspecified ‘corrective action.’ ” Shirvinski similarly asserted in his first amended complaint that the “Coast Guard did not intend its email to be dispositive,” but instead “communicated to SFA that it was not directing Mr. Shirvinski’s removal.” (emphasis in original). But as soon as SFA’s successor was dismissed from the suit, Shirvinski changed his story. In his second amended complaint, he contended that the Coast Guard requested his removal and then “attempted to cover up its actions by laying groundwоrk to claim that the decision to terminate [him] originated from SFA.” This strategic shift in narratives only undermines the credibility of his present claim.
The record is thus replete with evidence that the Coast Guard never requested Shirvinski’s immediate removal but instead expected SFA to investigate the allegations. The district court nevertheless refused to grant summary judgment on this basis largely because Lieutenant Armstrong had asked Lieutenant Commander Gero to remove Shirvinski from Deepwater and then claimed credit for his removal in a later email. The problem with this analysis is that Armstrong lacked authority to order SFA to remove one of its subcontractors on behalf of the Coast Guard. That power was instead vested in Contracting Officer Ellis, who had notified SFA early on that she was “the Contracting Officer responsible for the contract” and that except for technical issues, SFA *319 should “contact [her] ... on all other matters pertaining to the contract.”
Thus, even though Lieutenant Armstrong sought Shirvinski’s removal, the ultimate decision was not his to make. Unless appellant can provide evidence that Contracting Officer Ellis asked SFA to remove him, he cannot prove that the Coast Guard was responsible. As MISC’s Captain Ryan observed, in the field of government contracts, “if the statement [did] not come from the contracting officer ... it didn’t happen.” Appellant’s failure to provide evidence that Ellis requested his removal requires the dismissal of his procedural due process claim.
In sum, we cannot find fault with the Coast Guard’s conduct in this case. It neither provided “significant encouragement” to nor “exercised coercive power” over SFA in that contractor’s decision to order the removal of Shirvinski.
See Blum,
We cannot casually sweep the Coast Guard into every interaction between two privately contracting parties. Shirvinski was not a government employee. ■ He had nо contractual relationship with the Coast Guard either. To seek to affix responsibility here on the Coast Guard would not only expand the scope of state action, but burden the government contracting process with additional transaction costs. For “the mere fact that state áction sets in motion a chain of events that ultimately leads to loss of a plaintiffs protected interest does not of itself establish that there has been a ‘deprivation by state action’ in the constitutional sense.”
Stone,
III.
We now turn to Shirvinski’s state tort claims against Booz Allen. On appeal, he pursues three business tort actions against Booz Allen under Virginia law — common law civil conspiracy, statutory conspiracy, and tortious interference with prospective economic advantage — for its alleged involvement in removing him from the Deep-water Project. As the district court found, however, “there is no evidence that Booz Allen had any interactions with MISC or SFA” or “participated in the Coast Guard’s decision” to contact SFA or even “requested that the Coast Guard terminate Shirvinski’s involvement” in Deepwater. To shore up his claims, Shirvinski contends that Booz Allen, primarily through its employee Vik Singh, worked with Coast *320 Guard civilian employee Stephen Hoshowsky to remove him from Deepwater by spreading defamatory allegations. This argument fails in all three of its forms.
A.
jYe first address Shirvinski’s civil conspiracy claim under Virginia common law. To succeed, appellant must show that “two or more persons combined to accomplish, by some concerted action, some criminal or unlawful purpose or some lawful purpose by a criminal or unlawful means.”
Commercial Bus. Sys., Inc. v. BellSouth Servs., Inc.,
We do not agree. Shirvinski offers nothing more than sheer speculation to support this claim. As he admitted in his deposition, he has no direct evidence that Singh either “played any role in any part of the drafting of’ or “had seen” the August 6 email prior to receiving it that afternoon. Shirvinski consequently attempts to build his case through pure inferencе. He first relies on the fact that on August 6, Hoshowsky and Singh conferred sometime between 10:27 a.m. — when Singh sent an email to Hoshowsky stating that “Adam is going all over the place without telling us----I need to talk to you” — and 2:03 p.m. — when Hoshowsky sent out the allegedly defamatory email. But that sequence of events says nothing about whether they agreed to draft that email during the conversation. In fact, Singh and Hoshowsky each testified in their depositions that they did not discuss this email or its contents before it was sent.
Shirvinski also contends that correspondence between Singh and Hoshowsky a few hours after the transmission of the allegedly defamatory email indicates Singh’s involvement in the drafting process. As appellant observes, Hoshowsky emailed Singh at 5:15 p.m. to inquire whether Coast Guard officials had seen his earlier email and Singh soon replied with an update about its impact. In his request, Hoshowsky also noted the possibility of having “one more thing to add to the list of ‘Issues with Adam.’” Shirvinski believes this proves that the two men had prepared the list of allegations contained in Hoshowsky’s afternoon email. But discussing the impact of an email does not prove authorship. Nor does Hoshowsky’s reference to a “list of ‘Issues with Adam’ ” demonstrate that Singh was responsible for the list’s creation.
In short, the only way we could conclude that Singh helped draft Hoshowsky’s email is “through mere speculation or the building of one inference upon another,” both of which are insufficient justifications for prоceeding to trial.
Othentec Ltd. v. Phelan,
B.
Shirvinski’s statutory conspiracy claim fares no better. Under Virginia’s business conspiracy statute, injured parties can obtain treble damages against “[a]ny two or more persons who combine, associate, agree, mutually undertake or concert together for the purpose of ... willfully and maliciously injuring another in his reputation, trade, business or profession by any means whatever.” Va.Code Ann. §§ 18.2-499-.2-500. Appellant’s claim under this statute falters on multiple grounds.
To start, as with common law civil conspiracy, this statute requires proof “that the defendants have combined ... to accomplish some purpose, not in itself criminal or unlawful, by criminal or unlawful means.”
Potomac Valve & Fitting Inc. v. Crawford, Fitting Co.,
Appellant also cannot demonstrate an injury to a business interest. Despite its broad language, it is well-settled that this statute applies only to injuries “to business and property interests, not to personal or employment interests.”
Andrews v. Ring,
C.
Finally, Shirvinski challenges the district court’s grant of summary judgment on his claim for tortious interference with prospective economic advantage. To succeed on this action under Virginia law, Shirvinski must at a minimum prove that Singh “employed
improper
methods” in interfering with his business expectancy.
See Duggin v. Adams,
Appellant appears to forget that liability for this sort of tortious interference is not casually triggered. Interference involves improper methods “if it is illegal, independently tortious, or violates
*322
an established standard of trade or profession.”
Dunn, McCormack & MacPherson v. Connolly,
As previously discussed, there is no evidence indicating that Singh triggered Shirvinski’s removal through any illegal or independently tortious activities. It is important to keep in mind that Singh simply agreed with a co-worker’s assessment that another contractor should be terminated based on their shared perception that he was acting outside the scope of authority. While Shirvinski may be frustrated over his coworkers’ conclusion, that does not give him the right to hold them liable in tort. This cause of action provides redress for acts akin to “violence, threats or intimidation, bribery, [or] unfounded litigation,”
Duggin,
For us to expand liability for tortious interference — or conspiracy for that matter — to encompass Singh’s conduct would work inestimable damage to public-private partnerships. The effective execution of a government contract depends upon candor and teamwork between public and private employees. To penalize Singh’s actions here would render unlawful unpleasant but necessary communications between government employees and contractors over problems their coworkers were causing in the workplace. Artfully pled business tort actions can threaten valuable speech just as much as defamation claims can. “Authority [and] common sense ... dictate that if [a] letter is privileged against suit for defamation, it must also be protected in an action for interference with business.”
McLaughlin v. Copeland,
IV.
In the end, Shirvinski’s case involves both the wrong defendants and the wrong claims. Overlooking the most obvious parties, he goes after the most peripheral. And rather than pursue ordinary common law remedies, he spins the termination of a private at-will consulting agreement into a case involving conspiracy, treble damages, and constitutional guarantees. But plaintiff may not fashion such an extraordinary lawsuit out of the ordinary happenings of life. The damage to communications in the government contracting process and to valuable public-private partnerships this action would cause has been amply set forth in prior Supreme Court decisions as *323 well as our own precedent and that of the Virginia Supreme Court. We shall affirm the judgment of the district court.
AFFIRMED
Notes
Shirvinski had filed his first amended complaint a few months after the case began.
