OPINION
This сase is before the court on defendant’s Motion to Dismiss, pursuant to RUSCC 12(b)(1), for lack of subject matter jurisdiction. Defendant contends that plaintiff failed to properly certify its claim to the contracting officer before filing in this court, in accordance with the requirements of the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613 (1988). Plaintiff’s Reply alleges that Morgan C. Mun-ford, Shirley Construction Corporation’s Chief Estimator, properly certified the claim on behalf of the corporation. For the reasons stated more fully below, plaintiff’s complaint should be dismissed.
BACKGROUND
There is no dispute as to the relevant facts. In plaintiff’s Reply to Defendant’s Motiоn to Dismiss, plaintiff stated that it “concurs generally with the Statement of the Case as set forth in the Defendant’s brief, filed previously.”
On September 14, 1988, plaintiff, Shirley Construction Corporation entered into a contract with the United States Department of the Navy. The contract called for the construction of Amphibiоus and Sealift Support Operations Facilities at the Naval Amphibious Base, Little Creek, Virginia Beach, Virginia, at a cost of $9,174,341.42, with a contract completion date of September 19, 1990. The contract was obtained through the use of a sealed bid, signed by Jack D. Smith, Vice President of Shirley Construction Corporаtion.
On February 14, 1989, David S. Baird, project manager for Shirley Construction, notified the Resident Officer in Charge of Construction (Resident Officer) that a mistake had been made by one of the subcontractors and expressed his desire to file a claim for the difference between the misquoted bid and the amount it would cost to do the work. In a letter dated March 10, 1989, the Resident Officer requested additional information from Shirley Construction, including plaintiff’s original worksheets, the subcontractor’s bid quotations, certifications by the bidder that the bid sheets were the originals and any other evidence which could help establish the mistake. On March 27, 1989, Morgаn C. Munford replied with the requested information. On April 25, 1989, the contracting officer specifically requested the dollar amount of the alleged bid error and notified Shirley Construction of the certification requirement included in 41 U.S.C. § 605(c)(1).
On June 29, 1990, plaintiff filed its complaint in the United States Claims Court, pursuant to 41 U.S.C. § 609(a)(1),
DISCUSSION
The issue before this court is whether Morgan C. Munford, Shirley Construction’s Chief Estimator, was an appropriate person, under the applicable statute and regulations, to certify the plaintiff’s claim.
The pertinent section of the CDA, as implemented by 48 C.F.R. § 33.207, states that a claim in excess of $50,000 shall be accompanied by a certification in accordance with the regulation. The implementing regulation defines two categories of people who can legally certify a claim on behalf of a corporate contractor. The first is a “senior company official in charge at the contractor’s plant or location involved.” 48 C.F.R. § 33.207(c)(2)(i). The other authorized person under the Act is “an officer or general partner of the contractor having overall responsibility for the conduct of the contractor’s affairs.” 48 C.F.R. § 33.-207(c)(2)(h).
The certification requirement was enacted for the purpose of holding contractors personally liable for fraudulent claims. See Shelly & Loy v. United States,
[r]equire as a matter of law that prior to evaluation of any claim, the contractor must submit to the Government a certificate signed by a senior responsible contractor official, which states that the claim and its supporting data are current, complete and accurate. In other words, you put the contractor in the same position as our working man, the income tax payer who must certify his tax return.
Id. at 21. Admiral Rickover contended that subjecting contractors to financial risk would greatly deter the submission of false or inflated claims. See Paul E. Lehman, Inc. v. United States, 230 Ct.Cl. 11, 15,
The court’s subject matter jurisdiction in government contract cases is, in part, defined by whether or not the certification is validly exеcuted under this regulation. See National Surety Corp. v. United States,
The plaintiff asks this court to make a ruling that would proclaim the certification requirement as having been too stringently interpreted. In National Surety, however, the court held that “while concern may be raised that the certification requirement is drawn too narrowly, the Federal Circuit has directed that the regulation be applied as written.” National Surety,
To support its proposition that the government’s interpretation of the certification requirement is overly restrictive, plaintiff cites to Judge Plager in Grumman,
Although as a judge of the United States Claims Court, I find mysеlf bound by the precedent currently in force, and squarely on point on the issue of certification raised in the instant case, I am in total agreement with the language of the dissent in Grumman. I believe that Judge Plager and his colleagues are correct that the purpose of the certification requirement is to ensure that a claim is certified by a company official “able to speak for and bind the company regarding the claim.” Grumman,
This court and other judicial bodies spend far too much valuable time hearing motions to dismiss, brought by the government to challenge jurisdiction in government con
The public policy purpose of the statute to hold contractors who do business with the government personally accountable and liable for fraudulent claims, and thereby, also to discourage such claims from being filed, can be achieved without the corporate micro-management which is the result of the current case law. Moreover, this same purpose could be achieved if the courts were to follow Judge Plаger’s suggestion at the end of his dissent that failure to certify should not be considered jurisdictional. Grumman,
In cases involving whether or not a claim was properly certified, the court must look to the specific facts of the case before it and apply the applicable statute and regulations to those facts. The CDA statute implementing regulations provide for two categories of persons authorized to execute certification for corporation. In the instant case, the certification would have been valid if Mr. Munford had been a “senior company official in charge at the contractor’s plant or location involved,” 48 C.F.R. § 33.207(c)(2)(i), or had been an “officer or general partner оf the contractor having overall responsibility for the conduct of the contractor’s affairs,” 48 C.F.R. § 33.207(c)(2)(ii), at the time he signed the certification.
The location of the primary contract activity at issue here was the Virginia Beach Naval Base. There is no evidence in the record that Mr. Munford was “in charge” or even regularly present at the job site. See National Surety,
Thе only hint of Mr. Munford’s involvement with this contract is a general job description acknowledging that Shirley Construction allows Mr. Munford to certify claims and bind the contractor. Plaintiff argues that since the corporate hierarchy of Shirley Construction authorized Mr. Munford to certify claims, the court should not construe the aрplicable statute and regulations so as to allow the government to dictate Shirley Construction’s internal management and decide who is authorized to sign the certification on plaintiff’s behalf.
This argument must be rejected, as it was in Ball. In Ball, supra, Mr. Meeks, the “Chief Cost Engineer” had corporate authority to certify claims. The court in Ball, holding the certificatiоn in that case invalid, stated that the test was “not
Mr. Munford’s certification could also have been valid if he had been an “officer or general partner of the Contractor having overall responsibility for the conduct of the Contractor’s affairs,” at the time he signed the certification. 48 C.F.R. § 33.-207(c)(2)®). Plaintiff concedes that Mr. Munford does not meet this tеst. The answer to interrogatory 5A, signed by Mr. Munford, attached as an Appendix to defendant’s Motion to Dismiss, and not disputed by the plaintiff, states that Mr. Mun-ford is the most senior employee who is not a corporate officer.
CONCLUSION
In sum, under the case law, whether the corporation allows, or even prefers, Mr. Munford to сertify claims, unfortunately, is irrelevant. Under current, binding interpretations of the applicable, statutory and regulatory provisions, he did not have the authority to certify a claim. The attempt at certification by Mr. Munford was invalid. Defendant’s Motion to Dismiss is, hereby, GRANTED.
IT IS SO ORDERED.
Notes
. 41 U.S.C. § 605(c)(1) states: “For claims of more than 550,000, the contractоr shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.”
. The word "certified" with the quotation marks appears In the Statement of the Case in defendant’s Motion to Dismiss as follows: "By letter to the Contracting Officer of May 2, 1989, Mr. Munford ‘certified’ Shirley Construction's claim, and stated the amount claimed was $74,719.” Presumably, the defendant was not conceding the case at bar by this sentence, but rather was using shorthand language only to describe the May 2, 1989 letter.
. 41 U.S.C. § 609(a)(1) states that a contractor, instead of appealing to the Board of Contract Appeals, may bring an action directly in the United States Claims Court.
. 48 C.F.R. § 33.201 (1990) defines a claim as a "... written demand or written assertion by one of the contracting pаrties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.” 48 C.F.R. § 33.201 (1990).
. This court also notes that already in 1983, the Administrative Conference of the United States (ACUS), in their Annual Report, issued Recommendation 83-1, supported by a Background Report prepared by Thomas J. Madden, Esq., for ACUS, which suggested that Congress should amend the CDA to allow a certification "to be made or amended at any point up to the issuance of their [the contracting officer, the Board of Contract Appeals, or the Claims Court] respective final decisions of the claim____”
