Shihab & Associates Co., L.P.A. v. Ohio Department of TransportationShihab & Associates Co., L.P.A. v. Ohio Department of Transportation
{¶ 1} Relator-appellant and cross-appellee, Shihab & Associates Co., L.P.A., appeals from a judgment of the Franklin County Court of Common Pleas adopting a magistrate’s decision that (1) awarded attorney fees to respondentappellee and cross-appellant, Ohio Department of Transportation (“ODOT”), arising from relator’s allegedly frivolous conduct, and (2) denied relator’s cross-
{¶ 2} On April 4, 2003, relator submitted to ODOT two public records requests, pursuant to
{¶ 3} Between April 16, 2003 and April 18, 2003, relator received documents from ODOT related to its April 4, 2003 requests. Believing that ODOT had failed to produce all of the documents requested in relator’s initial request, relator, on April 17, 2003, filed a mandamus action against ODOT seeking to compel production of the remaining documents. On April 18, 2003, ODOT sent a letter to relator acknowledging its receipt of relator’s April 8, 2003 public records request and stating that ODOT would produce the documents within a reasonable amount of time.
{¶ 4} On April 24, 2003, ODOT forwarded to relator documents responsive to relator’s April 8, 2003 request. On that same date, ODOT sent a letter to relator stating that ODOT had fully complied with relator’s requests, rendering the mandamus action moot. ODOT requested that relator dismiss the mandamus action and warned that continued prosecution of the action constituted frivolous conduct under
{¶ 5} Relator did not dismiss the action but continued to demand further production of documents. According to relator, in seven requests to ODOT in 2000 and 2001 that were worded identically to the requests at issue, ODOT produced so-called “preliminary” right-of-way plans in addition to “final” right of way plans. Expecting, as in the past, to receive the “preliminary” plans, relator sent a May 13, 2003 letter to ODOT stating its entitlement to those documents.
{¶ 6} Stephanie McCloud, ODOT’s deputy chief legal counsel at the time relator submitted the 2000-2001 requests, testified that she decided to provide “preliminary” right-of-way plans even though she may not have been legally required to do so. At the time of the requests at issue in this case, the then current deputy chief legal counsel decided “preliminary” right-of-way plans did not have to be produced. Nothing in the record indicates ODOT advised relator of the policy change.
{¶ 7} On May 21, 2003, ODOT filed a motion for summary judgment but also sought a protective order regarding subpoenas directed to ODOT employees by
{¶ 8} On March 17, 2005, the magistrate issued a decision finding that relator’s mandamus action was rendered moot when ODOT’s April 24, 2003 letter informed relator that ODOT had produced all responsive documents. Although the magistrate concluded that relator’s mandamus action was not frivolous at the time it was filed, the magistrate also concluded that relator’s continuing to prosecute the action after April 24, 2003, was not warranted under existing law and was not supported by a good-faith argument for an extension, modification, or reversal of existing law. The magistrate thus awarded attorney fees to ODOT pursuant to
{¶ 9} On November 4, 2005, the trial court adopted the magistrate’s decision, despite relator’s objections, filed on March 31, 2005 and September 22, 2005. The trial court determined that relator’s objections were not specific or sufficiently particular as required by former
{¶ 10} Relator appeals, assigning the following six errors:
Assignment of Error I: The trial court erred as a matter of law and abused its discretion in holding that Shihab & Associates Co., LPA’s objections did not satisfy the requirements of Civil Rule 53(B); thus, the trial court erred by not adjudicating Shihab & Associates’ objections on the merits.
Assignment of Error II: The trial court erred as a matter of law, abused its discretion, and its decision is against the manifest weight of the evidence in upholding the magistrate’s decision that S & A’s request for “right of way-plans” did not encompass “preliminary right of way plans.”
Assignment of Error III: The trial court erred as a matter of law, abused its discretion, and its decision is against the manifest weight of the evidence in upholding the magistrate’s determination that ODOT had produced all documents responsive to relator’s public records request as of April 24, 2003.
Assignment of Error IV: The trial court erred as a matter of law, abused its discretion, and its decision is against the manifest weight of the evidence in holding a requestor under the public records act has no right to question the government’s assertion that all responsive documents have been produced, and has no right to question or challenge the government’s interpretation of what documents fall within the scope of the request.
Assignment of Error V: The trial court erred as a matter of law, abused its discretion, and its decision is against the manifest weight of the evidence in affirming the magistrate’s decision finding frivolous conduct in Shihab & Associates’ actions under O.R.C. § 2323.51.
Assignment of Error VI: The trial court erred as a matter of law in denying S & A’s cross motion for attorney fees, including that it abused its discretion in excluding S & A’s evidence of ODOT’s bias and ill will which were relevant to the requirements of O.R.C., Section 2323.51.
{¶ 11} ODOT cross-appeals, assigning the following error:
Having correctly found that Relator-Appellant engaged in frivolous conduct and that sanctions were appropriate underR.C. 2323.51 , the trial court abused its discretion by limiting the amount of the award to the attorneys fees incurred by ODOT prior to the date of the hearing on Respondent-Cross Appellant’s Motion for Sanctions.
{¶ 12} Relator’s first assignment of error contends that the trial court erred in not adjudicating relator’s objections and in failing to conduct an independent review of the magistrate’s decision.
{¶ 13} A magistrate’s decision is effective when adopted by the court. Former
{¶ 14} Former
{¶ 15} Objections that merely reiterate arguments already presented and ruled upon do not meet the standards required by former
{¶ 16} Here, the magistrate’s findings of fact Nos. 4, 6, 8, and 9 state that ODOT produced all documents in its possession that were responsive to relator’s requests. Based on those factual findings, the magistrate’s conclusion of law No. 5 states that relator’s mandamus action was frivolous after, but not before, the April 24, 2003 letter ODOT sent to relator informing relator that ODOT had produced all responsive documents. With conclusions of law Nos. 8 and 9, the magistrate denied relator’s cross-motion for sanctions against ODOT.
{¶ 17} Relator submitted two sets of objections, on March 31, 2005, and September 22, 2005. The first set objected to the magistrate’s decision denying relator’s cross-motion for sanctions against ODOT. Relator contended that the decision was contrary to law and against the manifest weight of the evidence. In support of relator’s objection, relator stated that (1) the magistrate did not mention letters relator wrote to ODOT, informing ODOT that relator had not
{¶ 18} In the second set of objections, relator objected to the magistrate’s decision granting ODOT’s motion for sanctions and again objected to the magistrate’s determination to deny relator’s cross-motion for sanctions. The first heading stated that under Ohio law, relator’s action in mandamus was warranted beyond April 24, 2003, because relator, based on ODOT’s past actions in producing preliminary plans, had reasonable cause to believe that relator’s current requests would result in the production of preliminary plans. By way of supporting argument, relator contended that, although the magistrate’s determined right of way was a “term of art” and did not include preliminary plans, the conclusion was immaterial in the context of the facts. Relator further contended that the magistrate wrongly deemed ODOT’s April 24, 2003 letter to be conclusive in light of ODOT’s responses to prior requests. As relator further pointed out, relator’s maintaining the mandamus action was not frivolous because ODOT on June 20, 2003, produced the preliminary right-of-way plans, as it had done in the past.
{¶ 19} Under the second heading, in sections (A) and (B), relator objected that the magistrate’s decision finding frivolous conduct under
{¶ 20} While relator’s objections are not the paradigm of “best” objections, they are sufficiently specific and stated with sufficient particularity to meet the requirements of
{¶ 22} Having sustained relator’s first assignment of error, rendering moot the remaining assignments of error, we reverse the judgment of the trial court and remand this matter to the trial court to consider relator’s objections and adopt, reject, or modify the magistrate’s decision accordingly.
Judgment reversed and cause remanded.