Shieldalloy Metallurgical Corp. v. Nuclear Regulatory CommissionShieldalloy Metallurgical Corp. v. Nuclear Regulatory Commission
Lead Opinion
Opinion for the Court filed by Senior Circuit Judge WILLIAMS.
Opinion concurring in part and dissenting in part filed by Circuit Judge ROGERS.
This case arises from our remand in Shieldalloy Metallurgical Corp. v. NRC,
The order now under review, Shieldalloy Metallurgical Corp., CLI-11-12, 74 NRC-(Oct. 12, 2011) (“Order”), presents that issue and several others. All stem from the interaction between the NRC’s regular decommissioning process and a statutory provision (§ 2021 of the Atomic Energy Act,
* * *
Petitioner Shieldalloy Metallurgical Corporation is an industrial company that manufactured metal alloys in Newfield, New Jersey between 1955 and 1998. Its manufacturing process generated radioactive byproducts, which the company held at the Newfield facility under license from the NRC. In the early 1990s, Shieldalloy began consulting with the NRC on the development of a proposal to decommission the facility and dispose of its radioactive materials on-site. It proposed that the disposal would be “restricted,” an NRC term of art requiring special conditions designed to minimize the risks to public health and safety. Restricted disposal- is in contrast to “unrestricted,” under which remediation and reduction of radiation levels have proceeded to the point where there is no need for limits on public access to the disposal site. See
The NRC rejected the 2002 plan as technically deficient. After further consultations with NRC staff, Shieldalloy submitted a second, revised plan in 2005. The NRC rejected that plan, too, with comments. In 2006, Shieldalloy submitted a third plan, which responded to the NRC’s comments, as well as to NRC guidance on decommissioning of licensed facilities issued earlier in 2006. The NRC accepted this third plan for the purposes of technical review, but still sought further clarification from Shieldalloy on various aspects. In the summer of 2009, Shieldalloy submit
In 2008, while the NRC was reviewing the 2006 plan, New Jersey applied for a transfer of regulatory authority over instate nuclear materials, pursuant to
Fearing that New Jersey would require it to abandon its plans for on-site disposal and pursue a more expensive off-site alternative (again, in NRC parlance, “unrestricted”), Shieldalloy appealed to this court. We agreed with the company in part and remanded the case to the agency. See Shieldalloy Metallurgical Corp.,
Existing NRC Licenses and Pending Applications. In effecting the discontinuance of jurisdiction, appropriate arrangements will be made ... to ensure that there will be no interference with or interruption of ... the processing of license applications, by reason of the transfer.
46 Fed.Reg. 7540, 7543 (Jan. 23, 1981). Shieldalloy had argued that as its license application had already been years in processing, transfer to New Jersey would clearly interrupt the process. See Shiel-dalloy,
To this twofold claim, the NRC offered a twofold response. As to the risk of an interruption in seeming violation of criterion 25, it expressed confidence that there would be a “smooth transition” in the processing of pending licensing actions (including decommissioning applications) because New Jersey’s regulatory scheme recognized existing NRC licenses and would continue “any licensing actions that are in progress.” Id. at 494 (quotations removed). As to Shieldalloy’s preferred solution — excepting Newfield from the transfer — the NRC claimed that the legislative history of
Shieldalloy’s initial suit raised a further claim, which we noted but did not address because Shieldalloy had not raised it sufficiently with the Commission. See
The core of Shieldalloy’s ALARA claim was that the New Jersey decommissioning regime, unlike the NRC’s, requires exhumation and off-site disposal of radioactive materials even where that course of action would expose the public to higher doses of radiation than on-site disposal. Thus, Shieldalloy contended, “while New Jersey’s standards may be more stringent, they are actually less safe.”
On remand, the NRC afforded Shieldal-loy a “fresh opportunity” to comment on the transfer agreement in order to “assure a full airing of the matter.” Order at 6-7. In its submission, Shieldalloy of course pursued the issues occasioning the remand, but it also pursued the contention that the New Jersey rules were more stringent but less safe.
The NRC’s Order rejected Shieldalloy’s objections and reinstated the transfer agreement. Shieldalloy again petitions us for review. We find that, on its second attempt, the agency adequately addressed Shieldalloy’s claims arising out of criterion 25 and the parties’ conflicting interpretations of
We begin with the question of concurrent federal and state jurisdiction under
Whether
In its Order, the Commission reconciles these two provisions by reading
In other words, the NRC saw
Shieldalloy argues that the permissive language found at
There remains Shieldalloy’s argument that the Commission violated criterion 25 by failing to ensure that there would be no interruption in the processing of license applications. Of course, once the Commission has precluded its exercise of
Indeed, if one reads criterion 25 as Shieldalloy contends it should be read, then the NRC in fact should have rejected New Jersey’s application once it determined that a partial transfer was unavailable. The company argues, not unreasonably, that where a regulated entity has engaged in an extensive process of dialogue and collaboration with an agency in pursuit of specific licensing outcome, then a sudden relinquishment of regulatory authority to a different sovereign with a radically different regulatory framework necessarily constitutes “interference with or interruption of’ the processing of its licensing application.
We certainly sympathize with Shieldal-loy’s frustration at having been jilted by the NRC after a decade of dogged courting. But under the extremely narrow standard by which we review an agency’s interpretation of its own regulations, see, e.g., Thomas Jefferson Univ. v. Shalala,
Shieldalloy’s ALARA argument concerns the operation of that principle in the context of a 1997 NRC final rule on the decommissioning of licensed facilities, termed the License Termination Rule (“LTR”).
Under the LTR, a site can be decommissioned for either unrestricted or restricted use.
Section 20.1402 of the LTR sets out the conditions under which a site will be released for unrestricted use on termination of a license. Section 20.1403 does the same for restricted release. Under § 20.1402, a licensee can pursue unrestricted release after reducing residual radiation at the site to “levels that are as low as reasonably achievable (ALARA),” and in any event no greater than 25 millirem (“mrem”). Id. § 20.1402.
In addition to these technical instructions, the LTR requires a licensee seeking restricted release to make what the NRC calls (Order at 41) an initial showing of “eligibility” set out at § 20.1403(a):
A site will be considered acceptable for license termination under restricted conditions if:
(a) The licensee can demonstrate that further reductions in residual radioactivity necessary to comply with the provisions of § 20.1402 would result in net public or environmental harm or were not being made because the residual levels associated with restricted conditions are ALARA Determination of the levels which are ALARA must take into account consideration of any detriments, such as traffic accidents, expected to potentially result from decontamination and waste disposal;
Id. § 20.1403(a) (emphasis added). The NRC characterizes the “net public or environmental” harm test alluded to in § 20.1403(a) as an “abbreviated” form of ALARA that takes into account only a subset of the costs involved in a full ALARA assessment. Order at 25-26; Resp. Br. 13-14 n. 3, 59-60 n. 13. The parties have focused exclusively on the ALARA test, and so shall we.
Shieldalloy argues that the NRC provides for an eligibility test for restricted release predicated on a comparative application of the ALARA principle. More specifically, its response to the Commission’s solicitation of views on remand argued that the Commission’s rules and interpretations allow a licensee to employ restricted release if it would result in a lower radiation exposure than unrestricted release (which necessarily involves a comparison of the two). Joint Appendix (“J.A.”) 712, 714-15; Pet’r Br. at 47. In other words, if we understand Shieldalloy correctly, the proper application of the emphasized language would entail a comparison between restricted and unrestricted release, and the former would win when it yielded lower risks than unrestricted. By contrast, Shieldalloy asserts, New Jersey does not contemplate any form of radiation dose comparison between restricted and unrestricted release, and may require unrestricted release even where restricted release would have been safer. On this analysis, and given the preferences for safety expressed in the statute, the Criteria Document and the Compatibility Guidance Document, Shieldalloy argues that the New Jersey rules are not “compatible” with NRC’s, as required by
In its Order and before us, the NRC rejects outright this reading of § 20.1403(a). It maintains that its regulations “neither explicitly nor implicitly require a comparison between the levels of protection afforded by the unrestricted
As for ALARA, the agency states that the principle’s operation is confined to comparisons of different remediation options of the same class — that is, for comparing two unrestricted-release proposals, or two restricted-release proposals, but never for comparing a restricted release option with an unrestricted one. Order at 40-41. The purpose of what it views as the correct understanding of ALARA, the agency avows, is twofold: First, it serves as a tool for measuring the reductions in radiation levels that it will require below the maxima set out in
With respect to the precise meaning of § 20.1403(a), the agency tells us that the provision requires unrestricted release, except where “remediation to the level of 25 mrem per year for unrestricted release [set forth in § 20.1402] would not be beneficial from a cost standpoint.” Resp. Br. at 55. The agency further asserts that the ALARA principle, as used in § 20.1403(a), is the analytic prism for such a weighing of costs and benefits. Order at 25, 41. As explained in its brief, the NRC sees the role of ALARA in § 20.1403(a) as helping to ascertain whether even the highest radiation levels permissible for unrestricted release under § 20.1402 are attainable in a cost-beneficial manner. Resp. Br. at 59.
We are quite baffled by the NRC’s current interpretation of § 20.1403(a). The agency’s order and its brief do not quote from the provision or make any effort to engage with its text. Instead, they state in bald and conclusory fashion that the regulation does not mean what Shieldalloy says it means. Unlike the NRC, we do not find the meaning of § 20.1403(a) self-evident. Rather, we think that its text neither precludes the reading given to the provision by Shieldalloy nor, at least without exegesis that is completely missing here, supports that proposed by the NRC.
The first sentence of § 20.1403(a) provides that a licensee is eligible for restricted release if it can prove that the remedial measures required of unrestricted release “were not being made because the residual levels associated with restricted conditions are ALARA.”
The language of
Further, the understanding of
Of course, a reading of the emphasized language in the first sentence of
Other NRC regulations and statements pertaining to ALARA only deepen the confusion.
Even harder to square with the NRC’s position are passages of an NRC policy statement called NUREG-1757, which the agency describes as a “comprehensive NRC guidance document” on license ter-
Appendix N of this volume discusses five different possible benefits.... In most comparisons between alternatives in the same class (e.g., both alternatives result in unrestricted release), the only important benefit should be the collective dose averted. In comparisons between restricted and unrestricted release, the other benefits can become important.
NUREG-1757 at 6-3 (emphasis added).
Pursuing this cross-reference to Appendix N, we find the following passage pertaining to the “benefits” side of ALARA’s cost-benefit analysis:
Regulatory Costs Avoided
This benefit usually manifests in ALARA analyses of restricted release versus unrestricted release decommissioning goals.... When evaluating the ability of a licensee’s proposal for restricted release according to 10 CFR [§ ] 20.1403(a), avoiding these costs should be included in the benefits of the unrestricted release decommissioning alternative. These should not be included as costs related to the restricted release.
Id. at N-6 (emphasis added).
These passages do not appear to be the product of inattentive drafting. NRC officials invoked the same concept in a letter they sent Shieldalloy after accepting of the company’s 2006 decommissioning plan for technical review. That letter, entitled “Request for Additional Information” (“RAJ”), warned Shieldalloy that overestimating the cost of unrestricted release “would bias the net harm or ALARA comparison away from the unrestricted use option.” J.A. at 393.
These statements from NUREG-1757 and the RAI can reasonably be read to call for precisely the kind of comparative dose analysis that Shieldalloy claims is contemplated by
Furthermore, if NUREG-1757 and the RAI mean what they appear to mean, the Order’s insistence that the choice between restricted and unrestricted dispositions can never turn on a direct comparison between the two would appear to be the sort of “swerve” from prior policy that requires explanation. Greater Boston Television v. FCC,
The NRC trots out the familiar proposition that deference to an agency’s interpretation of its own rule “is all the more warranted when, as here, the regulation concerns a complex and highly technical regulatory program.” Resp. Br. at 53 (quoting St. Luke’s Hosp. v. Sebelius,
Our dissenting colleague echoes the Commission’s assertions in its Order and in its brief. See Dissent at 387-94. Thus she fully accepts the idea that
Our colleague also suggests that the court has offered “its own interpretation of
We note finally our dissenting colleague’s contention that Shieldalloy did not properly raise its ALARA claim before the Commission. Her conviction appears to turn on Shieldalloy’s failure to (1) engage in an extensive textual analysis of
As to Shieldalloy’s failure to provide a “technical rationale” (a term which neither the Commission nor our colleague has bothered to define), we do not see how that omission hamstrung the Commission’s ability to grasp objections based on the contention that the NRC rules and directives permitted a licensee to choose the least dangerous solution. As the Commission itself observed, its rejection of Shieldalloy’s ALARA claim turned on the company’s “fundamentally inaccurate understanding of our license termination requirements,” Order at 36, and not a flawed engineering analysis. Even assuming otherwise, the reams of technical data Shieldalloy submitted to the Commission in its decommissioning plans, see, e.g., S.A. at 3-127, certainly supplied whatever quantitative detail the Commission might have needed to appreciate Shieldalloy’s position.
For the reasons stated, we again find the NRC’s transfer of authority to New Jersey arbitrary and capricious. We therefore grant Shieldalloy’s petition, vacate the NRC’s transfer of authority, and remand for proceedings consistent with this opinion.
So ordered.
Notes
. Criteria for Guidance of State and NRC in Discontinuance of NRC Regulatory Authority and Assumption Thereof by States Through Agreement, 46 Fed.Reg. 7540 (Jan. 23, 1981), as amended by 46 Fed.Reg. 36,969 (July 16, 1981) and 48 Fed.Reg. 33,376 (July 21, 1983). See Shieldalloy,
. Statement of Principles and Policy for the Agreement State Program; Policy Statement on Adequacy and Compatibility of Agreement State Programs, 62 Fed.Reg. 46,517 (Sept. 3, 1997). See Shieldalloy,
. All mrem references are to increments above background radiation.
Concurrence Opinion
concurring in part and dissenting in part.
I join the court in deferring to the interpretation of the Nuclear Regulatory Commission of its authority under the Atomic Energy Act,
To the extent the court concludes, however, that the NRC’s transfer to New Jersey is arbitrary and capricious, and again remands the case, I respectfully dissent. The court inexplicably excuses Shieldalloy from two fundamental requirements: first, to raise its challenges to agency action with the agency so it has an opportunity to respond, and second, to state its challenges on appeal in more than a skeletal
I.
In remanding the case to the NRC for a second time, the court has concluded that the NRC’s response upon remand fails for lack of clarity. Op. at 373. Indeed, the court cloaks its disposition vacating the transfer of authority to New Jersey in concern that the NRC has somehow jeopardized public safety. See id. Yet the administrative record before the court indicates that any lack of clarity arises not from the NRC’s lack of articulation, or evidence it has failed to protect public safety, but from Shieldalloy’s repeated failure to set forth its arguments with sufficient clarity so that the NRC could respond to them.
When the court initially remanded the case to the NRC, it noted that Shieldalloy had failed to raise in its comments to the NRC that removal of Shieldalloy’s radioactive materials from the Newfield site in New Jersey to a facility in Utah would result in greater harms to public health and the environment than onsite disposal. See Shieldalloy Metallurgical Corp. v. NRC,
The court has long instructed what it reaffirmed in ExxonMobil Oil Corp. v. FERC,
A party must first raise an issue with an agency before seeking judicial review. This requirement serves at least two purposes. It ensures “simple fairness” to the agency and other affected litigants.
It also provides this Court with a record to evaluate complex regulatory issues; after all, the scope of judicial review under the APA would be significantly expanded if courts were to adjudicate administrative action without the benefit of a full airing of the issues before the agency.
Id. at 962 (citations omitted); see also Advocates for Hwy. & Auto Safety v. Fed. Motor Carrier Safety Admin.,
On remand from this court, the NRC “decided to examine anew all of the issues surrounding transfer of the Newfield site to New Jersey and afford Shieldalloy a fresh opportunity to comment on New Jersey’s agreement-state application.” Shiel-dalloy Metallurgical Corp., CLI-11-12, 74 NRC — , Memorandum and Order at 6-7
Further examination of the NRC’s response on remand is discussed in Part II, infra. What is significant at this point is Shieldalloy’s procedural default. On remand the NRC observed:
Despite the open-ended opportunity we provided in this remand proceeding for Shieldalloy to fully articulate its position on this and other issues, it has presented its “comparative dose” position, and its related argument as to ALARA, in summary and conclusory fashion, leaving us largely to guess at the technical rationale and underlying foundation for its position. This is unfortunate, given the highly complex and technical nature of our license termination regulations. While we endeavor to respond fully to Shieldalloy’s comparative dose and related ALARA argument based on our understanding of them, we are mindful of the admonition that “the dialogue between administrative agencies and the public is a two-way street.”
Id. at 35-36 (quoting Northside Sanitary Landfill, Inc. v. Thomas,
The court today is in the same predicament as the NRC on remand as a result of Shieldalloy’s conduct. The court states: “In other words, if we understand Shiel-dalloy correctly, the proper application of the emphasized language [in
Even now, in this second appeal challenging the NRC’s transfer of authority to New Jersey, it is at best doubtful that Shieldalloy has properly presented the issues regarding comparative dose and ALARA. In its opening brief, Shieldalloy contends, in conclusory fashion, leaving the court to guess at its rationale, that “there is a need to compare the radiological doses that would result from the decoinmission-ing of a facility under unrestricted release and restricted release approaches and to apply the ALARA principle to select the option that results in the lowest doses.” Pet’r’s Br. 43. Although not referencing
That aside, on appeal Shieldalloy points for the first time to the NRC’s comprehensive guidance document on decommissioning, NUREG-1757, and to NRC staff requests for additional information purportedly in support of its comparative dose/ALARA contention. Additionally, only in its reply brief does Shieldalloy suggest that the NRC’s explanation of
For purposes of this court’s review, one problem is that identified by the NRC on remand: Shieldalloy failed to provide the NRC with a textual analysis of
II.
All is not lost, however; or at least it should not be. “[E]ndeavor[ing] to respond fully to Shieldalloy’s comparative dose and related ALARA argument based on [its] understanding of them,” Mem. at 35-36, the NRC stated on remand: “Shiel-dalloy apparently construes our license termination regulations as calling for a licensee to compare doses of the restricted-release and unrestricted-release decommissioning options and to choose the option that affords the lowest dose.” Id. at 36 (emphasis added). On appeal, Shieldal-loy does not dispute this interpretation of its position and the NRC addressed the issue comprehensively, providing a detailed and reasoned explanation as to how ALARA is used in the license termination regulations and why New Jersey’s program is compatible with the federal decommissioning standards. Id. at 34-44.
Upon reviewing the NRC’s response on remand, Shieldalloy’s contentions on appeal fail to present grounds upon which the court can conclude that the NRC failed to offer a reasoned explanation of its complex regulatory scheme, see Thomas Jefferson Univ. v. Shalala,
First, the NRC explained that Shiel-dalloy’s apparent argument “is a fundamentally inaccurate understanding of our license termination requirements and appears to lie at the heart of Shieldalloy’s claim that New Jersey’s program is not as protective of the public health and safety as our program with respect to the Newfield site.” Mem. at 36. The NRC noted, citing a 44-page staff re
Second, the NRC explained that the ALARA analysis in its regulation on restricted release,
A.
The NRC provided a reasoned explanation as to why its regulatory scheme does not envision a dose comparison between restricted and unrestricted decommissioning options. See Mem. at 36-39. The NRC explained that its “regulations neither explicitly nor implicitly require a comparison of the levels of protection afforded by the unrestricted and restricted decommissioning options” “because the levels of protection of unrestricted release and restricted release are simply not susceptible to being compared meaningfully.” Id. at 37. In the NRC’s view, dose comparison is not meaningful because “[e]ach option uses significantly different methods to achieve adequate protection and has significantly different risks and uncertainties associated with it.” Id.
The NRC elaborated that restricted release is “far more complex and involves significantly greater uncertainties than off-site disposal,” because it “relies on the sustained effectiveness of institutional controls over a 1000-year compliance period to restrict future access and use to meet the 25 mrem per year dose requirement.” Id. To wit: Engineering controls must perform numerous complex functions; monitoring and maintenance are required; sufficient long-term funding from an independent third party is also required. Id. For this reason, the NRC explained, its stated preference is for unrestricted release. Id. at 39. “Unrestricted release requires the removal of contamination on-site to the extent necessary to comply with the dose criteria of 25 mrem per year and transportation of the contaminated material to an isolated and regulated long-term disposal site.” Id. at 37. Acknowledging that “[sjome uncertainties are inherent in these activities,” id. at 37-38, the NRC explained, however, that they “generally involve!] well-known and quantifiable handling and associated radiological impacts on workers and the public over a short
For restricted use, the NRC explained,
The NRC also addressed Shieldalloy’s dose comparison position on its own terms, pointing out its flawed factual premise. The NRC found, first, that Shieldalloy’s statements — that license termination using onsite disposal for the Newfield site would result in lower doses to the public than offsite disposal — “are inaccurate.” Id. at 34-35. Shieldalloy claimed that this proposition had not been controverted, but the NRC pointed out that insofar as Shieldal-loy’s comparative dose position was “reflected in its proposed 2005 decommissioning plan,” that plan was rejected by NRC staff as not being in compliance with the license termination regulations, and that the NRC staffs request for additional information on Shieldalloy’s proposed 2006 plan likewise indicated rejection of Shiel-dalloy’s comparison approach and identified related technical concerns. Id. at 35.
The NRC found, second, that “Shieldal-loy’s own dose estimates for the Newfield site reflect that it is meaningless to compare the level of protection between unrestricted release and restricted release.” Id. at 38 (emphasis added). Shieldalloy asserted on remand that “terminating the license under restricted conditions by the
B.
The NRC reasonably explained how ALARA functions under its decommissioning regulations. Noting that “Shieldalloy has not set forth or explained the basis for its apparent position,” the NRC concluded, “perhaps it is alluding to our ALARA-based eligibility criterion for restricted release.” Mem. at 41 (emphasis added). Further noting “its submission is hardly clear on this point,” the NRC concluded “Shieldalloy apparently believes that our ALARA principle compels us to compare decommissioning options and to allow a licensee to select the lowest-dose option.” Id. at 40 (emphasis added). The NRC responded: “This is a fundamental misconception of our ALARA principle and appears to be the root of Shieldalloy’s misunderstanding of our approach to license termination.” Id. Indeed, the NRC explained that “the very premise of Shieldal-loy’s position on ALARA — that our license termination rule requires a choice to be made between a higher or lower dose option — is erroneous.” Id.
First, the NRC explained that the ALARA principle, “either as a general regulatory principle or as used in our license termination rule, [does not] incorporate or call for any comparative analysis of doses from restricted and unrestricted release.” Id. at 40. Rather, under the rule, the NRC explained, ALARA has two purposes in license termination: to reduce doses as low as achievable below applicable dose limits (not to “compar[e ] between achievable doses”), and to provide a criterion to limit the use of restricted release. Id. at 40-41. The latter purpose, “effectively, to screen out sites that should be removing contamination to achieve unrestricted use,” the NRC continued, is achieved in section
The ALARA analysis for restricted-release eligibility purposes does not and was never intended to demonstrate whether one decommissioning option affords greater protection than another. In fact, because an ALARA analysis focuses on dose reductions below what we have determined to be necessary for adequate protection of the public health and safety, that analysis does not go to adequate protection at all. A licensee’s demonstration of adequate protection is accomplished, instead, through satisfaction of the dose criteria and other conditions for its chosen decommissioning option.
Id. at 41. Notably ALARA “does not compare or explicitly analyze any of the uncertainties that affect the level of protection afforded by a particular disposal option.” Id. at 42.
Second, the NRC interpreted the ALARA test in
C.
Notwithstanding the NRC’s reasoned explanation of its regulatory scheme and reasonable interpretation of its regulations, including what ALARA is, the court concludes that a remand is required, principally in light of its own textual analysis of
Undeterred by Shieldalloy’s defaults, the court engages in a textual interpretation of
Ordinarily the court will defer to an agency’s reasonable interpretation of its regulations, see Auer,
The NRC’s “comprehensive guidance document” on decommissioning, id. at 24, supports the “exegesis” offered by the NRC. In describing the equation to be used to calculate doses that are ALARA, Appendix N states that “[t]he residual radioactivity level that is ALARA is the concentration ... at which the benefit from removal equals the cost of removal.” NU-REG-1757, Vol. 2, Appendix N at N-10 (Rev.l, Sept. 2006). The calculation of these benefits includes collective doses averted from a given action and the costs include the monetary costs to the licensee. Id. at § 6.3 at 6-3 to 6-4. So understood in light of NUREG-1757, the reference in
Consequently, the confusion the court identifies arising from passages of other NRC regulations and statements is dispelled. Op. 380-82 (citing the definition of ALARA, NUREG-1757, and the staff Request for Additional Information).
Inexplicably the court protests a lack of textual analysis by the NRC and the dissent, Op. at 379, 382, when, as discussed here, in fact the NRC explained, based on the plain text, that
Moreover, even assuming, for purposes of argument, that the NRC’s interpretation of
In sum, the regulatory scheme administered by the NRC is complex, and further explanation is welcome as a general principle, but the issues raised by Shieldalloy have been adequately addressed by the NRC. This is so even though, because Shieldalloy never referred to
. See Criteria for Guidance of States and NRC in Discontinuance of NRC Regulatory Authority and Assumption Thereof by States Through Agreement, 46 Fed.Reg. 7540 (Jan. 23, 1981), as amended by 46 Fed.Reg. 36,969 (July 16, 1981) and 48 Fed.Reg. 33,376 (July 21, 1983); Statement of Principles and Policy for the Agreement State Program; Policy Statement on Adequacy and Compatibility of Agreement State Programs, 62 Fed.Reg. 46,517 (Sept. 3, 1997) (the latter, "1997 Policy Statement”).
.
The licensee can demonstrate that farther reductions in residual radioactivity necessary to comply with the provisions of§ 20.1402 [standards for unrestricted release] would result in net public or environmental harm or were not being made because the residual levels associated with restricted conditions are ALARA. Determi*386 nation of the levels which are ALARA must take into account consideration of any detriments, such as traffic accidents, expected to potentially result from decontamination and waste disposal.
. S ection 20.1402 provides:
A site will be considered acceptable for unrestricted use if the residual radioactivity that is distinguishable from background radiation results in a TEDE [total effective dose equivalent] to an average member of the critical group that does not exceed 25 mrem ... per year, including that from groundwater sources of drinking water, and that the residual radioactivity has been reduced to levels that are as low as reasonably achievable (ALARA). Determination of the levels which are ALARA must take into account consideration of any detriments, such as deaths from transportation accidents, expected to potentially result from decontamination and waste disposal.
. Pursuant to the 1997 Policy Statement, supra note 1, Agreement States may adopt programs that provide a level of protection that is "equivalent to, or greater than, the level provided by the NRC program.” 62 Fed.Reg. at 46,524. Category C elements of Agreement State programs are required "in order to avoid conflicts, duplications, gaps, or other conditions that would jeopardize an orderly pattern in the regulation of agreement material on a nationwide basis." Id.; see also Radiological Criteria, 62 Fed.Reg. at 39,079-80, 39,086.
. Neither the passages in NUREG-1757 nor the staff Request for Additional Information support Shieldalloy's position that