Shieldalloy Metallurgical Corp. v. Nuclear Regulatory CommissionShieldalloy Metallurgical Corp. v. Nuclear Regulatory Commission
Opinion for the Court filed by Senior Circuit Judge WILLIAMS.
Under § 274 of the Atomic Energy Act of 1954 as amended, Pub.L. 86-373, 73 Stat. 688 (1959), codified at
From 1955 to 1998, Shieldalloy manufactured metal alloys at its Newfield, New Jersey facility. Shieldalloy’s manufacturing process generated radioactive byproducts in the form of slag and baghouse dust; the firm held these materials on site under a license from the NRC. In the early 1990s, Shieldalloy took the first steps toward decommissioning the Newfield facility. Based on discussions with the NRC staff, it developed a conceptual plan for on-site disposal of the materials under conditions restricting the site’s use. At the same time, the NRC developed, and in 1997 published, a final rule on the decommissioning of licensed facilities.
In October 2008 New Jersey applied for a transfer of regulatory authority over instate nuclear materials from the NRC, pursuant to
To evaluate the compatibility of the state and federal regulatory programs, the NRC considers thirty-six criteria that it enumerated in a policy statement that we will call the “Criteria Document.”
1
It further clarified its evaluation process in a later policy statement, the “Compatibility Guidance Document,”
2
which interprets the compatibility requirement as mandating that the state program must “not create conflicts, duplications, gaps, or other
*492
conditions that would jeopardize an orderly pattern in the regulation of agreement material on a nationwide basis.”
After finding New Jersey’s program adequate and compatible with the federal program, the NRC published notice of the proposed agreement in the Federal Register and sought comments from the public, pursuant to its statutory obligation under
In reviewing agency action that is alleged to be arbitrary or capricious, we are “not to substitute [our] judgment for that of the agency,” but we must ensure that the agency has “examine[d] the relevant data and articulatefd] a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made.’ ”
Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co.,
Item 25 of the Criteria Document states in relevant part,
Existing NRC Licenses and Pending Applications. In effecting the discontinuance of jurisdiction, appropriate arrangements will be made by NRC and the State to ensure that there will be no interference with or interruption of licensed activities or the processing of license applications, by reason of the transfer.
46 Fed.Reg. 7540, 7543.
In its comments to the NRC, Shieldalloy argued that New Jersey had not attempted to make appropriate arrangements to guarantee a smooth transition for the pending Shieldalloy decommissioning plan; in fact, New Jersey had challenged Shieldalloy’s decommissioning process at every stage. This resistance, Shieldalloy contended, was incompatible with criterion 25’s commitment to the uninterrupted “processing of license applications.” Shieldalloy Comment Letter at 9-10. In response, the NRC staff aptly noted that New Jersey is entitled to take part in hearings on licensing actions and to petition for rulemaking, and that the state’s exercises of those rights did not in themselves indicate the New Jersey plan’s incompatibility with the federal regime under criterion 25. NRC Staff Comments at 8.
But Shieldalloy also invoked criterion 25 in support of its separate contention that, even if the NRC entered a transfer agreement with New Jersey, it might exclude the Newfield site from the transfer. Shieldalloy Comment Letter at 11-12. In that context Shieldalloy went well beyond New Jersey’s conduct in the NRC decommissioning proceeding. It pointed to the time and expense that Shieldalloy devoted to working with the NRC staff to develop a plan for safely decommissioning the site (over $2 million in 2007-2009 alone), which it implied would be largely wasted under New Jersey’s different approach. Id.
In response, the NRC staff noted that the “legislative history for [
These responses were inapposite and woefully incomplete. As to
In the late 1990s, Oklahoma submitted a draft transfer application that excluded five specific sites undergoing decommissioning. Id. at 1-2. Though the NRC staff recognized that the NRC had entered into limited agreements in the past, it rejected Oklahoma’s request as inconsistent with the statutory provisions, because the exclusion of single licensees, “absent an identified subcategory of material,” might create “an unwieldy and confusing pattern of regulation.” Id. at 3. The NRC staff recommended rejecting Oklahoma’s proposal. At the same time, however, it offered guidelines for considering future proposals for limited agreements:
[Rjequests for limited Agreements would have to identify discrete categories of material or classes of licensed activity that (1) can be reserved to NRC authority without undue confusion to the regulated community or burden to NRC resources, and (2) can be applied logically, and consistently to existing and future licensees over time. Under this approach, NRC would not reserve authority over a single license unless that licensee clearly constituted a single class of activity or category of material meeting the two criteria described above.
Id. at 5-6. The NRC approved both of the staff recommendations. 7 Two years later, in 1999, Oklahoma proposed a limited agreement that excluded a subcategory of materials — a category that aligned closely with the sites Oklahoma had desired to exclude in its site-specific proposal two years earlier. Applying the previously developed factors for limited agreements, the NRC staff this time recommended approval of the limited transfer. 8 The Oklahoma case is strikingly relevant to Shieldalloy’s situation because Shieldalloy argues, and the NRC does not dispute, that its radioactive wastes constitute the sole New Jersey example of a discrete subcategory of materials.
Other elements of the NRC’s response as to criterion 25 were equally dismissive. The NRC staff said that New Jersey’s regulatory scheme recognized existing NRC licenses and would continue “any licensing actions that are in progress” at the time of the agreement. NRC Staff Comments at 8. The NRC thus concluded that there would be a “smooth transition” and that New Jersey would make decisions on pending licensing actions. Id.
This hardly answered Shieldalloy’s contention that its license termination process would be disrupted and that no appropriate arrangements had been made. Although the fact of New Jersey’s participation in prior or concurrent NRC regulatory proceedings does not necessarily prejudice a transfer agreement, the formal existence of New Jersey provision for transfer seems in no way an assurance that the transfer would satisfy criterion 25’s intended preclusion of “interference with or interruption of licensed activities or the processing of license applications.” 46 Fed.Reg. at 7543. Obviously the NRC need not automatically consider every single pending licensing action individually when it considers transfer to a state. But in this case the NRC had a long history of dialogue and cooperation regarding the *495 termination of a license, the state has been consistently hostile to those termination proceedings, and the regulated entity alerted the NRC not only to the likely interference with decommissioning but also to partial transfer as a possible solution. At the very least, the NRC should have explained how Shieldalloy’s decommissioning process could proceed under the New Jersey regime free of the interference and interruption sought to be avoided by criterion 25 and why the partial transfer was not an appropriate alternative arrangement.
At oral argument, the NRC offered an argument that the statute did not permit a partial transfer otherwise than at the request of the would-be transferee state, pointing to
On the current record we cannot decide the interpretation of the statute. Our concern is whether NRC provided a sufficient explanation for its actions. We cannot defer to the agency’s statutory interpretation under
Chevron, U.S.A. v. Natural Res. Def. Council,
Because the NRC’s response to Shieldalloy’s comments on criterion 25 and the retention of jurisdiction does not draw a “rational connection between the facts found and the choice made,”
Burlington Truck Lines,
Shieldalloy challenges the compatibility of many other aspects of the New Jersey and NRC regimes. It argues that a cost-benefit analysis principle called the ALARA principle (“as low as reasonably achievable”) is an essential objective of the LTR, and that New Jersey’s remediation program excludes ALARA from consideration. It argues that the New Jersey program fails to allow license termination for on-site decommissioning under restricted use conditions. It argues that New Jersey’s program includes a variety of standards that diverge significantly from the NRC program, including the maximum allowable total dose to a member of the public, the duration of time over which peak dosage is calculated, the total effective dose equivalent limits, and the approach to releases to ground and surface water. It argues that the New Jersey program fails criterion 12 by not authorizing exemptions in the interest of public health and safety. And it argues that the New Jersey program fails criterion 23, *496 regarding the fair and impartial administration of regulatory law, because the state’s regulations only affect Shieldalloy. Shieldalloy contends that these divergences, individually and together, render the New Jersey program incompatible with the federal regime.
The NRC provided responses to each of these claims in its comments. It claimed that Shieldalloy was simply wrong on whether New Jersey allows exemptions and, among other things, said that there was no evidence of unfair administration of New Jersey law. NRC Staff Comments at 6-7. With respect to ALARA, restricted use, and the various dosage standards, the NRC argued that New Jersey’s program merely has more stringent requirements than the federal regime — and that greater stringency is acceptable under the Compatibility Guidance Document, 62 Fed.Reg. at 46,520. Id. at 4. Given that the LTR is a category C regulation, they argued, the state regulatory program only needs to meet the LTR’s “essential objectives.” Id. at 5.
Shieldalloy replies that while New Jersey’s standards may be more stringent, they are actually less safe. See Shieldalloy Br. at 50. Because of the higher stringency, Shieldalloy states that it is prevented from using on-site disposal and will be forced to ship the materials to a facility in Utah. The consequence is that the doses of radiation to the public resulting from removing the radioactive materials from the site and relocating them in Utah will actually be greater than the public health and environmental harms that accompany on-site disposal of the materials. Id. Although this is a troubling prospect, given the NRC’s commitment to protecting public health and safety from nuclear materials throughout the nation, see, e.g., Compatibility Guidance Document, 62 Fed.Reg. at 46,520 (stating that the NRC’s mission is to enable civilian nuclear use “with adequate protection of public health and safety” and that the NRC must ensure a “coherent nationwide effort” for the control of nuclear materials), Shieldalloy did not raise this criticism in its comments on the proposed transfer (though it had done so in its second decommissioning proposal to the Commission, filed in October 2005). 9
Given our findings on criterion 25 and the retention of jurisdiction, we need not address whether this and Shieldalloy’s other allegations hold up and whether the NRC’s explanations in response were sufficient. But we do pause briefly to note one curiosity.
* * *
Together, the NRC’s insufficient explanations on the applicability of criterion 25 and the retention of jurisdiction render its transfer of regulatory authority to New Jersey arbitrary and capricious. We therefore grant Shieldalloy’s petition, vacate the NRC’s transfer of authority, and remand for proceedings consistent with this opinion.
So ordered.
Notes
. Criteria for Guidance of State and NRC in Discontinuance of NRC Regulatory Authority and Assumption Thereof by States Through Agreement, 46 Fed.Reg. 7540 (Jan. 23, 1981), as amended by 46 Fed.Reg. 36,969 (July 16, 1981) and 48 Fed.Reg. 33,376 (July 21, 1983).
. Statement of Principles and Policy for the Agreement State Program; Policy Statement on Adequacy and Compatibility of Agreement State Programs, 62 Fed.Reg. 46,517 (Sept. 3, 1997).
. See Compatibility Categories and Health and Safety Identification for NRC Regulations and Other Program Elements — SA-200, at App. A (June 5, 2009) (stating that program elements in 10 C.F.R. are classified at http:// nrc-stp.ornl.gov/regsumsheets_newregs.html) (follow link for Standards for Protection Against Radiation).
. See, e.g., State of New Jersey: NRC Staff Assessment of a Proposed Agreement Between the Nuclear Regulatory Commission and the State of New Jersey, 74 Fed.Reg. 25,283 (May 27, 2009).
. Letter from Hoy E. Frakes, Jr., President, Shieldalloy, to Michael T. Lesar, NRC (June 11, 2009).
. State of New Jersey: Discontinuance of Certain Commission Regulatory Authority Within the State; Notice of Agreement Between the Nuclear Regulatory Commission and the State of New Jersey, 74 Fed.Reg. 51,882 (Oct. 8, 2009).
. Memorandum from John C. Hoyle, Secretary, NRC, to L. Joseph Callan, Exec. Dir. of Operations, Oklahoma Agreement State Negotiations, SECY-97-087 (June 19, 1997).
. Memorandum from William D. Travers, Exec. Dir. of Operations, to NRC Commissioners, 1, 6, Oklahoma Agreement State Negotiations, SECY-99-123 (Apr. 28, 1999).
. Shieldalloy, Decommissioning Plan for the Newfield Facility 92, Report No. 94005/G-28247, Rev. 1 (Oct. 21, 2005).