MEMORANDUM OPINION
The plaintiff, Sherwin-Williams Company (“SW”), filed a complaint against defendants, ARTRA Group, Inc. (“ARTRA”), et al., asserting claims against ARTRA and other former owners and operators of a contaminated property in an industrial area south of Baltimore, Maryland. Specifically, the plaintiff alleges that the defendants’ activities on the property caused the release of hazardous and toxic chemicals that contaminated the soils and groundwater at the property. In its eight-count Complaint, the plaintiff seeks cost recovery, contribution, and declaratory relief pursuant to the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), 42 U.S.C. Sections 9607(a), 9613(f), and 9613(g)(2) (Counts I — III). In addition, SW asserts claims for common law indemnification, common law contribution, contract indemnification, negligence, and nuisance. This case was stayed for a number of years, on the parties’ request, pending certain administrative proceedings, which have now been concluded.
The case is before the Court on numerous motions from the plaintiff, SW, and the defendant, ARTRA. SW filed a motion for partial summary judgment on Counts I-III (the CERCLA claims), and Count VI (for contract indemnification). ARTRA filed five motions with the Court. These included: (1) a motion for judgment on the pleadings with respect to Counts I (CERCLA cost recovery), IV-V (common law indemnification and common law contribution), and counts VII-VIII (negli-genee and nuisance); (2) a motion for partial summary judgment as to Count VI (contractual indemnification); (3) a motion for partial summary judgment on Counts I — III, alleging that those claims are time-barred; (4) a motion for partial summary judgment as to drum removal costs and costs associated with the so-called 200, 600, and 700 Areas; and (5) a motion for summary judgment regarding SW’s alleged failure to comply with the National Contingency Plan. The Court has considered the pleadings submitted by the parties, and no oral hearing is necessary. Local Rule 105.6 (D.Md.).
For clarity, the Court will rule with respect to each Count of the initial Complaint. As to Count I (CERCLA cost recovery), SW’s motion for partial summary judgment is DENIED, and ARTRA’s motion for judgment on the pleadings is GRANTED.
1
As to Count II (CERCLA contribution), SW’s motion for partial summary judgment is GRANTED, and ARTRA’s motion for partial summary judgment is DENIED. As to Count III (declaratory judgment), SW’s motion for partial summary judgment is GRANTED, and ARTRA’s motion for partial summary judgment is DENIED. As to Count IV (common law indemnification), ARTRA’s motion for judgment on the pleadings is GRANTED. As to Count V (common law contribution), ARTRA’s motion for judgment on the pleadings is GRANTED. As to Count VT (contract indemnification), SW’s motion for partial summary judgment is GRANTED with respect to those costs incurred within the limitations period, and ARTRA’s motion for partial summary judgment is DENIED, except that it is GRANTED to the extent that claims falling outside the statute of limitations are barred. As to Counts VII and VIII (negligence and nuisance), ARTRA’s motion for judgment on the pleadings is GRANTED. Finally, ARTRA’s motion
BACKGROUND
This case involves a dispute about who is responsible for paying for the cleanup of hazardous substances contaminating a 23-acre parcel of land located on Hollins Ferry Road in Baltimore, Maryland. The site has been used by various owners since the late 1940s for paint manufacturing. The defendant, now known as ARTRA, became an owner of the site through a series of mergers and corporate name changes beginning in approximately 1962. In 1980, ARTRA (which at the time was known as Dutch Boy) signed an agreement to sell its assets, including the subject property, to Sherwin-Williams, the current owner of the property. The sale agreement signed by the parties contains an assumption of liabilities clause.
During ARTRA’s ownership of the property, hazardous substances were used and hazardous waste was generated, including toluene, xylene, methylene chloride (varnish remover), and trichloroethylene (TCE) waste that was shipped from the property as indicated by waste manifests from 1979 and a 1979 Waste Generation Study. These substances were primarily used as solvents. SW’s expert, whose conclusions have been questioned by AR-TRA’s expert, determined that a large portion of the contamination on the property was caused by leaks from underground storage tanks (USTs) that began during ARTRA’s ownership. These tanks were removed during SW’s ownership and, at that time, there was evidence that several of the tanks contained holes and were leaking. An analysis of photographs taken during ARTRA’s ownership shows open storage of drums, and “[ejvidence of what may be a recent flow of liquid(s)” in an area near one of the buildings at the site. The deposition testimony of several former Dutch Boy (now ARTRA) employees indicates that there was a leak in an underground storage tank, pipeline leaks, and leaking drums. Specifically, the employees stated that the contents of drums (including traffic paint and industrial finishes) sometimes spilled when palettes would break or forklifts would accidentally puncture them, splashing would occur when drums were filled with product, and pits dug in the ground were used to drain solvent wastewater from drums. According to the employees, these drums and tanks contained hazardous substances such as xylene, toluene, methylene chloride and other substances that have been found on the site. A spill prevention plan dated November 15, 1973 noted that “[tjhere have been no spills greater than a few hundred gallons outside of buildings during the last 3 years” and “only one tank failure in the 25 years [sic ] plant history.”
Sherwin-Williams used many of the same chemicals in its paint manufacturing processes, including trichloroethane (TCA), toluene, methyl ethyl keytone (MEK), and methyl isobutyl keytone (MIBK). In the early 1980s, after SW took over ownership of the property, officials from the State Department of Health and Mental Hygiene, Environmental Health Administration (now Maryland Department of the Environment (MDE)) began to direct SW to clean up contamination at the site. Drum removal was ordered by the State in 1984 after a finding that SW was in violation of state law regarding the proper storage and removal of waste drums. On January 29, 1985, SW entered into a Consent Order with MDE in which SW was ordered to construct a drum storage pad, install monitoring wells, and pay a fine. In May 1985, the State brought an action against SW for the unpermitted discharge of water pollutants and controlled hazardous substances. The case was settled in 1986, and SW was ordered to pay a fine and to conduct environmental improvements at the facility. The State also
SUMMARY JUDGMENT STANDARD Under Rule 56(c) of the Federal Rules of Civil Procedure, summary judgment is appropriate when there is no genuine issue as to any material fact, and the moving party is plainly entitled to judgment in its favor as a matter of law. In
Anderson v. Liberty Lobby, Inc., 477
U.S. 242, 249,
ANALYSIS
Count I — CERCLA Cost Recovery
In this Count, SW seeks to recover cleanup costs under CERCLA from former owners (ARTRA) of the site it now owns. CERCLA provides a method whereby a private party who responds to contamination at a facility covered by CERCLA can recover response costs from responsible parties.
See
42 U.S.C. § 9607. There are, however, limitations on the use of this cost recovery device by parties who are themselves potentially responsible for pollution on the site. The Fourth Circuit has made clear that a party who is a potentially responsible party (PRP) cannot sue for cost recovery. Rather, such party’s method of cost recovery should be an action for contribution. In
Axel Johnson, Inc. v. Carroll Carolina Oil Co.,
As a current owner and operator of the site where hazardous substances have been released, SW is itself a potentially responsible party (PRP), even if SW did not own the property at the time the hazardous waste disposal occurred.
See
42 U.S.C. § 9607(a)(i);
Trinity American Corp. v. EPA,
In this Count, SW seeks contribution from ARTRA under CERCLA, 42 U.S.C. § 9613(f)(1). This section of the statute provides that “[a]ny person may seek contribution from any other person who is liable or potentially liable under section 9607(a) of this title, ....” 42 U.S.C. § 9613(f)(1). Therefore, SW is entitled to seek contribution from ARTRA if ARTRA is a potentially responsible party under Section 9607(a).
Statute of Limitations
SW filed its complaint in this action on September 23, 1991 for the recovery of cleanup costs it began to incur in the early to mid 1980s. ARTRA argues that SW’s CERCLA contribution claim is barred by the statute of limitations. CERCLA was amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA) to include, among other things, a statute of limitations which became effective on October 17, 1986. 42 U.S.C. § 9613(g). The provision provides a statute of limitations to be applied to initial actions for recovery of costs under § 107 and a statute of limitations that applies to contribution actions under § 113(f). Section 113(g)(3), the section applicable to contribution actions, provides that:
[n]o action for contribution ... may be commenced more than 3 years after— (A) the date of judgment in any action under this chapter for recovery of such costs or damages, or (B) the date of an administrative order under section 9622(g) of this title (relating to de min-imis settlements) or 9622(h) of this title (relating to cost recovery settlements) or entry of a judicially approved settlement with respect to such costs or damages. 42 U.S.C. § 9613(g)(3).
SW began to incur response costs in 1984 when the State requested that it remove drums from the property, and in 1985, in response to a consent order it signed with the State Department of Health and Mental Hygiene, Environmental Health Administration (now the Maryland Department of the Environment) requiring it to build a drum storage pad by March 1, 1985, and to conduct a survey and study for the placement of groundwater monitoring wells. SW did not incur costs in re
The Tenth Circuit, faced directly with the question of what statute of limitations to apply to an action for contribution under CERCLA when none of the triggering events listed in § 113(g)(3) has occurred, concluded that the statute of limitations for initial cost recovery actions found in § 113(g)(2) should apply.
See Sun Co., Inc. v. Browning-Ferris, Inc.,
Section 113(g)(2) provides that:
[a]n initial action for the recovery of the costs referred to in section 9607 of this title must be commenced — (A) for a removal action, within 3 years after completion of the removal action .... and (B) for a remedial action, within 6 years after initiation of physical on-site construction of the remedial action, except that, if the remedial action is initiated within 3 years after the completion of the removal action, costs incurred in the removal action may be recovered .... (Emphasis supplied). 42 U.S.C. § 9613(g)(2).
Therefore, in order to determine both the date on which the cause of action accrued and the correct period of limitations to apply, this Court must determine whether the actions taken by SW were removal or remedial actions.
As an initial matter, however, the earliest date that the cause of action could have accrued is October 17, 1986, which is the effective date of the CERCLA statute of limitations, because the statute should
Removal actions are generally short-term actions taken to “cleanup or remov[e]' released hazardous substances from the environment ...”, 42 U.S.C. § 9601(23), including actions to “monitor, assess, and evaluate the release or threat of release of hazardous substances, the disposal of removed material, or the taking of such other actions as may be necessary to prevent, minimize, or mitigate damage to the public health or welfare or to the environment ....,” while remedial actions are “those actions consistent with permanent remedy •taken instead of or in addition to removal actions ....” 42 U.S.C. § 9601(24).
ARTRA admits that SW took removal actions through at least February 1988, including the removal of drums and underground storage tanks and the cleanup of a xylene wastewater spill. See AR-TRA’s Reply in Supp. of Mot. for Summ. J. at 10. The drum and underground storage tank removal, undertaken prior to the implementation or preparation of any remediation plan or permanent remedy, should be characterized as removal actions. See cases cited in note 2, supra.
Furthermore, these actions, which preceded the implementation of a permanent remedy, should be considered as one removal action for statute of limitations purposes.
See Kelley v. E.I. DuPont de Nemours and Co.,
However, there is a dispute as to whether the excavation of soils which was completed on September 23, 1988 constitutes a removal or remedial action. This dispute need not be decided for purposes of the statute of limitations. If it is classified as a removal action and is deemed the last removal action, suit was filed on September 23, 1991, which is within the 3-year limitations period for removal actions. In addition, the installation of monitoring wells continued into 1990, which would constitute additional monitoring activities that may be characterized as a continuation of the removal actions, thus still falling within the 3-year period. If it is characterized as the initiation of remedial activity, it was initiated within three years of the completion of removal action, occurring on February 1988 (clean up of xylene wastewater), and therefore all of the costs would fall within the statute of limitations.
Therefore, even though the dividing line between removal and remedial actions in this case is far from clear, it is apparent that removal actions were ongoing at least through to some time in early 1988. Regardless of whether the soil extraction which was completed on September 23, 1988 is considered a removal or a remedial action, it was either within the statute as part of a continuous removal action, or was the initiation of a remedial action which occurred within three years of the completion of removal activity in February 1988. The CERCLA contribution claim is, therefore, not barred by the statute of limitations.
Liability
Section 9607(a) provides that:
any person who at the time of disposal of any hazardous substance owned or operated any facility at which such hazardous substances were disposed of, ... from which there is a release, or a threatened release which causes the in-currence of response costs, of a hazardous substance, shall be liable for ... any other necessary costs of response incurred by any other person consistent with the national contingency plan ....
42 U.S.C. § 9607(a);
see also Axel Johnson,
It is undisputed by the parties that AR-TRA was an owner of the property that is the subject of this litigation. Furthermore, the property is a “facility,” as that term is broadly defined in CERCLA, because the definition includes “any building, structure, installation, equipment, pipe ...
A. Disposal and Release
CERCLA has adopted the definition of “disposal” found in the Solid Waste Disposal Act, 42 U.S.C. § 6903(3). 42 U.S.C. § 9601(29). It is defined as:
the discharge, deposit, injection, dumping, spilling, leaking, or placing of any solid waste or hazardous waste into or on any land or water so that such solid waste or hazardous waste or any constituent thereof may enter the environment or be emitted into the air or discharged into any waters, including ground waters. 42 U.S.C. § 6903(3).
Disposal includes depositing hazardous waste into enclosed containers such as drums or USTs.
Nurad, Inc. v. William E. Hooper & Sons Co.,
ARTRA argues that the deposition testimony of the former employees is vague and speculative, in part because the employees were unable to precisely identify the quantity of waste released. It further argues that the spills discussed by former employees were minimal or infrequent.
See
Ex. 82, Def.’s Opp’n to Pl.’s Mot. for Summ. J. SW need not prove the quantities of chemicals or frequency of releases in order to prove by a preponderance of the evidence that ARTRA is liable under CERCLA for contribution.
See, e,g., HRW Systems,
CERCLA liability may be assessed on circumstantial evidence.
Crofton Ventures Ltd. Partnership v. G & H Partnership,
B. Release Resulting in Incurrence of Response Costs
ARTRA argues that SW’s proof “does not establish that the constituents later found to make up the contamination found in the mid-1980s were released before 1980 ....” ARTRA’s Opp’n to SW’s Mot. at 12. However, CERCLA does not require this level of proof. CERCLA was designed to be a strict liability regime under which strict causation requirements need not be met.
See Monsanto Co., 858
F.2d at 167 (“[T]he overwhelming body of precedent ... has interpreted [CERCLA] as establishing a strict liability scheme.”);
Westfarm Associates Ltd. Partnership v. Washington Suburban Sanitary Comm’n,
[t]here is no statutory requirement that in order for an owner or operator to be held liable for cleanup costs, the hazardous substances that cause the incurrence of those costs must be the same hazardous substances that were deposited at the facility when the party owned or operated it. Rather, under § 107 a former owner or operator can be held liable for response costs caused by hazardous substances that were deposited at the facility at times when it did not own or operate the facility, so long as some hazardous substances were deposited at the facility during the period when the party did own or operate it and the other requirements of the statute are met. Axel Johnson,191 F.3d at 414 .
Therefore, it is only necessary for SW to prove that a hazardous substance was disposed of and released during ARTRA’s ownership of the facility and that SW later incurred response costs. As detailed above, the plaintiffs have presented ample evidence that there was a disposal and release of hazardous substances during ARTRA’s ownership and SW has incurred costs to clean up hazardous substances on the property.
C. Liability for the 200, 600, and 700 Areas and Drum Removal Costs
ARTRA has moved for partial summary judgment as to its liability for drum removal costs and for costs associated with the cleanup of the 200, 600, and 700 areas. With respect to the drum removal costs, it argues that SW has presented no evidence that the drums for which it seeks removal costs belonged to ARTRA, and it further argues that SW executed a release in November of 1983 that had the effect of foreclosing all future liability of ARTRA for costs of drum removal. With respect
A question does remain to be decided, though, as to whether these costs are recoverable as damages.
See United States v. Alcan Aluminum Corp.,
D. Consistency with the National Contingency Plan
In order to recover costs from AR-TRA, SW must prove that the response costs it has incurred are consistent with the National Contingency Plan (NCP).
See
42 U.S.C. § 9607(a)(4)(B);
White v. County of Newberry,
Although the Fourth Circuit has not directly addressed the issue of the necessary level of compliance with the NCP, this Court has held on several occasions that in order to meet this element, it is only necessary for a plaintiff to prove that it incurred some response costs consistent with the NCP. This Court has held that:
the plaintiff need only show that it has incurred some cost consistent with the NCP in order to maintain a CERCLA cause of action. So long as [the plaintiff] has demonstrated that some of its costs are recoverable under CERCLA, it is entitled to judgment on the issue of liability; proof of the consistency of the remaining costs may wait until trial on the issue of damages.
Weyerhaeuser v. Koppers Co., Inc.,
ARTRA argues that SW’s 1984 drum removal did not comply with the 1982 NCP’s removal requirements, and that SW’s drum removal in 1985-1988, and its removal of USTs in beginning in 1986, did not comply with the 1985 NCP’s removal requirements. Specifically, it argues that there was no determination made that there was a threat to public welfare or the environment before these removals, nor were preliminary assessments conducted. Furthermore, ARTRA argues that the soil excavation completed in September 1988 was a remedial action which did not comply with the 1985 NCP’s requirements for remedial actions. Finally, ARTRA argues that many of SW’s activities failed to meet the requirements for public participation and comment required by the 1985 and 1990 NCPs.
Several courts have held that government oversight of hazardous waste cleanup efforts may satisfy the public participation/comment element of the NCP.
See Bedford Affiliates v. Sills,
SW has met its burden of showing that at least some of its response actions substantially complied with the NCP. Both the drum and UST removal actions taken prior to 1990 substantially complied with the 1982 and 1985 NCP plans. These removal actions, which are not required to meet the more stringent requirements outlined for remedial actions, were taken at the direction of the MDE and were designed to effectuate the removal of sources of contaminants on the property that posed a risk to the environment. MDE was involved throughout the process of removing these tanks and drums. Furthermore, as to the remedial actions taken — the soil vapor extraction system installed in the 200 Area and the groundwater pump-and-treat system in the 100/500 area — it appears that SW, with the continuous involvement of MDE, assessed and investigated these areas, proposed alternative remedies, and provided opportunities for public comment through notices published in the
Baltimore Sun
(a local general circulation newspaper) prior to the initiation of the remedial actions. While SW has met its burden of showing consistency with the NCP for liability purposes, more proof may be considered as to which specific costs were or were not consistent with the NCP at the damages phase of this case.
See Weyerhaeuser,
Count III — CERCLA Declaratory Relief
In its Motion, SW asks this Court to enter a declaratory judgment as to AR-'TRA’s liability for SW’s future response costs pursuant to Section 118(g)(2) of CERCLA. ARTRA asks this Court to dismiss this count of the complaint as time-barred, based on its arguments regarding compliance with the statute of limitations for cost recovery and contribution actions. Because this Court has determined that SW’s contribution claim is not barred by the statute of limitations, it follows that the claim for a declaratory judgment is likewise not time barred.
The section of CERCLA regarding declaratory judgments for future response costs provides that “the court shall enter a declaratory judgment on liability for response costs or damages that will be binding on any subsequent action or actions to recover further response costs or damages.” 42 U.S.C. § 9613(g)(2). Courts have held that the provision in the statute regarding declaratory judgments applies to contribution actions brought pursuant to Section 113(f) as well as to actions brought to recover costs under Section 107, despite the fact that the statutory language appears in the section of the statute involving costs recovery actions brought under Section 107 and not in the section regarding contribution.
See Boeing Co. v. Cascade Corp.,
Furthermore, the Fourth Circuit has concluded that the entry of a declaratory judgment is mandatory in cases where there has been a judgment as to liability, holding that “[e]ven if multiple response cost actions exist or might exist, the court in the first action to reach decision is
required
to enter judgment as to liability
Count IV — Common Law Indemnification
In Maryland, “[indemnification is appropriate if there is a legal relationship mandating it, e.g. contract or respondeat superior, or when one party’s role is so passive or secondary that it would be inequitable to require that party to sustain any of the burden of judgment.”
Canjura v. Able Serv. Contractors, Inc.,
Count V — Common Law Contribution
In Maryland, an action for contribution, like an action for indemnification, is derivative of a finding of liability on the main claim. See id. Therefore, in order to have a viable claim for contribution, SW must prove that it shares some common liability or obligation with ARTRA, whether in tort, contract, or by statute. SW and ARTRA are not joint tortfeasors, as there has been no finding that SW is liable in tort to the state or to any third party, and as will be discussed below, ARTRA is not liable to SW for negligence or nuisance. Therefore, there are no grounds for an action for contribution under the Maryland Uniform Contribution Among Joint TortFeasors Act, Md.Code Ann., Cts. & Jud. Proc. § 3-1401 et seq. ARTRA’s potential contractual liability to SW will be addressed separately below.
The only remaining basis upon which SW may seek contribution from ARTRA must be based on some statutory right to contribution. While SW correctly cites to case law supporting this proposition, it broadly states that ARTRA is liable for contribution under state and federal law, without pointing to any specific provisions of law which create a common obligation between the parties as required by the court in
Lyon v. Campbell,
Count VI — Breach of Contract/ Contract Indemnification
SW argues that the agreements signed by the parties regarding the sale of the assets and business of Dutch Boy (now ARTRA) to SW in 1980 contain language requiring ARTRA to indemnify SW for the costs of the cleanup of the property and for its legal expenses and attorney’s fees. Specifically, SW points to section 8(b) of the Sales Agreement signed by the parties on July 31, 1980 and the Assumption Agreement signed by the parties on August 25, 1980. The relevant language is contained in the Assumption Agreement. It reads:
Seller hereby retains and agrees to pay and discharge all other liabilities, obligations and commitments of Dutch Boy, whether known, unknown, contingent or otherwise, and whether or not disclosed to Purchaser or set forth in Dutch Boy’s Financial statements or books, and any and all claims, losses, damages, expenses, costs, obligations, liabilities and commitments which may arise or result from from [sic] such liabilities, obligations, or commitments, that are not specifically assigned to and assumed by Buyer under said Sections 8 and 13.
Section 8(a) of the Sales Agreement states that:
Purchaser shall assume on the Closing Date and agrees to pay, perform and discharge (i) all liabilities and obligations of Seller under the leases, mortgages, license arrangements, contracts and other agreements set forth in Schedule 9 annexed hereto accruing and allocable to the period from and after the Closing Date and (ii) all other obligations relating to this transaction which are specifically set forth in this Agreement.
Section 8(b) states that:
Except as expressly set forth in Section 8(a) and 13 hereof, [regarding employee and employee benefit matters] Purchaser shall not assume, agree or be obligated to pay, perform or discharge any debts, liabilities, leases, mortgages, licenses, or other obligations of Seller, whether now existing or hereinafter arising for whatever reason; and, without limiting the generality of the foregoing, Purchaser shall not assume or pay, perform or discharge ... (v) any liability or obligation with respect to any claim, action, suit, or demand or any legal, administrative or other proceeding or judgement with respect to causes of action arising out of Seller’s ownership of Seller’s Coatings Division or the Assets prior to the Closing Date or arising from a product manufactured prior to the Closing Date.
CERCLA allows parties to shift CERCLA liability through the use of an indemnity or assumption agreement that was entered into prior to the enactment of CERCLA.
See Dent v. Beazer Materials and Servs., Inc.,
Under both Ohio and Maryland law, the interpretation of an unambiguous contract is a matter of law for the court.
See Potti v. Duramed Pharmaceuticals, Inc.,
The Fourth Circuit has adopted the Third Circuit’s method for determining the validity of pre-CERCLA assumption and indemnification agreements, stating that “whether a pre-CERCLA indemnification provision was intended to cover CERCLA claim [sic ] depends upon whether it is ‘either specific enough to include CERCLA liability or general enough to include any and all environmental liability.’ ”
Dent,
The Assumption Agreement at issue in this case provides that “Seller [Dutch Boy, now ARTRA] hereby retains and agrees to pay and discharge all other liabilities, obligations and commitments of Dutch Boy, whether known, unknown, contingent or otherwise, ... and any and all claims, losses, damages, expenses, costs, obligations, liabilities and commitments which may arise or result from from [sic ] such liabilities, obligations or commitments, that are not specifically assigned to and assumed by Buyer [Sherwin-Williams] under said Sections 8 and 13.” (emphasis supplied). The only liabilities assumed by the buyer, SW, under Sections 8 and 13 include any liabilities relating to leases, mortgages, license arrangements, employee matters, and other specific obligations under the agreement. Environmental liabilities were not mentioned in either the original Sales Agreement or the Assumption Agreement. Therefore, the language in the Assumption Agreement is sufficiently general to encompass all remaining liabilities that were not specifically allocated to SW in either of the agreements and is sufficient to require ARTRA to indemnify SW for at least that part of the CERCLA liability that is determined to be attributable to ARTRA’s ownership of the Coatings Division or the assets prior to the closing date.
ARTRA argues in its motion for partial summary judgment on this issue that even if the assumption agreement entitles SW to be indemnified for the costs that it has incurred that are attributable to ARTRA’s ownership, SW’s claim is nonetheless barred by the statute of limitations. While Ohio law applies to the construction of the contract between the parties, Maryland’s statute of limitations will apply. The Maryland courts have followed the general rule that the statute of limitations of the forum state applies even when that state’s choice of law rules require that another state’s substantive law be applied.
See Morley v. Cohen,
With regard to the date that a claim for contract indemnification accrues, Maryland applies the rule that the claim accrues at the time payment was made by the party seeking indemnification.
See Southern Maryland Oil Co. v. Texas Co.,
In
Singer Co. v. Baltimore Gas and Elec. Co.,
where a contract provides for continuing performance over a period of time, each successive breach of that obligation begins the running of the statute of limitations anew, with the result being that accrual occurs continuously and a plaintiff may assert claims for damages occurring within the statutory period of limitations.
Applying the rule in
Singer
to claims for indemnification, the Court of Special Appeals held that “[w]here the duty to defend and potentially to indemnify might attach, the failure to perform that duty with respect to each separate claim would constitute a distinct breach.”
Commercial Union Ins. Co. v. Porter Hayden Co.,
Count VII — Negligence
Statute of Limitations
ARTRA argues in its motion for judgment on the pleadings that SW’s negligence claim is barred by the applicable three year statute of limitations.
See
Md. Code Ann., Cts.
&
Jud. Proc. § 5-101. In Maryland, the discovery rule governs the time of accrual of a cause of action
ex delicto.
Under this rule, the cause of action accrues “at the time the plaintiff had actual knowledge
or
implied knowledge of the existence of the cause of action.”
Weyerhaeuser,
SW alleges in its Complaint that AR-TRA “wrongfully, illegally and negligently failed to deliver to Sherwin-Williams at the time of the transfer of ownership of the Site a site that was environmentally clean and safe.” Compl. at ¶ 52 (emphasis supplied). Furthermore, in 1985, SW signed a consent order with the state of Maryland regarding the improper storage of drums and incurred cleanup costs associated with the drums. See Compl. at ¶ ¶ 58-59. Therefore, it is clear that SW knew or should have known about the contamination of the property either at the time it purchased the property in 1980 or when it first incurred cleanup costs in 1984 and 1985. Using either date as the date of discovery, the cause of action for negligence, having been filed in September of 1991, is time barred.
Even were this claim not time barred, judgment on the pleadings in favor of the defendant would still be appropriate on it. The Maryland Court of Appeals has held that a prior occupant of land owes no duty to a subsequent occupant of that land for losses resulting from a condition on the property that could have been discovered and addressed prior to occupancy.
See Rosenblatt v. Exxon,
Count VIII — Nuisance
ARTRA argues in its motion for judgment on the pleadings on SW’s nuisance claim that SW, as a subsequent occupier of the land, has no cause of action for nuisance for activities conducted on the land during a prior owner’s occupancy.
4
This Court recently stated that “Maryland courts do not recognize the right of a subsequent occupant of land to bring an action in private nuisance against a prior occupant for activities conducted on the land during the prior occupancy.”
Adams v. NVR Homes, Inc.,
CONCLUSION
In light of the above, a separate order will be issued as follows: As to Count I (CERCLA cost recovery), SW’s motion for partial summary judgment is DENIED,
The only issue that remains to be decided is the amount of damages that should be awarded to SW. The parties’ suggestions as to how to proceed on this issue, including whether a reference to a Magistrate Judge or other intermediary for mediation or other resolution of this issue would be appropriate, should be submitted within 15 days of the date hereof. In addition, the parties’ positions regarding the continuing viability of any claims against the remaining parties in this case should be addressed.
Notes
. Because the Court has granted ARTRA’s motion for judgment on the pleadings on this issue, its motion for partial summary judgment on grounds that the claim is time barred need not be considered.
.
See, e.g., United. States v. Akzo Nobel Coatings, Inc.,
. The definition of "release” includes "disposal.” Therefore, at least one court has held that where there is a disposal, there is a release.
See HRW Systems, Inc. v. Washington Gas Light Co.,
. ARTRA raises the statute of limitations as an alternate ground for granting judgment on the pleadings in its favor on the nuisance claim. The application of the statute of limitations turns on whether the alleged nuisance is defined as temporary or permanent. If a nuisance is permanent, an action must be brought “within three years of the time that the permanency of the conditions ... became manifest to a reasonably prudent person .... ”
Goldstein v. Potomac Elec. Power Co.,
