52 Ct. Cl. 407 | Ct. Cl. | 1917
Lead Opinion
delivered the opinion of the court:
This is a suit brought by the Sheridan-Kirk Contract Co. against the United States for the sum of $8,576.50. The plaintiff bases its suit upon the provisions of two contracts. The original contract was entered into on May 5, 1903, and provided for building a section of the Colbert Shoals Canal in the Tennessee Diver. The second contract was a modification of the first and was entered into by the parties on the 14th day of December, 1903. Under the first contract the plaintiff contracted to build a concrete wall on the edge of the river parallel with the south bank to form the boundary of a canal which was cut in the river and bank. Among the .specifications attached to and made a part of the first contract were the following:
“45. Cofferdam. — Should a cofferdam be necessary in the construction of the lock or other work, it shall be built and maintained by the contractor at his own expense, its cost being included in his bid on other parts of the work; it may be of any design that shall be approved by the engineer.
“46. Removal of cofferdam. — When the necessity for the cofferdam shall have ended, the contractor will be required to remove at his own expense all the material composing it, and to leave the river unobstructed to its full depth. The time and manner of such removal and the place of deposit of all waste material shall be prescribed by the engineer.”
After the work had commenced and the contractor had built a series of longitudinal cofferdams, the Government proposed to the contractor to modify and change the plan so that for about a mile from the head of the canal the concrete wall should be abandoned. This new plan greatly reduced the amount of concrete. This new plan was contained in a proposition in writing made by the United States to the contractor and among other things therein contained was the following:
“The excavation of that portion of the towhead lying between the ends of the cofferdams, and acting itself as a coffer, and the construction of a cofferdam of similar style, size, and strength joining these two ends, a length of approximately 400 feet, together with the excavation of all the material down to bedrock on a space 20 feet immediately outside of the outer line of this closing coffer. The longi*412 tudinal cofferdams, except that portion upstream of the upper end of the canal wall to be left in place instead of being removed, as provided for in paragraph 46 of the specifications. This to apply not only to the cofferdams of the section now being considered, but also to the longitudinal cofferdams clear down to the guard lock. * * * The cost of building and filling the coffer should be included in the price bid per linear foot of coffer.'1’’ [Italics ours.]
This proposition was made to the plaintiff by the defendant on October 26, 1903. On November 3, 1903, the plaintiff replied to this proposition by accepting the same in substance and stating:
“ Cofferdam, $2.60 per linear foot. Type to be built the same as cofferdam now in use.”
On December 14, 1903, the supplemental contract was executed ; this contract embodied the propositions above recited and its terms are in part as follows:
“ The longitudinal cofferdam, where the concrete wall is omitted, will be left in place. The portion of the towhead lying between the ends of the present cofferdam and acting as a coffer, approximately 400 feet long, shall be removed and a coffer built of similar style, size, and strength to that now in place.”
and as to compensation the supplemental contract provides:
“ Cofferdam, two dollars and fifty cents ($2.60) per lineal foot.”
The plaintiff claims that under this supplemental contract of December 14, 1903, it is entitled to receive payment at the rate of $2.50 per lineal foot for 3,854 feet of longitudinal cofferdam where the concrete wall was omitted and which was built after the contract of December 14, 1903, was entered into. In other words, that the supplemental and not the original contract governs the transactions of the parties as to the building of and compensation for cofferdam constructed after the date of the supplemental contract.
It is clear that under the original contract the plaintiff was not bound to perform the work by building cofferdams. It was optional with him as to what method he would use. Under the supplemental contract he was compelled to build
The matter in issue is, therefore, what part of the cofferdam is to be paid for by the defendant, under the terms of the contract. It must be determined by a sound construction of the supplemental contract. It is evident that the language of the contract does not convey a very clear meaning and is, with regard to this matter, ambiguous. The change made by the supplemental contract departs from the original contract, and that change was made at the request of the engineer officer of the Government. It was therefore for the accommodation of the defendant. It is a well-settled principle that where a contract is prepared by an officer of the Government, and is ambiguous in its terms, that construction must be adopted which is more to the advantage of the claimant. Otis v. United States, 20 C. Cls., 315-327; 9 Wall., 407. In Edgar & Thompson Works v. United States, 34 C. Cls., 205-219, the court says, “It is a most familiar principle of Irav that the words of an agreement are taken most strongly against the party who prepared it, and if any liberality is to be indulged in it will be in favor of the party Avho merely signs and not the party who signs and prepares the instrument for execution,” citing 7 Wallace, 688, and 24 C. Cls., 387. The defendant having failed to make the contract clear, and there being ambiguity and uncertainty
The plaintiff, in making answer to the defendants’ proposal for a change in the work, distinctly stated that it would charge $2.50 per linear foot for building cofferdam.
This proposition of the plaintiff was embodied in the supplemental contract. The plaintiff made a demand for payment for the work done on the cofferdam. In view of the wording of the contract of the parties and all of the surrounding circumstances, the court can not do otherwise than come to the conclusion that the plaintiff is entitled to be paid for the number of feet of cofferdam built after the supplemental contract was entered into.
It follows that the plaintiff is entitled to a judgment for the sum of $8,567.50; and it is so ordered.
Dissenting Opinion
dissenting:
After a very careful consideration of this case in an attempt to reconcile my views with those stated I find that I can not do so without too great violence to my own convictions. I am persuaded that it was the intention of the parties, and within a proper construction of the supplemental contract, that the contractors should be paid only for the 427 feet of cofferdam constructed across the towhead and not for the other cofferdam required to be left in the completed work.
Under the original contract cofferdam, if necessary, was to be built by the contractor at his own expense, its cost to be included in the prices bid on other parts of the work. By the next section of the specifications, made a part of the contract, the contractor was required to remove the cofferdam at his own expense. It is not necessary that I should discuss the question as to the necessity for the use of a eoffer-dam in the construction of the work, since the findings very properly state that “ a cofferdam was necessary for the completion of the work prescribed by the original and supplemental contracts.” It follows, therefore, that the original
It is quite apparent that the required removal of the cofferdam was a burden on the contractor rather than a benefit. The character of its construction, if nothing else, would indicate this. That there would be large quantities of waste material to be disposed of in connection with its removal is apparent from the character of its construction and is also indicated in the specifications. The salvage in materials must, of necessity, have been small and no doubt less than the cost of removal. Mr. Sheridan, in his testimony, attempts to show that materials composing the cofferdam would have been of value over and above the cost of removal, but a careful examination of his testimony in this respect must lead to the conclusion that it is entitled to but little, if any, weight, and he finally, contrary to this contention, specifically admits upon cross-examination that it would have been a hardship to be compelled to remove it. The findings correctly state that “ the contractor never removed any of the longitudinal cofferdam,” and this fact must be taken in connection with the further fact that there were portions of the cofferdam which they were not required by the supplemental contract to leave in place and which they might have removed had they seen fit. The findings also show that prior to the execution of the supplemental contract it had been agreed between the parties that the contractor might allow the cofferdam to remain. After that agreement and before the execution of the supplemental contract the contractors had for their own purposes dumped waste rock from the excavation against the cofferdam, rendering its removal practically impossible. What has been said indicates the conditions existent with reference to the cofferdam under the original contract and up to the time of the execution of the supplemental contract, and if the plaintiff is to recover in this action it must be because the supplemental contract changed the whole situation with reference to cofferdam necessarily to be built by the contractors for their own pur
The supplemental contract recites “that with the object of securing the construction of about 1,500 feet additional concrete river wall downstream to the lock by the substitution of a rock-fill dam with rubble masonry toe for about 5,500 feet of the upper end of said wall, the following changes shall be made in the agreement entered into by said parties of the first and second parts on the third day of May, 1903, * * * all the other terms and conditions of which agreement remain unchanged.” Paragraph 1 then prescribes the river wall at the upper end to be omitted, to the approximate length of 5,500 feet, with a reduction in the amount of concrete of approximately 12,000 cubic yards. Paragraph 2 provides for the extension of the concrete river wall downstream. Paragraph 3 prescribes the method of construction of the toe wall along the line of the omitted concrete wall, and paragraph 4 prescribes the method of construction of the rock dam where the concrete wall is omitted.
At that time a part of the longitudinal cofferdam along the portion of the work where, under the original contract, the 5,500 feet of concrete wall was to be built had already been constructed under the provisions of the oi’iginal contract and for the contractor’s own purposes, and, as stated above, the contractors had dumped waste rock against a part of it, indicating even then not only that it was the intention to leave it, but that it was to the advantage of the contractors to be permitted to do so; and this rock thus dumped finally became a part of the rock dam or dump substituted for the concrete river wall under the modified plan and its then existence is recognized by and is the explanation of the requirement in paragraph 4 of the notice to contractors for “the more careful construction of the dump of waste rock.” The portion of the cofferdam already constructed was, by the supplemental contract, not simply permitted to remain in place at the option of the contractor as had already been done, but was required to be left in place in the completed work and this cofferdam built before the execution of the supplemental contract and against which waste rock had been
Paragraph 6 provided “ that as full compensation for making said changes and supplying all the materials and labor necessary for doing said work, the said Sheridan-Kirk Contract Company shall be paid the following prices:
“ Rock excavation, after December 1, 1903, where the maternal excavated is used as described in paragraphs 1, 3, and 4, to form a rock fill dam with rubble masonry toe, to replace the concrete wall, two dollars and thirty-three cents ($2.33) per cubic yard.
“ Cofferdam, two dollars and fifty cents ($2.50) per lineal foot.
“All other rock excavation and additional earth excavation and concrete will be paid for at the unit prices specified in the original contract.”
It should be noted that outside of the question of payment for longitudinal cofferdam, other than that required to be built across the towhead, these provisions of the supplemental contract afforded compensation to the contractors for any loss of profits accruing to them by reason of the lessening of the amount of concrete river wall to be built and for any other expense properly to be incurred by them in connection with the prosecution of the work under the supplemental contract in lieu of that provided for in the original contract. One of these provisions gave to the contractors $2.33 per cubic yard for rock excavation as against a price of $1.98 ■provided for in the original contract, by virtue of which in
It is to be borne in mind that the supplemental contract did not supersede the original contract, but that it simply modified it, leaving all the other terms and conditions of the original contract unchanged, and it follows, necessarily, that the contract for consideration in determining the question is not alone the supplemental contract, but it is both contracts construed together.
It is found, as a fact, and is unquestionably true, that the construction of a cofferdam was necessary for the completion of the work prescribed by the supplemental contract as well as that to be done under the original contract. To hold that under the two contracts, construed together, the United States agreed to pay the contractors $2.50 per foot for longitudinal cofferdam necessarily to be constructed by them for their own purposes, is to hold that the United States deliberately abandoned the provision of the original contract expressly requiring the contractor to construct such cofferdam at his own expense and assumed, with no apparent reason therefor, the burden of paying $2.50 per foot for that cofferdam. There is no doubt about the fact that a cofferdam was required for the construction of one class of work just as it was required for the construction of the other class of work, and there is no possibility of doubt about the fact that when this supplemental contract was made it was made in the light of knowledge upon the part of both parties that the contractor was required, for his own purposes, to build this cofferdam as a necessary prerequisite to
The supplemental contract changed the conditions with reference to the removal of the cofferdam after the completion of the work, and required that the cofferdam should be left in place. It is false logic to argue that because the supplemental contract required the contractors to leave the longitudinal cofferdam in the completed work, the supplemental contract therefore required the contractors to build the cofferdam, and inferentially provided for payment therefor. The requirement as to the building of the longitudinal cofferdam, otherwise than that across the towhead, is found not in the supplemental contract, but in the necessities of the work itself. That necessity existed under the original contract and it continued to exist under the supplemental contract as a necessary adjunct to the construction of both classes of work, and it is the necessities of the case, recognized at the time by both parties, which required the construction of this longitudinal cofferdam and not the supplemental contract.
The removal of the cofferdam after the completion of the work, I submit, was a burden upon the contractor and not a privilege. The specifications themselves, in the terms used, indicate that it was a requirement as against the contractor and not a privilege extended to him, and common knowledge, with reference to such construction as that described in the record in this case, is thoroughly satisfying upon the proposition that when there was provision in the supplemental contract for the leaving of the cofferdam in place instead of its removal it was a provision which relieved the contractors from an otherwise imposed burden. A “ hardship,” Mr. Sheridan says he would have regarded it.
The question of a timely demand for payment for the cofferdam in question bears upon the construction the parties themselves put on the supplemental contract at the time. The contract provided, as is usual in such cases, for payment on monthly estimates of the amount of work done with the usual percentage retained. The findings show that request for an estimate was made of the engineer in charge in 1906. and that a letter was written in February, 1907, by the
The finding shows that in reply to the demand by letter the engineer officer in charge stated that the provision for payment for cofferdam at $2.50 per foot applied only to the additional cofferdam referred to in the supplemental contract, and that they had been paid for that in the estimate for January, 1904, a fact not disputed. The supplemental contract was signed December 14, 1903, and approved December 30, 1903. The 427 feet of cofferdam across the towhead, including necessary preliminary excavation, must have been built in January, 1904. Assuming that the demand made in 1906 was in the middle of the year, two years and a half elapsed before there was any demand for payment for any of the other cofferdam. The findings show that the cofferdam in question was built in 1904, 1905, and 1906, and that a considerable portion of the rock dam or dump in which the cofferdam in question was left was completed several months before any demand was made for payment for cofferdam. The nature of the work, the necessity for cofferdam in the prosecution of the work, the continued progress of the work, even though slow, would certainly justify the conclusion that much cofferdam was built long before 1906.
The contractors did not have to wait until they had completed the rock dam or any part of it before claiming pay
As further throwing some light upon the question, although possibly not of great importance, it is noted that in the letter written by Capt. Barden to the plaintiff company, with reference to the contemplated changes in the plans for this work, and soliciting proposal with reference thereto, the engineer officer indicates that he would like to have “ a proposition from you as to the unit prices at which you would be willing to make these changes.” After specifying the changes to be made, he says, “The longitudinal cofferdams, except that portion upstream of the upper end of the canal wall, to be left in place, instead of being removed as provided for in par. 1¡.6 of the specifications." Further on he states, “All the earth excavation required under (5) will be paid for at the present price of 50 cents per cubic yard ” (5) provided for the excavation of the towhead. Further, he says, “As there are only three classifications under the existing contract, namely, earth excavation, rock excavation, and concrete, and as the extra earth excavation will be taken up at the present price, it will therefore be necessary to alter only the price of rock excavation.” He concludes by saying, “ Your proposal should cover, then, an agreement to make the changes specified above at a certain increased price for rock excavation if (3) (rubble toe) be used, and another
It is conceded that the contractors were paid the contract price for the 427 feet of cofferdam constructed across the towhead and, in my judgment, they are not entitled to further compensation on account of cofferdam.