Shell Pipe Line Corp. v. SarverShell Pipe Line Corp. v. Sarver
Shell Pipe Line Corporation, plaintiff-appellee, filed an expropriation suit against Arley A. Sarver, defendant-appellant. Subsequent to the judgment granting the expropriation and the later jury verdict awarding compensation, various rules were filed by both parties. From a judgment denying Sarver an award of attorney‘s fees and interest on the jury award and reducing by one-half (½) the proposed fee of Sarver‘s expert, A. Byron Core, Sarver appealed. We find that the trial court did not err in denying Sarver an award of attorney fees and interest. We find no error in the award of the expert fee. However, we find the trial court erred in ordering Sarver to return the payment of interest paid by mistake by Shell.
The issues on appeal are whether the trial court erred:
1. In fixing the expert fee of A. Byron Core;
2. In not granting Sarver attorney fees;
3. In denying Sarver interest on the jury award; and 4. In ordering Sarver to return the payment of interest paid to him by mistake by Shell.
Shell instituted the present action against Sarver to gain a right of way for the construction of a pipeline. The expropriation was allowed and the right of way was awarded by judgment dated November 28, 1978. In June 1982 a trial was held to determine the compensation due Sarver. After hearing evidence regarding the value of the property taken and damages caused by the taking, a jury determined that the compensation to be awarded was $30,191.26.
On June 10, 1982, Shell deposited in the Registry of the Court the sum of $37,271.07 representing the principal amount of the verdict ($30,191.26) together with interest on compensation for the taking of the right of way from December 4, 1978, and interest on damages from June 20, 1980. The interest paid was $7,079.81. Sarver subsequently withdrew the total deposit from the Registry of Court.
A few days later Shell discovered that Sarver had never prayed for interest in his pleadings addressed to the subject of compensation. Shell then filed a motion styled: “Return of Erroneous Payment of Interest.” Sarver countered with rules to fix expert fees, fix interest and set attorney fees.
After hearing these rules the trial court in written reasons denied Sarver all interest, denied attorney fees and fixed A. Byron Core‘s appraisal fee at $1,300.00. The trial court also rendered a judgment ordering Sarver to reimburse Shell the interest amount of $7,079.81 previously deposited in the Registry of Court in error and withdrawn by Sarver.
On appeal Sarver contends that he is entitled to attorney fees under
Judge Hebert in his written reasons for judgment addressed the issues raised by Sarver on appeal. After reviewing the record and the jurisprudence, we find that the trial court was correct in his denial of attorney‘s fees and in his determination of the expert fee. Therefore, we adopt Judge Hebert‘s well articulated reasons as to these issues as our own.
“Defendant seeks attorney‘s fees under the provisions of
“The Court is given the power to grant or deny attorney‘s fees in expropriation suits. See City of Lafayette vs. Delhomme, 401 So.2d 1044 (La.App. 3rd Cir., 1981). The intent of
“It is stipulated between the parties that the plaintiff is liable for costs of these proceedings. A disputed item of costs consists of the expert witness fee of A. Byron Core. Sarver contends that a fee of $2650.00 is reasonable due to time spent, and the jury‘s use of his land value figure. The Court recognizes the value of Mr. Core‘s testimony, but also considers plaintiff‘s argument that much of Mr. Core‘s
Concerning the issue of whether Sarver was entitled to judicial interest on the amount of the jury award calculated from the date of taking, the trial court denied this claim because there was no specific prayer for interest in Sarver‘s pleadings. Additionally, the trial court ordered Sarver to return the erroneous payment of interest by Shell.
We find the trial court was correct in determining Sarver was not entitled to an award of interest. In cases of expropriation by entities such as the plaintiff the defendant is entitled to legal interest on his compensation from the date of judgment taking the property or from the date the plaintiff appropriates the property for its use, whichever is sooner. Trunkline Gas Co. v. Rawls, 394 So.2d 1250 (La.App. 2nd Cir.1980), writ denied 400 So.2d 904 (La. 1981). However,
However, the trial court was incorrect in ordering the return of the erroneous payment of interest. Shell deposited in the Registry of Court the sum of $7,079.81 representing interest. Sarver subsequently withdrew this amount. In its rule seeking the return of that money, Shell declared it had mistakenly paid Sarver a debt not due. The trial court granted the motion and ordered Sarver to return the payment of interest. We find the court erred in this portion of its judgment and that the plaintiff is entitled to keep the interest that was paid.
Under
To acquire this right, it is necessary that the thing paid be not due in any manner, either civilly or naturally. A natural obligation to pay will be sufficient to prevent the recovery. (emphasis added)
In the present case an obligation on the part of Shell for payment of interest arose on the date of the expropriation judgment. Because Sarver did not specifically pray for interest, this obligation could not be civilly enforced. However, once the plaintiff voluntarily paid the obligation by depositing the money into the Registry of Court and once the defendant withdrew the sum, the plaintiff is precluded by Art. 2303 from acquiring the right to reclaim this sum.
For these reasons the judgment of the trial court ordering the defendant to return the payment of interest made by the plaintiff is reversed; the judgment of the trial court is affirmed in all other respects at the appellee‘s cost.
AFFIRMED IN PART; REVERSED IN PART.