145 Mass. 528 | Mass. | 1888
The committee was an agent of the town, and not a judicial body or a board of public officers, and the ruling of the court that the committee could act only as a body, and not by the agreement of individual members separately obtained, cannot be sustained. Haven v. Lowell, 5 Met. 35.
The defendant contends that the further ruling, that there was no evidence sufficient to show agency on the part of Swasey, or action by the committee, was right, for the reasons that the
The committee was appointed by the defendant town to build a Memorial Hall. Mead, Mason, and Company contracted with the committee to erect the building according to certain specifications. The plaintiff contracted with Mead, Mason, and Company to do all the stone-work according to the specifications. The plaintiff’s bill of particulars contains five items for materials and labor which he contends were not included in his contract with Mead, Mason, and Company, but were furnished under a contract or contracts, between him and the defendant, through the committee and Swasey, the supervising architect. The largest of these items, and the only one in reference to which any evidence was given, is $2500, for brown-stone trimmings for the building. It is not disputed that these trimmings were put in by the plaintiff, and that they were not included in the specifications. The first question is as to the authority of the committee to contract for work outside of the contract with Mead, Mason, and Company.
The Memorial Hall was built under authority of the St. of 1883, o. 119, which authorized the town to borrow for the purpose a sum not exceeding $20,000, but put no limit upon the amount the town might expend.
In November, 1883, a committee, which had been appointed in the April preceding to consider location, plans, and estimates, and to make recommendations, reported, to quote the words of the exceptions, “ recommending the location on which the hall was afterwards built, and the plan and specifications of Frederick Swasey, architect, and reported that the price should not exceed $20,000.” We would say here, that we do not understand by this that the committee recommended that the town should vote that the cost of the building should not exceed $20,000, but that they expressed the opinion that it would not, meaning the same as if they had said “ ought not ” or “ would not.” In the absence of the language of the report, and upon the mere statement of its substance, the plaintiff ought not to be bound by a meaning that is not clear, and the fact that this is not among the things recommended in the
At a town meeting in March, 1884, the following votes were passed : “Voted, that the report and plans of the Memorial Hall committee be adopted. Amended : also location adopted. Also that the same committee locate and build the same. Voted, that, for the purpose of building a Memorial Hall, we raise by taxation the sum of $2000, and the town borrow the sum of $20,000, payable in equal instalments of $5000, in one, two, three, and four years.”
The specifications reported by the committee in November, 1883, so far as material, were as follows : “ Specifications of material and labor required in the erection and entire completion of a Memorial Building for the town of Milford, said building to be erected on the corner of Spruce and School streets in said Milford, and to be built in accordance with drawings and these specifications, furnished by Frederick Swasey, architect, of said Milford, and under his superintendence. Conditions. The contract will include all labor and material necessary to carry into entire completion all the works of every name and nature shown by drawings, except such parts as the specifications expressly designate to be furnished by the town..... No charge of any kind shall be made for extra work except said work be ordered in writing by said architect. All orders for extra work or claims therefor must be presented to the committee within thirty days from the issue of said order.”
The first question which arises under this action of the town is, whether the plan and specifications reported by the committee were adopted by the town as a limitation upon the powers of the committee. We think that they were, and that the committee was authorized to locate and build only according to the plan and specifications. This would require the committee to make one contract for the completion of the building. They could not materially change the location or the specifications for the building. The town had voted to build according to the specifications, and under one contract for the completion
After the votes of the town, the committee made the contract with Mead, Mason, and Company, by which the price to be paid for the building was $20,324.40. The defendant contends that the committee was limited to an expenditure of $20,000, and that, having contracted for more than that amount, they had no authority to make a contract which involved any further payment. We have already said that we do not regard the vote adopting the report of the committee as a vote that the expenditure should be limited to $20,000.
It is further argued that the committee could not make any contract which involved an expenditure in excess of the whole amount appropriated by the town, $22,000. The vote does not expressly prohibit the committee from incurring liabilities beyond the amount of the appropriation, and we do not think that such prohibition can be implied. While it was probably intended to make an appropriation large enough to cover the
The course of the trial is apparent from the exceptions. Th? plaintiff put in documentary evidence to prove the authority given to the committee by the defendant. He then proceeded to prove that authority was given by the committee to Swasey, and that Swasey ordered the work done; and called one Stratton, a member of the committee, and offered to prove by him that three members of the committee, including Swasey, who was a-member of the committee as well as the architect, stated to him that they agreed to the change, and that he agreed to it, and that Swasey, in the presence of the witness, told the plaintiff that he had seen the committee, or a majority of the committee, and they had agreed to have the brown-stone trimmings. The
But if the ruling that the evidence was not sufficient can be separated from the ruling that the evidence of agency was incompetent, and taken as an independent ruling upon evidence in the case, we think that it cannot be sustained. Swasey was the architect, having superintendence of the whole work, and through whom orders for extra work must pass, and was also a member of the committee. The testimony of Stratton was sufficient to show that, after there had been conversations among members of the committee, and between members and the plaintiff, in regard to having brown-stone trimmings, Swasey told the plaintiff that the committee, or a majority of the committee, had agreed to have it done, and that the plaintiff went on and did the work, with the knowledge and approval of the committee, and that the work was accepted by the committee. This was some evidence of agency in Swasey, and of action by the
We think, however, that the ruling must be taken to be a ruling that the evidence offered was not competent to prove any action of the committee, and that the plaintiff had for that reason failed to prove his case, and not as a ruling as to the sufficiency, to prove every part of the plaintiff’s case, of evidence offered only to prove one part, and held to be incompetent for that. Exceptions sustained.