DONNA M. SHEA & another[1]
vs.
BAY STATE GAS COMPANY & another;[2] CAMP DRESSER & McKEE INC., third-party defendant.
Supreme Judicial Court of Massachusetts, Norfolk.
Present: HENNESSEY, C.J., BRAUCHER, KAPLAN, WILKINS, & ABRAMS, JJ.
David W. Kelley for J. Andreassi & Son, Inc.
Francis H. Fox (S. Elaine Renfro with him) for Camp Dresser & McKee Inc.
ABRAMS, J.
The plaintiffs in this action sought damages from the defendants Bay State Gas Company (Bay State) and J. Andreassi & Son, Inc. (Andreassi), for injuries incurred when a gas pipe ruptured near 1044 Turnpike Street, in the town of Canton, causing an accumulation of natural gas and a subsequent explosion in the basement of the building occupied by the plaintiffs. The plaintiffs alleged that Bay State negligently maintained and serviced the gas *219 pipe and that Andreassi was negligent in excavating, backfilling, and inspecting a sewer system in that area, causing the rupture.
Andreassi filed a third-party complaint against Camp Dresser & McKee Inc. (CDM), seeking contribution on the grounds that CDM negligently supervised, tested, and inspected the sewer construction. See G.L.c. 231B, §§ 1, 3. CDM moved for summary judgment on the third-party complaint, claiming that a clause on an insurance certificate requires Andreassi to indemnify CDM against CDM's concurrent negligence. CDM's motion was allowed and the judge entered a judgment dismissing the third-party complaint. The Appeals Court reversed the judgment. Shea v. Bay State Gas Co.,
The essential facts are not in dispute. In April, 1973, CDM and the town of Canton entered into a contract whereby CDM was to provide services as consulting engineers for the construction of a sewer system on Turnpike Street. Those services included basic engineering and inspection services, as well as the preparation of construction plans, specifications and contract documents for the project. On October 18, 1973, Andreassi and Canton executed a contract, based on the documents prepared or provided by CDM, for construction of the sewer system.
Andreassi began construction on the project in September, 1974, and completed the work about one month later. On February 7, 1975, a gas pipe ruptured near 1044 Turnpike Street, causing the explosion which injured the plaintiffs (members of the public). The action against Bay State and Andreassi was filed on November 3, 1975, and, on January 21, 1980, a jury found Bay State and Andreassi negligent.
On May 19, 1978, CDM filed a motion for summary judgment,[3] going on the assumption that, for the purposes *220 of the motion's disposition, CDM is equally at fault with the primary defendants. An affidavit of one of CDM's officers was filed in support of the motion, as well as copies of the contract between CDM and Canton and a certificate of insurance provided to CDM by Andreassi as a result of Andreassi's contract with the town.[4]
CDM was responsible for drafting all documents for the town's use in contracting for the sewer construction. The certificate of insurance was one of these documents. It is signed by an authorized insurance representative and certifies that certain companies have issued policies to Andreassi providing comprehensive insurance protection.[5] At the bottom of the certificate, a paragraph entitled "Contractual *221 Liability" reads in part as follows: "The Contractor [Andreassi] shall at all times indemnify and save harmless the OWNER, CAMP DRESSER & McKEE Inc.... on account of any and all claims, damages, losses, ... arising out of injuries ... caused in whole or in part by the acts, omissions, or neglect of the contractor...."[6]
The issue on appeal is whether the "contractual liability" clause, properly construed, shifts to Andreassi as the general contractor responsibility for CDM's negligence. Andreassi argues two basic points on its claim that CDM is responsible for its own negligence. First, Andreassi argues that the contract of indemnity should be strictly construed. See Boston & Me. R.R. v. T. Stuart & Son,
*222 "Contracts of indemnity are to be fairly and reasonably construed in order to ascertain the intention of the parties and to effectuate the purpose sought to be accomplished." New York, N.H. & H.R.R. v. Walworth Co., supra at 3, quoting from Century Indem. Co. v. Bloom,
Andreassi and CDM each has a written contract with the town. CDM is not engaged in excavation or construction work and Andreassi is not an agent, servant or employee of CDM. CDM relies on the contractual liability clause on the bottom of the certificate of insurance naming CDM. See note 6, supra. CDM asserts that if the clause is not construed to provide CDM with indemnification against its own concurrent negligence, the clause has no content or purpose. The question is, What construction of the contractual liability clause reflects the intent of the parties?
CDM is protected at common law without the agreement if its liability were purely vicarious. See Afienko v. Harvard Club,
Granted, the language of the clause in issue here is less broad and less precise than that in clauses we have previously construed to encompass the indemnitee's negligence, see, e.g., Boston & Me. R.R. v. Hall,
We do not agree with Andreassi's argument that ambiguities in the language of the clause require this matter to be resolved against CDM as the drafter of the instrument. "A prerequisite to the application of [that] rule is that the alternative interpretation placed upon the alleged ambiguity by the contractor be, under all the circumstances, a reasonable and practical one." Gelco Builders & Burjay Constr. Corp. v. United States,
In this case the indemnity clause as we have interpreted it places full responsibility for the proper conduct of the work on the party primarily responsible for it, thus giving the contractor a necessary and desirable incentive to assure both proper performance and appropriate safety measures during the construction process. There was no error in granting CDM's motion for summary judgment.
Judgment of the Superior Court affirmed.
NOTES
Notes
[1] Dennis P. Shea, Jr., husband.
[2] J. Andreassi & Son, Inc.
[3] Andreassi asserts that since CDM failed to plead the indemnity agreement as an affirmative defense in its answer we should deem the point waived. Assuming without deciding that indemnification is an affirmative defense, "affirmative defenses, even though not appearing on the face of the complaint, may be established upon motion ... for summary judgment when, by affidavits, depositions and admissions, a set of undisputed facts is revealed upon which the moving party is entitled to judgment as a matter of law." Suckow Borax Mines Consol. v. Borax Consol.,
[4] The contract between Canton and Andreassi is not in the record.
[5] Coverage was distributed among insurers as follows: Hanover Insurance Co., Owner's Protective Liability; Royal Globe Insurance Companies, Comprehensive General Liability, Auto Liability, Workmen's Compensation; Maryland Casualty Company, Auto Liability, American Home Assurance Company, Comprehensive General Liability, Auto Liability.
[6] The entire paragraph reads as follows: "The contractor shall at all times indemnify and save harmless the OWNER, CAMP DRESSER & McKEE Inc. and their respective officers, agents, and employees, on account of any and all claims, damages, losses, litigation expenses, counsel fees, and compensation arising out of injuries (including death) sustained by or alleged to have been sustained by the officers, agents, and employees of said OWNER or CAMP DRESSER & McKEE Inc., or of the contractor, his subcontractors, or materialmen, and from injuries (including death) sustained by or alleged to have been sustained by the public, any or all persons on or near the work, or by any other person or property, real or personal (including property of said OWNER or CAMP DRESSER & McKEE Inc.) caused in whole or in part by the acts, omissions, or neglect of the contractor including but not limited to any neglect in safeguarding the work or through the use of unacceptable materials in constructing the work of the contractor, any subcontractor, materialman, or anyone directly or indirectly employed by them or any of them while engaged in the performance of the contracts, including the entire elapsed time from the date ordered to start work or the actual start whichever occurs first until completion of the guarantee period, as certified by the OWNER or CAMP DRESSER & McKEE Inc."
[7] Andreassi also claims that the contractual liability clause is not a contract. Andreassi's contract with the town is not included in the record. However, it is undisputed that the contractual liability clause was provided by Andreassi pursuant to its contract with the town and names CDM in its text. In these circumstances, CDM is an appropriate party to raise the issue of the proper scope of the clause.
[8] The strict construction rule originally was developed to ensure that the party assuming the liability understood the breadth of the undertaking. See Boston & Me. R.R. v. T. Stuart & Son,
[9] The shift in liability could have been more artfully phrased. See, e.g., the clause quoted by the Appeals Court in Shea v. Bay State Gas Co.,
