Shawnee Coal Company v. Cecil D. Andrus, Secretary of the InteriorShawnee Coal Company v. Cecil D. Andrus, Secretary of the Interior
The issue in this case is whether the district court erred in asserting jurisdiction over an action to enjoin the Secretary of the Interior from enforcing certain provisions of the Surface Mining Control and Reclamation Act of 1977,
I.
BACKGROUND
The Surface Mining Act is a comprehensive statute designed to “establish a nationwide program to protect society and the environment from the adverse effects of surface coal mining operations.” § 102(a),
The Act’s principal regulatory and enforcement provisions are contained in Title V, which establishes a two-tiered regulatory program to achieve the purposes of the statute. The two tiers consist of an interim regulatory program and a permanent regulatory program. § 501(a) of the Act,
§ 502(c) of the Act,
The second tier of regulation contemplated by the Surface Mining Act, the permanent phase, is provided for in § 501(b),
During the permanent phase, a state may seek to assume primary jurisdiction over the regulation of surface coal mining on “non-Federal lands” within its borders by submitting a proposed “State program” of regulation to the Secretary. § 503(a),
. Under § 521(a)(2),
Under § 518,
Section 525 of the Act,
An operator may also apply to the Secretary for temporary relief from any notice or order. The Secretary may grant such temporary relief if there is a substantial likelihood that the applicant will prevail on the merits, and the relief will not adversely affect the public health or safety or cause significant, imminent environmental harm. § 525(c),
If temporary relief from a cessation order is denied by the Secretary, the applicant may seek immediate review directly in the United States District Court for the district in which the surface mine is located. § 526(c),
B.
Pursuant to a mining permit issued by the State of Ohio, Shawnee Coal Co. operated a surface coal mine in Perry County, Ohio, until December, 1978. At the same site Shawnee operated a coal tipple — a processing operation consisting of machinery that crushed and prepared coal for transport. Although Shawnee terminated its mining operations at the site relevant here
On September 5, 1979, federal mine inspectors from the Interior Department’s Office of Surface Mining Reclamation and Enforcement inspected the Shawnee mine site and tipple operation. That inspection led to the issuance of notices of four violations of the Act.
2
In their final form the notices charged Shawnee with operating a surface mining operation within 100 feet of a road and with failing to meet certain water quality standards in the effluent discharge leaving the tipple site area. Under the notices Shawnee was to abate the violations by November 5, 1979. This period was subsequently extended until December 5, 1979, giving Shawnee the full 90 days permitted under the Act for abating the violations. After that period, § 518(h) of the Act,
The Act also provides that the violations notices specify the measures necessary for abating the violations and the procedures necessary for obtaining administrative review of the notices.
See
The Shawnee tipple was reinspeeted on December 13, 1979 and cessation orders issued for the same violations noticed in Sep
Shawnee then filed the instant action on December 19, 1979, in the United States District Court for the Southern District of Ohio, seeking preliminary and permanent injunctive relief against the Secretary’s enforcement of the orders. In its complaint Shawnee alleged: 1) that its tipple operation was not covered by the Act because it was no longer affiliated with its coal removal operation; 2) that by imposing the $750.00 per day penalties the Secretary, in effect, was forcing Shawnee to surrender its right to appeal; 3) that the abatement methods required by the Secretary were unreasonable; and 4) that the Secretary’s decision to apply the Act to tipples formerly associated with a surface mine but not to tipples operating independently from any surface mine violated Shawnee’s equal protection and due process rights. In response to the complaint the district court granted a temporary restraining order on December 19,1979. On December 26,1979, the Secretary moved to dismiss the complaint and dissolve the TRO on the grounds that Shawnee had failed to exhaust its administrative remedies. The Secretary argued that before Shawnee could seek relief in a district court, it was required to seek temporary relief from the Secretary' under § 525(c) of the Act,
On December 28, 1979, the district court conducted a hearing on Shawnee’s motion for a preliminary injunction. Following the hearing the court granted an injunction enjoining enforcement of the cessation orders against Shawnee until the court rendered a final disposition on the merits of Shawnee’s claims. The district court rejected the Secretary’s contention that Shawnee had failed to exhaust proscribed administrative remedies. Instead, it held that the Act established alternative avenues for review of administrative orders and that under § 526(c) of the Act,
In the district court’s view, the administrative review provisions of the Act were insufficient to prevent irreparable harm to Shawnee because the Secretary was not required to act for five days and even then the Secretary could render temporary relief only after finding that the public would not suffer any significant harm. Finally, the court concluded that § 10(c) of the Administrative Procedure Act,
The only issue with which we must deal is whether the district court had jurisdiction to review and enjoin the Secretary’s issuance of cessation orders under the circumstances present here. The relevant provisions of the Act providing for judicial review state in pertinent part:
Section 1276
(a) (2) Any order or decision issued by the Secretary in a civil penalty proceeding or any other proceeding required to be conducted pursuant to Section 554 of Title 5 shall be subject to judicial review on or before 30 days from the date of such order or decision in accordance with subsection (b) of this section in the United States District Court for the district in which the surface coal mining operation is located. * * *
(b) The court shall hear such petition or complaint solely on the record made before the Secretary. Except as provided in subsection (a) of this section, the findings of the Secretary if supported by substantial evidence on the record considered as a whole, shall be conclusive. The court may affirm, vacate, or modify any order or decision or may remand the proceedings to the Secretary for such further action as it may direct.
(c) In the case of a proceeding to review any order or decision issued by the Secretary under this chapter, including an order or decision issued pursuant to subparagraph (c) or (d) ofSection 1275 of this title pertaining to any order issued under subparagraph (a)(2), (a)(3), or (a)(4) ofSection 1271 of this title for cessation of coal mining and reclamation operations, the court may, under such conditions as it may prescribe, grant such temporary relief as it deems appropriate pending final determination of the proceedings j * ijs *
The district court held that
In upholding the Act’s cessation order and temporary relief provisions against due process challenges, the Supreme Court in
Hodel
v.
Virginia Surface Mining & Reclamation Ass’n.,
- U.S. -,
A mine operator aggrieved by an immediate cessation order issued under § 521(a)(2) or by a cessation order issued after a notice of violation and expiration of an abatement period under § 521(a)(3) may immediately request temporary relief from the Secretary, and the Secretary must respond to the request within 5 days of its receipt. § 525(c),30 U.S.C. § 1257 . [Sic.] Section 526(c) of the Act. SO U.S.C.§ 1276(c) , authorizes judicial review of a decision by the Secretary denying temporary relief. In addition, cessation orders are subject to informal administrative review under § 521(a)(5), and formal administrative review, including an adjudicatory hearing,, under § 525(b),30 U.S.C. § 1275(b) . The Secretary’s decision in the formal review proceeding is subject to judicial review pursuant to § 526(a)(2),30 U.S.C. § 1276(a) .
(footnote omitted) (emphasis added).
This synopsis of the Act accurately describes the function and .operation of § 526(c),
Section 525 of the Act reflects Congress’ desire to assure expeditious review and due process for parties seeking administrative relief of enforcement decisions of the Secretary under the provisions of § 521. It sets forth clear and definitive review procedures for all notices of violation and cessation orders. § 525(a)(1) allows a permitee or person adversely affected by an order of the Secretary to apply to the Secretary for relief, and in that event requires the Secretary to conduct an appropriate investigation. The complaining party is provided a public hearing at which information relating to the notice or order may be presented. After the investigatory process is completed the Secretary must make findings of fact in issuing a written decision. Where the application for review concerns an order for cessation of surface coal mining and reclamation operations, the Secretary is obligated to issue a written decision within thirty days of receipt of the application for review. § 525(b).
Congress recognized that certain circumstances would not permit even so much as a thirty day process. Thus, in § 525(c), it provided for more immediate relief. Pending completion of an investigation by the Secretary, any applicant may petition the Secretary for temporary relief from any order; the Secretary must respond by issuing an order granting or denying relief expeditiously. When the applicant requests relief from any order for cessation of coal mining and reclamation operations, an order responding to the request must be promulgated within five days.
7
In the event
The logic of the operation of the Act’s administrative relief procedures is clear when applied to the cessation orders issued against Shawnee. When the notices of violations were issued on September 5, 1979, Shawnee became entitled to seek administrative review before the Secretary. Had it sought such relief it may well have received a decision on the merits before it was ordered to abate the violations or cease operations. More importantly, had it sought temporary relief under § 525(c) when the cessation orders issued on December 13, 1979, the Secretary would have been forced to grant or deny relief within five days. Thus, Shawnee could have received the relief it ultimately sought, administratively, before it filed this lawsuit on December 19, 1979.
The ready availability of adequate administrative relief also dictates that an aggrieved party exhaust its administrative remedies before procuring judicial review.
Seepe v. Dept. of the Navy,
In the Surface Mining Act Congress has provided a well-defined administrative system for resolution of enforcement actions stemming from cessation orders. Given this machinery, we are reluctant to permit a district court to interrupt the Secretary’s determinations. Bypassing the administrative remedies would impair the expeditious resolution of disputes and result in the forfeiture of administrative expertise. By circumventing the proscribed procedures, quick resort to the district court could easily preclude the Secretary from building a factual record, from clarifying or narrowing the dispute, or from resolving the controversy altogether so as to obviate the necessity for judicial intervention. Accordingly, we conclude that Shawnee was required to exhaust its administrative remedies by seeking review and relief pursuant to Section 525 before obtaining judicial review under Section 526(c).
Although exhaustion of administrative remedies is typically required as a condition
Another exception to the exhaustion doctrine is that a litigant may bypass available administrative procedures where there is a readily observable usurpation of power not granted to the agency by Congress.
Leedom v. Kyne,
The
Leedom
jurisdiction exception to the exhaustion doctrine is not automatically invoked whenever a challenge to the scope of an agency’s authority is raised. On the contrary, it is a narrow anomaly reserved for extreme situations.
See American General Ins. Co. v. FTC,
In many circumstances it is easier to theorize than to discern when an agency’s action is so far out of bounds, so beyond the realm of its delegated authority that the
Leedom
exception should be invoked. In grappling with this problem the courts have employed three criteria for determining whether the exhaustion requirement should be waived: 1) is the agency’s jurisdiction conspicuously lacking; 2) will the agency’s expertise assist in resolving the jurisdictional issue; and 3) will exhaustion of administrative remedies result in irreparable harm to the claimant.
See Marshall v. Burlington Northern, Inc.,
In deciding the “jurisdictional appearance” issue, the initial focus is on Shawnee’s contention that the Secretary exceeded his authority because Shawnee’s tipple is not an “activity ... in connection with a surface coal mine ...”
The scope of surface coal mining operations covered by the Act is exceptionally broad. Section 701(28),
Activities conducted on the surface lands in connection with a surface coal mine * * *. Such activities include * * * the cleaning, concentrating, loading of coal for interstate commerce at or near the mine site. * * * and the areas upon which such activities occur (including) stockpiles * * * processing areas * * * and other areas upon which are sited structures, facilities, or other property or materials on the surface; resulting from or incident to such activities.
This provision leaves little doubt that Congress intended tippling operations to fall within the Act’s ambit. And for the reasons outlined in In re Permanent Surface Mining Regulation Litigation, (D.D.C.1980) (No. 79-1144) we conclude that Congress intended the Act to encompass off-site processing operations, such as Shawnee’s tippling operation. On this point then, there is every indication that the Secretary correctly asserted jurisdiction over Shawnee. 8
In the district court Shawnee also argued that it is not an “operator” as that term is defined in § 701(13),
The second prong of the test examines whether the agency’s expertise will be helpful in deciding the jurisdictional challenge. In this case the jurisdictional answer will be provided by applying the statute to the facts. Agency expertise is particularly helpful when a question turns on such analysis.
McKart, supra,
Finally, we must consider whether exhaustion of administrative remedies would have resulted in irreparable harm to Shawnee. The district court found that Shawnee would suffer such harm because upon receipt of the cessation order it was faced with the choice of shutting down or incurring a $750.00 per day penalty for each violation. That analysis ignores the temporary relief provisions expressly provided in the Act; first with the Secretary and subsequently, if necessary, in district court, Shawnee could have sought suspension of the cessation orders. If either the Secretary or the court had granted temporary relief, not only could operations continue, but any penalty assessed, as here, under § 518(h),
Shawnee has also argued that exhaustion was not required because Section 10(c) of the Administrative Procedure Act,
The decision of the district court is reversed and the case is remanded to the district court for vacation of the injunction entered against the Secretary.
Notes
. At the time of this litigation the State of Ohio had submitted a proposed state program to the Secretary of the Interior for approval, but the Secretary had not yet acted on that proposal. Thus, the interim regulatory program was in effect.
. The notices were issued pursuant to §§ 521(a)(3) and 522(e)(4) of the Act,
“1. Violation of (§ 1272(e)(4))
Remove coal mines and sediment from (within 100 feet of) S.R. 155 feet drainage ditch between C.R. 44 and TWP RD 275 and either; (2) pull back all operations beyond 100 feet ... or obtain permission from State of Ohio.
2. Violation of § 715.17(a) of Federal Interim Regulations
Pass all drainage ... through a sedimentation pond or series of sedimentation ponds before leaving permit area.
3. Violation of § 715.17(a) of Federal Interim Regulations
Install .. . facilities to treat any water discharged (which violate certain unspecified effluent limitations)”
4. Violation of § 715.17(1)(4), Federal Interim Regulations
“Failure to construct access and haul roads associated culverts and ditches so as to prevent additional contributions of suspended solids to streamflow or to runoff outside the permit area ...”
The fourth claimed violation was vacated by the Secretary on December 7, 1979.
. Shawnee contended that the citation for a § 522(e)(4) violation, (operating a mining facility within 100 feet of a road) was invalid because that section of the Act did not apply to operations, such as Shawnee’s, in existence on the effective date of the Act, August 3, 1977. At the district court hearing the Secretary did not challenge this contention.
. It appears that Shawnee considered the water quality violations impossible to abate because the main water line supplying the Village of Shawnee ran under the only area available for construction of sedimentation ponds and treatment facilities. The water quality problem apparently resulted from the coal fines (an inferi- or coal product) stored near the tipple; the market for fines was depressed, and the fines would not be removed until at least June, 1980.
. In considering the issuance of injunctive relief, the district court employed the traditional criteria for such relief,
see Mason County Medical Association v. Knebel,
(1) all parties to the proceedings have been notified and given an opportunity to be heard on a request for temporary relief;
(2) the person requesting such relief shows that there is substantial likelihood that he will prevail on the merits of the final determination of the proceeding; and
(3) such relief will not adversely affect the public health or safety or cause significantenvironmental harm to land, air, or water resources.
The chief difference between these criteria and the traditional standards is that the statute does not specify any consideration of irreparable harm to the plaintiff but rather contains a distinct preoccupation with the public health and environmental consequences. The district court below acknowledged the existence of the statutory criteria but did not explain its reasons, if any, for disregarding them.
In a comparable case,
Virginia Surface Mining and Reclamation Ass'n. v. Andrus,
. Unfortunately, the legislative history of the Surface Mining Act offers no insight into the relationship between the Secretary’s actions in issuing cessation orders and the scope of district court jurisdiction contemplated by Congress. See H.R.Rep.No. 218, 95th Cong., 1st Sess., reprinted in 1977 U.S.Code Cong. & Ad. News 593.
. The district court below concluded that this form of administrative relief was “insufficient” because the Secretary need not act for five days and even then must refuse relief unless it appears that the applicant will prevail on the merits and there will be no significant environmental harm caused by granting the relief. The Supreme Court in
Hodel, supra,
squarely rejected a similar indictment aimed at the adequacy of the administrative relief provisions. After concluding that the statutorily prescribed time was satisfactory, the Court closed with
. The district court relied on the decision of the Board of Surface Mining Appeals in Western Engineering, Inc., 1 IBSMA 202 (1979). There, the IBSMA held that a wholly independent coal transportation company which never removed or owned any of the coal it processed was not covered by the Act. This decision would not, without more, protect Shawnee because Shawnee has mined coal and owns the coal it processes. Moreover, in a subsequent decision the IBSMA limited Western Engineering to its facts in refusing to hold that all independent tipple operators are excluded from the Act. Ross Tipple v. OSM, 1 IBSMA 303 (1979). This holding was reaffirmed in Drummond Coal Co., 2 IBSMA 96 (1980), and in Bethlehem Mines Corp., 2 IBSMA 215 (1980).