Shawangunk Mountain Environmental Ass'n v. Planning Board of the Town of GardinerShawangunk Mountain Environmental Ass'n v. Planning Board of the Town of Gardiner
OPINION OF THE COURT
This proceeding was commenced to challenge the validity of a determination under the State Environmental Quality Review Act (ECL art 8) (hereinafter SEQRA) by respondent that a proposed residential subdivision in the Town of Gardiner, Ulster County, had no significant environmental effect (hereinafter the negative declaration) and was, therefore, approved.
The subdivision plan of intervenor, Petone, Inc., provided for some 17 residential lots, finally reduced to 13, within a tract of some 253 acres
There should be a reversal. It is uncontested that the Shawangunk region where this subdivision is situated is an environmentally important area. It is also agreed to by all parties that the project is a Type I action which, under the regulations of the Department of Environmental Conservation (hereinafter DEC), is deemed more likely to require the preparation of an environmental impact statement (hereinafter EIS) (see, 6 NYCRR 617.12 [a]). The highly significant environmental effects of this project were early recognized by respondent’s
According to the consultant’s affidavit, by letter of October 18, 1988 Petone submitted revisions of the proposal setting forth new restrictions on lot clearing and grading, improvements in the storm water management system, changes in the design of the subdivision road and a stipulated requirement of individual site plan approval for buildings, septic fields, driveways and stream crossings. The modifications were, in the judgment of respondent’s consultant, sufficient to eliminate the significant environmental concerns he had to the point that he could recommend the issuance of a negative declaration, and respondent followed this recommendation at its meeting that evening.
While we have no doubt that respondent and its consultant acted under a good-faith belief that the mitigating measures agreed to by Petone were sufficient to safeguard against adverse environmental risks, the procedure employed to achieve the negative declaration violated both the letter and the spirit of SEQRA and its implementing regulations. "The heart of SEQRA is the Environmental Impact Statement (EIS) process” (Matter of Jackson v New York State Urban Dev. Corp.,
Clearly, despite the fact that the project was initially found to entail a substantial number of highly significant environmental risks, i.e., "potential large impact[s]”, and its scope as approved remains largely the same as originally proposed, environmental review was cut short by the negative declaration, without the procedural safeguards of the EIS process, and without any assurance that the substantive requirements of SEQRA have been met. Most notably, there was no review of possible alternatives (including no action) which has also been characterized as the "heart of the SEQRA process” (Marsh, Symposium on the New York State Environmental Quality Review Act Introduction—SEQRA’s Scope and Objectives, 46 Alb L Rev 1097, 1111 [1982]). Nor was the lead time between Petone’s submission of final revisions on October 18, 1988 and respondent’s approval the same date, sufficient for. public disclosure and feedback as would have been the case had environmental review of this project been processed through an EIS.
Respondent’s determination was, at best, equivalent to a conditioned negative declaration, a dispositional option only permitted under the regulations for unlisted actions, not Type I actions such as this (see, 6 NYCRR 617.2 [h]). Although the negative declaration states that the mitigations respondent found sufficient to eliminate all environmental effects were "proposed by the applicant and made part of the filed applica
For all the foregoing reasons, the negative declaration and subdivision approval cannot stand. In so ruling, we do not necessarily imply that in any Type I action mitigating measures incorporated in the proposal may never justify a negative declaration. Here, however, the environmental risks were identified as pervasive and quite serious and the mitigations, introduced at the behest of the lead agency, did not substantially reduce the scope of the project. Under such circumstances, an EIS was required as a matter of law.
Kane, J. P., Weiss, Mikoll and Yesawich, Jr., JJ., concur.
Judgment reversed, on the law, with costs, determination annulled, petition granted and matter remitted to respondent for further proceedings not inconsistent with this court’s decision.
Notes
One lot contained 143 acres, the remaining lots ranged in size from 4 to 17 acres.