Opinion
we are called upon to interpret Code of Civil Procedure section 1286.6, subdivision (a); more specifically, to determine the meaning of the words “evident miscalculation of figures” as they apply to the arbitrator’s authority to correct an award previously made.
A dispute which had arisen between property owners and the contractor they hired to construct their residence was submitted to arbitration. After two days of hearings, the arbitrator made his award and the owners applied for a correction, claiming an error had been made. The arbitrator agreed and amended the award by increasing the amount of damages and also granted the owners’ motion for additional attorneys fees and costs. The owners petitioned the superior court to have the amended award approved, and the contractor petitioned to have the original award approved. The superior court approved the original award and vacated the amended award, finding that the arbitrator had no authority to amend the original award. The owners appeal, contending the amended award should have been confirmed. Meanwhile, owners accepted payment of the original award and contractor asserts the appeal should be dismissed as moot. We affirm the confirmation of the original award and the vacation of the amended award.
Richard and Diane Severtson entered into a contract with Bill Williams, doing business as Williams Construction Company, to construct a single-family dwelling. The Severtsons alleged defective workmanship and sued Williams in superior court. Williams cross-complained for monies due. By stipulation of the parties, it was agreed that the matter be arbitrated and that the arbitrator’s decision would be binding. Oral and documentary evidence was presented to the arbitrator on two hearing dates. The matter was submitted; written arguments were prepared and filed. The arbitrator made his written award in favor of the Severtsons with a minor offset in favor of Williams and provided each party with a letter stating the reasons for the award. The major item of damages was found to be $15,000 to correct the exterior siding which included removal of the existing knotty pine siding found to be inappropriate for exterior use, repapering, fixing of flashing and installing tongue and groove cedar on all exterior walls. In addition, the arbitrator awarded the Severtsons attorneys fees and costs.
The Severtsons then filed an application to arbitrator to correct award and motion to recover attorneys fees and costs after decision. Both were granted. In an amended award, the arbitrator increased the damages by $6,408 and granted additional attorney fees and costs to include the period during the hearing and for preparation of the briefs and written arguments. In addition, the Severtsons were awarded expert witness fees. A letter of explanation of the amended award was provided. From the letters accompanying the awards and a declaration of the arbitrator accompanying the motion for confirmation of the amended award, the rationale for the amendment was presented.
Issues
The questions on appeal are (1) whether the arbitrator’s action in amending the award was within his authority as a correction of an evident miscalculation of figures; (2) whether an arbitrator has authority to amend an award to increase attorneys fees and costs and provide for expert witness fees; and (3) whether the appeal is rendered moot by appellants’ accepting the amount of the original award.
Discussion
California has a comprehensive statutory arbitration scheme. (Code Civ. Proc., § 1280 et seq.)
1
The parties to this litigation voluntarily agreed
The statutory scheme provides a process for correction of an arbitrator’s award by the arbitrator under certain limited conditions. 2 The arbitrator purported herein to act pursuant to sections 1284 and 1286.6, subdivision (a), which provides for correction in the event of an “evident miscalculation of figures.”
Evident Miscalculation of Figures
A review of the documentation surrounding the award provides the factual background for the trial court’s action. The correction concerned what the arbitrator later characterized as a miscalculation of the costs of removing the knotty pine siding to replace it with cedar.
In the letter accompanying the original award,
3
the arbitrator indicated that he considered the bid of a Mr. Bartels which specified the amount of $11,634 “to remove and install one-half inch plywood” over the frame
In his declaration accompanying the motion for confirmation of the amended award, the arbitrator asserted his reliance upon the Bartels proposal, but stated he believed the $11,634 figure to “[r]emove and install l/>” plywood over frame walls” meant to remove the existing pine exterior siding. The arbitrator stated that he did not believe that all of the exterior siding needed to be removed and chose instead to award the lesser sum of $5,226 for that task. The latter figure was then added to item 2 of the proposal which indicated a cost of $9,774 to install tongue and groove cedar on all exterior walls. When presented with the application to correct, the arbitrator states that in reviewing the testimony given at the hearing, it became clear to him that Bartels used the word “remove” in item 4 to refer to removing the windows which had to be done in any case. Thus, the total cost to repair the exterior walls was the sum of item 4 ($11,634) plus item 2 ($9,774), or a total of $21,408. The arbitrator thereupon corrected the award by adding the difference of $6,408.
The Severtsons characterize the original award as a miscalculation of figures; Williams urges that the correction was not a miscalculation, but a misinterpretation of the evidence. Both the original award and the amended award simply set forth the dollar amount entitlements, there being no statement of rationale contained therein.
The arbitrator’s award must be in writing. (§ 1283.4.) The award need not, however, set forth findings of fact or a statement of reasons. The award is valid as long as it serves to settle the entire controversy and simply state that one party pay the other a sum of money.
(Sapp
v.
Barenfeld
(1949)
Review of arbitration awards is restricted. Only a limited form of judicial review is provided by statute. The arbitrator’s findings on questions
Correction of an award is likewise restricted to the narrow statutory grounds, “and a dissatisfied litigant is limited thereto.”
(Durand
v.
Wilshire Ins. Co.
(1969)
Webster’s Third New International Dictionary (1981) page 789, defines “evident” as “capable of being perceived . . . clear to the understanding: Obvious, Manifest, Apparent . . . Apparent, Patent, Manifest, Plain, Clear, Distinct, Obvious, Palpable, along with Evident, are often interchangeable without much variation in meaning, implication, or suggestion . . . .”
The definition adopted in
Matter of Hermance et al.
(1877)
In applying the
Hermanee
definition to the instant case, no evident miscalculation can be discerned. An examination of the original award and accompanying letter would not reveal any miscalculation, but a deliberate choice rejecting certain items of evidence. It was well within the province of the arbitrator to reject the Bartels proposal of $11,634 to “remove”
Carolina Va. Fash. Exhibitors
v.
Gunter
(1979)
The case of
First National Oil Corp. and Arrieta
(1956)
The miscalculation, to be evident, must appear
on the face
of the award (see
DeMello
v.
Souza
(1973)
Attorneys ’ Fees and Costs
The parties’ stipulation to arbitrate this case expressly provided that they would equally share the arbitrator’s fee, but did not mention payment of attorneys’ fees and costs. Section 1284.2 provides that in absence of agreement of the parties or where the arbitration agreement does not otherwise provide, each party shall pay a pro rata share of the expenses and fees of the arbitrator and the other expenses of arbitration incurred or approved by the arbitrator, not including attorneys’ fees or witness fees or other expenses incurred for the party’s own benefit.
However, the parties’ construction contract provided in paragraph 6 that “[i]n the event Contractor shall employ an attorney or bring suit . . . Contractor shall be entitled to reasonable attorney’s fees and expenses of litigation.” Civil Code section 1717 makes such clauses mutual so that when a contract provides for only a particular party to be awarded fees and costs, the prevailing party obtains the right.
(Reynolds Metals Co.
v.
Alperson
(1979)
The Severtsons argue that the award of additional attorneys’ fees and costs, including the expert witness fee, was appropriate because the prevailing party could not be known until the arbitrator made his award, and only thereafter could a full cost bill be prepared. The parties, however, put on evidence of attorneys’ fees and costs at the original hearing. The arbitrator, in the letter accompanying the original award, found the Severtsons to be the prevailing party and noted that the Severtsons’ attorney had produced an exhibit outlining attorney’s fees for service up to but not in-
Mootness
While the appeal was pending, Williams tendered the full amount of the original award and the Severtsons provided a full satisfaction of judgment.
Trollope
v.
Jeffries
(1976)
The judgment is affirmed.
Stone, P. J., and Abbe, J., concurred.
Notes
Assigned by the Chairperson of the Judicial Council.
All further statutory references are to the Code of Civil Procedure unless otherwise noted.
Section 1284 provides: “The arbitrators, upon written application of a party to the arbitration, may correct the award upon any of the grounds set forth in subdivisions (a) and (c) of Section 1286.6 . . . .”
Section 1286.6 provides for correction if “(a) There was an evident miscalculation of figures or an evident mistake in the description of any person, thing or property referred to in the award; [H] . . . [f] (c) The award is imperfect in a matter of form, not affecting the merits of the controversy.” (In addition to these grounds, a court can also act pursuant to subdivision (b) to correct the award if arbitrators exceeded their powers, but only if correction can be accomplished without affecting the merits of the decision.)
The arbitrator’s letter accompanying the original award set forth his reasoning and calculations on that subject on pages 4 and 5, as follows:
“The award of damages with respect to the exterior siding is based upon the bid of Mr. Bartels (Plaintiffs’ Exhibit 6). Mr. Bartels bid specifies an amount of $11,634.00 to remove and install one-half inch plywood over the frame walls and then either the sum of $10,233.00 to install shakes on all exterior walls or the sum of $9,774.00 to install tongue and groove cedar on all exterior walls. It does not appear to me that either the original plans prepared by the architect, Mr. Jolly, or the revised plans prepared by Mr. Williams called for plywood over the frame walls before application of the siding. Under the circumstances, it is my view that Plaintiffs did not bargain for such plywood and there is no reason to make an award of damages at this time requiring Defendants to provide it. It is my conclusion that the award should only include the cost of removing the existing siding and installing it [sic] its place tongue and groove cedar siding. Because of my conclusions in this regard, none of the above-mentioned figures of Mr. Bartels quite responds to the costs involved and I have awarded the sum of $15,000.00 which appears to me to be within the evidence and estimates the cost of removing the existing siding, but does not include the cost of installing half inch plywood.” (Italics added.)
