The plaintiff Seppala & Aho Construction Co., Inc. (Seppala & Aho), junior creditor of the mortgagor, Ronrino Realty Trust (Ronrino), brought a bill in equity in the Superior Court against the first mortgagee, the trustees of Fidelco Growth Investors (Fidelco). The bill alleged that Fidelco had violated a duty owed to the plaintiff to exercise due diligence to commence proceedings to foreclose a mortgage on real estate in Leominster, and that as a result of Fidelco’s delay Seppala & Aho lost its lien on the mortgagor’s equity in the property. The trial judge found for the plaintiff, and awarded damages of $85,000, with interest. Fidelco’s appeal was entered in the Appeals Court, and we transferred the case here. G. L. c. 211A, § 10 (A). There is before us the judge’s report of material facts and a transcript of the evidence. We reverse because in the circumstances of this case Fidelco was under no obligation to commence foreclosure proceedings promptly after Ronrino’s default.
We summarize the facts. In November, 1970, Irvin Freedman and Albert Zimmerman, the trustees of Ron-rino, entered into a construction contract with Seppala & *318 Aho to construct two industrial buildings on land in Jytek Industrial Park in Leominster, for $750,000, to be completed by May 2,1971.
Seppala & Aho commenced construction despite Ron-rino’s inability to obtain a construction loan. In February, 1971, Seppala & Aho notified Ronrino that construction would stop if no payment was forthcoming. By March, 1971, Seppala & Aho had nearly completed the buildings, and was owed approximately $500,000. Indeed, it appears that at that time Ronrino had not yet purchased the land on which the buildings were constructed.
In March, Fidelco committed $965,000 in first mortgage funds to the project. Further negotiations ensued, particularly regarding Seppala & Aho’s reluctance to finish construction unless it was compensated. Under the agreements that were reached, Fidelco disbursed $800,000 at the loan closing. This sum was applied as follows: Seppala & Aho received $515,000 immediately, $150,000 was deposited in an escrow account which was released to Seppala & Aho in three periodic payments of $50,000 each as construction progressed, and the remaining $135,000 was paid for the land, title insurance costs, legal costs, and closing costs. The balance of $85,000 due to Seppala & Aho on its $750,-000 contract was to be paid on completion of the buildings. This transaction was documented by (1) a mortgage to Fidelco from Ronrino, (2) an escrow agreement, and (3) a modification of the original construction contract between Seppala & Aho and Ronrino whereby no mortgage monies above $800,000 were to be distributed to Ronrino by Fi-delco until Seppala & Aho was paid, and whereby Seppala & Aho could require Ronrino to convey its equity to it if Ronrino defaulted in the required mortgage payments. Fidelco was not a party to the modification agreement.
Ronrino soon defaulted on the mortgage, and in May, 1971, Seppala & Aho agreed to cover the default with funds from the second payment of $50,000 from the escrow account. Ronrino did not make the June or July mortgage payments and Seppala & Aho then brought suit against Ronrino and attached the mortgaged property. On July *319 20, 1971, Fidelco formally advised Seppala & Aho of the default. The buildings were substantially completed by July, and were certified for occupancy in August. There remained a dispute about the installation of the fire alarm system in the larger building, which delayed the issuance of an unconditional certificate of occupancy on that building until February, 1972.
In November, 1971, Fidelco learned that the trustees of Ronrino had moved to Florida. At some point the smaller building was occupied under a lease given by Ronrino and assigned to Fidelco who received the rents, but the larger building remained unoccupied.
In December, 1971, Seppala & Aho expressed concern to Fidelco that the larger building had not been winterized, the heat had not been turned on, pipes had burst, floors had cracked, and vandalism had occurred. Seppala & Aho asked Fidelco to foreclose the mortgage at that time.
In January, 1972, representatives of Seppala & Aho and Fidelco met on the premises. Fidelco authorized Seppala & Aho to winterize the building and install a fire alarm system, and later paid for this work.
Throughout the winter Fidelco, with the assistance of Seppala & Aho, sought a purchaser for the buildings. Negotiations with at least one potential buyer terminated without agreement. Seppala & Aho considered taking a deed in lieu of foreclosure, and assuming the mortgage, but rejected the idea because Ronrino demanded $75,000 above the outstanding indebtedness to Fidelco. On July 13, 1972, Fidelco notified Ronrino of its intention to foreclose the mortgage. On November 27, 1972, Fidelco purchased the property at the foreclosure sale for $990,000, which equaled the total amount of Ronrino’s indebtedness. There had been $800,000 advanced, and $190,000 in charges had accrued in sixteen months after default in July, 1971.
Fidelco sold the large building on March 5, 1973, for $841,000, and the small building on May 18, 1973, for $235,000, a total of $1,076,000.
*320 The judge concluded that as of January, 1972, 2 when Fidelco authorized Seppala & Aho to winterize the unoccupied building, “[f]or all practical purposes Fidelco had taken actual physical possession of the premises under the powers granted to them in the mortgage.” He further found that Fidelco “did not complete the foreclosure with reasonable diligence,... that there was no bad faith on their part in that they attempted to deliberately wipe out ... [Seppala & Aho’s] interest; namely, the $85,000 remaining to be paid upon the construction contract... [and] that there was no fraud or collusion on the part of Fidelco with Ronrino or anyone to deprive Seppala and Aho of the balance due on the contract.” He also found that the fair market value of the property was $1,000,000 in August, 1971, and that the property “was sold at the foreclosure sale for less than its fair market value, as evidenced by the private sale after the foreclosure sale by Fidelco.”
From the default by Ronrino in June, 1971, until the foreclosure sale in November, 1972, Ronrino’s debt to Fi-delco rose from $800,000, to $990,000, by reason of the addition of unpaid interest and other charges. Seppala & Aho claims that had Fidelco foreclosed earlier, the debt would have been smaller — less interest would have accrued — and some equity in the property would have remained to pay Seppala & Aho.
We have frequently stated that the basic rule of law applicable to the foreclosure of real estate mortgages is that “a mortgagee in exercising a power of sale in a mortgage must act in good faith and must use reasonable diligence to protect the interests of the mortgagor.”
West Roxbury Co-op. Bank
v.
Bowser,
The precise question before us is whether Fidelco, by reason of its failure or refusal to foreclose the Ronrino mortgage promptly after the latter’s default, violated any duty owed to Seppala & Aho under the rule stated above.
The judge expressly found that Fidelco was not guilty of any bad faith nor of any attempt deliberately to wipe out Seppala & Aho’s interest, and that there was no fraud or collusion on the part of Fidelco with Ronrino or anyone else to deprive Seppala & Aho of the balance due on the contract. Yet he found in favor of Seppala & Aho in the amount of $85,000. He did so on the basis of findings stated in his decision that (a) Fidelco “did not complete the foreclosure with reasonable diligence,” and (b) “[t]he property in question was sold at the foreclosure sale for less than its fair market value.” We now examine separately these two grounds for the decision.
1. Reasonable diligence in foreclosing mortgage. As a preliminary question we must determine by what events the timeliness of Fidelco’s prosecution of the foreclosure is to be measured. The judge appears to have considered the date of Ronrino’s default, and to have assumed that Fidelco’s meeting with Seppala & Aho on the mortgaged premises on January, 1972, was an entry into possession for the purpose of foreclosing the mortgage. 3 This conclusion is in conflict with the applicable statutes and a number of our decisions which recognize that not every entry by a mortgagee on the mortgaged premises is an entry into possession for the purpose of foreclosure.
By G. L. c. 244, § 1, “[a] mortgagee may, after breach of condition of a mortgage of land, recover possession of
*322
the land mortgaged by an open and peaceable entry thereon...; and possession so obtained, if continued peaceably for three years, shall forever foreclose the right of redemption.” This entry must be accompanied by the prompt recording of a memorandum or certificate of the entry. G. L. c. 244, § 2. See G. L. c. 185, § 70 (registered land). In the absence of such recording, the entry is ineffective for the purposes of foreclosure. G. L. c. 244, § 2.
Fitchburg Co-op. Bank
v.
Normandin,
The record on appeal does not indicate that any memorandum or certificate of entry to foreclose the mortgage was executed or recorded. If the meeting on the premises in January, 1972, can be considered an entry intended for the purposes of foreclosure, which is doubtful, it cannot be considered an “effectual” one in the terms of G. L. c. 244, § 2. See
Corrigan
v.
Payne,
It follows that the timeliness of Fidelco’s completion of foreclosure proceedings must be measured from July 13, 1972, when it sent notice to Ronrino and Seppala & Aho of its intention to foreclose, and petitioned the Superior Court for authority to enter and to exercise the power of sale in accordance with the Soldiers’ and Sailors’ Civil Relief Act of 1940. See
Beaton
v.
Land Court,
Because the record does not contain the pertinent information, the details of Fidelco’s actions in completing *323 the foreclosure cannot be set forth. The record does contain a copy of the notice dated July 13, 1972, and returnable on August 23, 1972, sent by Fidelco to Ronrino and Seppala & Aho under the Soldiers’ and Sailors’ Civil Relief Act. That notice states that the mortgagee has filed a bill asking for authority to foreclose the mortgage “by entry on and possession of the premises ... and by exercise of the power of sale.” It does not appear whether Fidelco did enter into possession, but the judge found that the property was sold at a foreclosure sale on November 27,1972.
We note that G. L. c. 244, § 14, as amended by St. 1975, c. 342, requires the publication of notice of the sale “once in each of three successive weeks, the first publication to be not less than twenty-one days before the day of sale.” Thus, compliance with the minimum statutory time periods for the accomplishment of a foreclosure, without considering whether a mortgagee may wish to advertise more extensively than is provided for by statute, accounted for a good deal of the time between July 13, 1972, and November 27, 1972. Therefore, measuring Fidelco’s diligence by the time between those two dates, the evidence does not warrant the finding that the xoreclosure was not completed with reasonable diligence. However, Seppala & Aho contends that it must be measured from Ronrino’s default in June, 1971. We have found no prior case in our law in which a mortgagee has been held liable in damages for delay in commencing proceedings to foreclose a mortgage.
The effect of delay in commencing foreclosure has been before this court in several analogous contexts. In
City Inst, for Sav.
v.
Kelil,
In
Lewis
v.
Blume,
In
North End Sav. Bank
v.
Snow,
In
Porter
v.
Engel,
These cases, of course, are not dispositive of the present issue, yet they illustrate a reluctance to place a duty on the mortgagee to commence foreclosure promptly after default. The many cases permitting, but not requiring, a mortgagee to adjourn the foreclosure sale show a similar flexibility regarding the timing of foreclosure.
DesLauries
v.
Shea,
Furthermore, G. L. c. 244, § 1, which provides for foreclosure by entry, requires that after an entry to foreclose the possession must continue peaceably for three years before it can ripen into a foreclosure. See
Grabiel
v.
Michelson,
The duty of reasonable diligence has never been construed to compel a mortgagee at his peril to commence foreclosure proceedings promptly after default. Rather this duty requires effort and attention by the mortgagee to conduct the sale of the property fairly and in good faith through the observance of the procedural requirements of the statutes and the mortgage. 6 Indeed, the judge expressly found that there was no bad faith or sharp dealing by Fidelco in this case.
In the absence of such a finding, an award of damages to a junior lienor for a mortgagee’s delay in commencing foreclosure would be unwarranted. We do not exclude the possibility that in an exceptional case delay would bear on the issue of bad faith, but this is hardly such a case. To award damages to a junior lienor for a delay in commencing foreclosure would be tantamount to permitting the mortgagor or junior lienholder to compel foreclosure. We have found no case in American jurisprudence which authorizes such compulsion. 7
Strong reasons of policy support the result we have *327 reached. Mortgagees should not feel compelled to undertake the drastic remedy of foreclosure, thereby terminating the mortgagor’s interest in the property, where alternative accommodations are possible. Temporarily depressed conditions in the real estate market may counsel against foreclosure; a mortgagor may have experienced temporary reverses, but the debt may remain adequately secured. The imposition of a vague duty on a mortgagee to commence foreclosure promptly after default, though beneficial to the plaintiff in this case, could work to the great detriment of mortgagors and junior lienholders generally. Under such a rule mortgagees would no doubt begin foreclosures soon after default rather than risk damage judgments for delay in commencing foreclosure proceedings. In many cases this would wipe out all junior liens along with the owner’s equity of redemption. Such a drastic result should not be compelled.
2. Foreclosure sale price. Fidelco purchased the property at the foreclosure sale for $990,000. The judge found that the property “was sold at the foreclosure sale for less than its fair market value, as evidenced by the private sale after the foreclosure sale by Fidelco____Fidelco sold the large building March 5,1973 for $841,000 and the small building on May 18, 1973 for $235,000,” a $1,076,000 total. It is questionable whether the fact of the sale of the buildings for $1,076,000 in March and May, 1973, supports a conclusion that the foreclosure price of $990,000 was less than the fair market value of the property at the time of the foreclosure sale in November, 1972. However, we need not pursue that point because, even if true, it would not itself form any basis of liability by Fidelco to Seppala & Aho in view of the entire circumstances.
In
Clark
v.
Simmons,
We have stated in a number of our decisions that “[w]hen, as was the fact under the mortgage in this case, a mortgagee rightfully is both seller and buyer, his position is one of great delicacy. Yet, when he has done his full duty to the mortgagor in his conduct of the sale under the power, and the bidding begins, in his capacity as bidder a mortgagee may buy as cheaply as he can, and owes no duty to bid the full value of the property as that value may subsequently be determined.”
Cambridge Sav. Bank
v.
Cronin,
*329
3.
Conclusion.
Applying the rules discussed above to those subsidiary facts which were properly found by the judge, we hold that they do not support a conclusion that Fidelco violated any duty owed by it to Seppala & Aho in the foreclosure of the mortgage in question. The final decree entered on November 29, 1973, is affirmed as to par. 1, dismissing the bill of complaint of Edward G. Shamgo-chian against the trustees of Fidelco, and as to par. 2, dismissing the bill of complaint of Seppala & Aho against Latimer and Buck, Inc., and Latimer and Buck Advisers, Inc. The final decree is vacated as to par. 3 thereof awarding damages of $85,000, plus interest, to Seppala & Aho Construction Co., Inc., against the trustees of Fidelco Growth Investors, and instead judgment is to be entered to the effect that this plaintiff takes nothing against these defendants, and that the action be dismissed as to them. Mass. R. A. P. 28,
So ordered.
Notes
The judge’s findings of fact, by inadvertence, stated that the date was January, 1973.
The judge found that the foreclosure was ten months after “the entry or possession in January.”
See
O’Connell
v.
Everett,
See
Marshall
v.
Francis,
See
Guarino
v.
Farley,
Cases from other jurisdictions hold that a mortgagee may select the time for enforcing his security, and that, in the absence of statute or contract to the contrary, a mortgagor or one claiming under him has no right to compel the mortgagee to foreclose on breach of condition.
Housing Equity Corp.
v.
Joyce,
