108 Wis. 365 | Wis. | 1900
The principal question presented for adjudication is raised by exceptions to the findings of fact respecting the cause of action pleaded by the owner of the building against defendants Jones and Forster for a reformation of the bond indorsed upon the back of the building contract making it run to such owner iiistead of to his architect, Dohmen. The evidence upon which the conclusions of the trial court are based has been examined without disclosing any warrant for this court to say they are clearly against the preponderance of such evidence. Olear and satisfactory evidence of mutual mistake, or of mistake upon one side and fraud upon the other in reducing a contract to writing, is required to -warrant changing such writing with a view to express the actual agreement of the parties. The direct evidence here is substantially all to the effect that the obligors
The court, in failing to charge the contractors, Biemann & Co., with damages for delay in completing the building by the time named in the contract, must have entirely overlooked the provision thereof that “unless the contractor shall notify the architecfcin writing, in each instance, of his intention to claim an extension of time, within twenty-four hours from the time of the occurrence of the alleged cause of delay, he shall thereby waive all right to said extension.” Parties have a right to make such a stipulation in a building contract, and if they do so they are bound by it the same as by any other part of their agreement. If a contractor agree in writing to construct a building without taking reasonable time therefor, or agree that relief from delays caused by unforeseen causes shall depend on claims being
The building was to have been completed by May 22, 1897. It was not finished till July 15, 1897. There was a ■delay of one month and twenty-three days. There was no •evidence of any claims being made for allowances of time as provided in the contract, so the contractors were clearly liable to the appellant Farr, upon the proper rule for computing his damages under the agreement.
That brings us to the necessity of determining, whether the parties agreed upon $10 a day as the amount to be allowed as damages for each day’s delay, or whether that clause in the contract was intended as a mere security for the completion of the building by the time agreed upon, hence should be considered as a penalty and the recoverable damages be limited to such as proof shows Farr actually ■sustained.
The law is too well settled to permit any reasonable controversy in regard to it at this time, that where parties stipulate in their contract for damages in the event of a breach of it, using appropriate language to indicate that the damages are agreed upon in advance, and such damages are ■unreasonable considered as liquidated damages, the,stipulated amount will be construed to be a mere forfeiture or penalty and the recoverable damages be limited to those actually sustained. "While courts adhere to the doctrine that the intention of the parties must govern in regard to whether damages mentioned in their contract are liquidated, they uniformly take such liberties in regard to the matter, based ■on.arbitrary rules of construction, so called, as may be neces.sary to effect judicial notions of equity between parties, guided of course by precedents that are considered to have the force of law, sometimes calling that a penalty which the .parties call stipulated damages, and that which the parties
This court, in harmony with the weight of authority, early adopted the arbitrary rule that where damages may be readily computed and the stipulated damages, so called, are-largely in excess of actual damages, the court will disregard what the parties say they intended, and presume that they intended what is fair and reasonable under the circum-however much that may violate their language. Pierce v. Jung, 10 Wis. 30; Fitzpatrick v. Cottingham, 14 Wis. 219. In Berrinkott v. Traphagen, 39 Wis. 219, there is-found quoted with approval from 3 Parsons, Cont. 156, language to the effect that parties may contract for stipulated damages at their pleasure, but such damages only as the law says are liquidated according to the artificial rules which have been adopted to justify courts in saying what the parties intended are in fact to be regarded as such damages-The most significant of such rules is the one above referred
The rental value of the building is trifling in amount as compared with the stipulated damages, so called, of $10 per day. There was, in the nature of the case, at the time the contract was made, no difficulty to be apprehended in arriving at the actual damages that might arise from mere delay in completing the building. So we have the two elements recognized as controlling the language of parties respecting stipulated damages, first, the amount the parties say they agreed upon is grossly in excess of the actual damages sustained or that could have been reasonably apprehended at the time of making the contract; second, the damages actually sustained are readily ascertainable.
It follows that we must hold that the parties intended the $10 per day as a mere penalty to secure the performance of the contract, and limit the recoverable damages to such as were actually sustained, to wit, $38 per month for fifty-three days, or $67.13, with six per cent, interest thereon from the date the breach of the contract was complete, July 15,1897.
The question is raised as to whether the amount adjudged to defendant Fra/ndi Moody is excessive, and it seems that such question must be answered in the affirmative, in regard to the following matters.
A claim is made that Moody delayed the work of Biemann Co. some forty days; that the company’s delay in large part is attributable to that fact; and that they should recoup in this action for the benefit of themselves and of Farr the damages which such misconduct caused. On the general proposition that Farr is entitled to insist upon all defenses which Biemann & Co. had to Moody's claim, there can be no controversy. It was the duty of Biemann & Co. to defend against the Moody claim in this action upon all the legitimate grounds they had and at their own expense. The statute so expressly provides. Sec. 3315, Stats. 1898.
A careful reading of the evidence leads to the conclusion that Biemann & Co. were delayed in their work, by Moody's breach of contract, for a considerable length of time. It is not deemed necessary here to review in detail the evidence bearing on the subject. Suffice it to say that the evidence has been examined with care and to our minds shows clearly that Biemann & Co.’s breach of contract, in that they did not finish the building till one month and twenty-three days after the time agreed upon, is accounted for to the extent of at least one month by Moody's failure to furnish the mill work as agreed upon, and that he should be charged, as damages, for the rental value of the building for that length of time, or $38, with interest thereon from the time of the breach.
It is claimed that none of the subcontractors’ lien claims are lienable because their rights are referable to the rights of Biemann & Co., and that, as the company stipulated against incumbering the property by liens, the subcontractors must be held to have likewise stipulated. That claim is based upon the following provision of the contract: ■ “It is understood and agreed that all money drawn on this contract shall be held in trust for the owner by the contractor, to be applied in payment of all claims for labor and ma
A further claim is made that the liens were not enforce
Appellants’ counsel refer with confidence to Goodman v. Baerlocher, 88 Wis. 287. The point there decided was that the calls of the statute for a building must be satisfied as a condition precedent to the existence of a lienable claim; that by the terms of the statute a mechanic’s or material-man’s lien can only be acquired on land or the in’terest of the owner of a building in land, in the event of there being a building thereon, in the construction of which such mechanic or materialman contributed labor or material as provided in the statute. In that view it was decided that where there is no building by reason of one partially constructed having been destroyed by fire there can be no lien either in favor of a contractor or subcontractor. All that is said in the opinion should be read -with reference to the point so decided. The reference to Malbon v. Birney, 11 Wis. 107, where it was held that if there is nothing due the principal contractor so he can recover, no recovery can be had by a
Appellants’ counsel urge the point that the court should have held that the bond running to Dohmen was made for the benefit of Farr, and that Jones and Forster were liable,
There are some other points discussed in the briefs of appellants’ counsel. None of them seems to require any special mention in this opinion. All have been covered which in our view of the case can affect the judgment appealed from. The judgment as to plaintiff Gustav Seeman, and defendants Forster Lumber Company, John J. Jones, and Charles G. Forster, was correctly rendered and must be affirmed. The judgment as to defendant Frcmlo Moody must be reduced by $80 and interest, in all $87.31, leaving the total amount of his recoverable claim and costs $415.45. Otto
By the Court.— The judgment of appellant as to Biemmm, Bruenmg, and Koehler is reduced to $574.56. The judgment in favor of Franh Moody is reduced to $415.45. The judgment as a whole as so modified is affirmed. For the purpose of the taxation of attorneys’ fees in this court, all of the lien claimants must be considered as one party and the appellants as one party (Allis v. Meadow Spring D. Co. 67 Wis. 17, 23) and no attorneys’ fees be allowed to either party. Appellant is awarded judgment for clerk’s fees and $25 for printing against respondent Moody, and judgment is awarded in favor of respondents John J. Jones, the Forster Lumber Company, Gustav Seeman, and Charles G. Forster for their disbursements for printing briefs. No other costs than as indicated are to be taxed in favor of any person interested in the appeal.