126 Wis. 370 | Wis. | 1905
Upon the former appeal of this case it was determined that if plaintiff succeeded to the rights of the subcontractor with the consent of the principal contractor, the administratrix of Eobson’s estate, and the defendant as owner, then plaintiff stood as subcontractor in place of the deceased Eobson, and this “put the bank in the shoes of Eobson and constituted it, in truth and in fact, a subcontractor.” 117 Wis. 211, 94 N. W. 74. The plaintiff now claims the right to a subcontractor’s lien against defendant’s property as the party substituted for Eobson after his decease. Plaintiff and defendant assert conflicting claims as to whether the evidence establishes such a substitution. The court held that no such substitution was effected, and we are urged by plaintiff to reverse this conclusion of the court. It is, however, unnecessary to review this question in view of the conclusion we
As indicated, tbe plaintiff asserts tbe right to a subcontractor’s lien under our statute because it has taken the place of Bobson under his contract with King. In this position it is bound by the covenants of the agreement thus assumed, and any rights arising from the execution of the contract by the completion of the flume must be determined under it. It was therein agreed:
“The said builder [plaintiff] shall save and keep the improvement hereinbefore referred to and the lands on which it is situated free from any and all mechanics’ liens and other liens by reason of his work or of any materials or other things used therein; and if said builder fails so to do the owner may retain sufficient of the contract price to pay for the same and all costs by reason of or in consequence thereof, and may pay said lien or liens, if any, and costs, and deduct the amount thereof from said contract price.”
The trial court held this to be an express waiver of the right of the builder to a mechanic’s lien upon the land and the improvements erected thereon. There is no contention but that the right to a mechanic’s lien may be waived by the parties (see Brzezinski v. Neeves, 93 Wis. 561, 67 N. W. 1125; 2 Jones, Liens (2d ed.) § 1500a; Murray v. Earle, 13 S. C. 87), but it is insisted that this provision in the agreement does not constitute1 such a waiver. The language employed, though not the most apt to express a waiver, points with reasonable certainty and directness to the conclusion that the builder was to protect and keep the premises free from all mechanics’ and other liens, and that this protection and freedom from liens was to extend to the builder’s work as well as to any claim for materials used. We think this the evident intention of the parties and the significance of the phraseology employed. By it the right of lien which the law would have awarded plaintiff was waived, and it is precluded from asserting such a claim.
It is urged that only the principal contractor, King, can
It is claimed that defendant is liable to plaintiff for this
Upon plaintiff’s claim for extras the court found that the items of it were not incurred under the Eobson contract, but related to matters entirely outside its terms; that the extra work done and the materials furnished were at the request of defendant’s engineer, under a separate contract with the engineer, and that King never became obligated therefor. The pleadings set out no such claim, but it is sought to include these amounts as a part of the claim against King. The bill of exceptions shows that objections were properly taken to any evidence as to these items, and the trial court properly indicated in its legal conclusions that such evidence was erroneously received and should be so treated in the final result of the trial. This disposition of. the claim was proper, and the ruling must stand.
No grounds for a personal judgment against defendant have been established.
By the Court. — Judgment affirmed.