Seattle Lumber Co. v. Sweeney

43 Wash. 1 | Wash. | 1906

Rudkin, J.

This action was brought to recover a balance due on account of the purchase price of material furnished to he used in the1 construction of certain buildings belonging toi the defendants Sweeney and wife, and to foreclose a lien for the amount thereof; The plaintiff had judgment below, and the defendants Sweeney and wife appeal.

The appellants state in their brief that the most important question presented by the appeal is the construction of § 5900, Bal. Code, which provides that “Every person performing labor upon or furnishing material to he used in the construction ... of any . . . building,” etc., shall have a lien for the same. It is further stated that the respondent contended throughout the trial that it was only necessary for it to show that the material was furnished to- ha used in the buildings, whereas, the appellants contended that it must show not only that the material was furnished to be used in the buildings, hut that the same was actually delivered and used. The court below found, however, that the material was furnished to. he used in the construction of the buildings, and was actually so used, and if this finding is sustained by the testimony, the question suggested by the’ appellants does not arise in this case.

*3While the testimony as to. the delivery of the material and its use in the buildings is not as clear and satisfactory as it might be, yet, there was. competent evidence tending to show these facts and in the absence of any testimony to the contrary, we would not be warranted in disturbing the findings of the court below. The books of the respondent, kept in the usual course of its business, showed that all the material alleged to have been furnished was actually furnished to be used in the construction of the buildings in question. Upon the delivery of material, it was. the custom of the respondent to have the foreman or other person in charge of the buildings receipt to the teamsters for all material delivered, but it sometimes happened that there was. no person about the buildings to sign the receipt, and in such cases the teamster returned the receipt unsigned. A number of the receipts of: fered in evidence in this case were returned in this condition. The architect, who was in charge of the buildings, for at least a portion of the time during their construction, testified to the delivery and use of a portion of the material, and that all the material for which the lien was claimed was actually necessary for the completion of the buildings. It was. eon-ceded that substantially all the; material used in the buildings came from the respondent’s yards, and we think this made a prima facie case in its behalf.

On the other hand, one of the appellants testified that he did not know whether all of the material for which the lien was claimed was actually used in the buildings or not, but that he was reasonably sure that it was- not, and was proceeding to state the reasons for his belief, namely, an estimate made by his architect, when stoppled by the court. He further testified that he was informed that the contractor for the buildings was engaged in the construction of another building in some other portion of the city, but there was no evidence that any material furnished for these buildings was delivered elsewhere. It was further shown that the first delivery of material was made on the wrong corner of the block, *4but this material was afterwards brought back and used in the buildings. Long after the last delivery of material, this same appellant wrote the respondent that his architect had reported to him that he was charged up with several thousand feet of lumber that had never been used in the buildings, that he had directed the architect to go over his figures again, and that he would take the matter upi with the respondent- as soon as the architect made his report. Ko attempt was made to prove by this architect or any other employee or servant of the appellants that all the material for which the lien was claimed was not actually used in the buildings. We allude to this fact, not because the burden was on the appellants to prove that the material was not in fact used in the buildings, but for the purpose of showing that the appellants offered no testimony to defeat the prima facie case made by the respondent, although such testimony was necessarily within their reach. As said by Mr. Justice Brewer in Rice v. Hodge Bros., 26 Kan. 164:

“It is undoubtedly true, that it is not affirmatively and specifically'shown, that each separate article charged in these bills actually went into such buildings. It does appear, however, that each one of the three separate claimants made contracts for furnishing materials for said buildings; that in pursuance of said contracts they furnished materials, and supposed that they were to be used in the construction of said buildings; and, as to a few articles, that they did not in fact go into said buildings. T'o this there is no- contradictory testimony; nothing tending to show that any of the materials so delivered were in fact taken away by the builder and used elsewhere; nothing even tending to- raise a suspicion that there was any deviation of materials from their intended and contracted use. Under these circumstances, it would not be justice to¡ refuse the lien. To require direct and positive testimony, that as to each specific article delivered, that it was in fact used in the buildings, would make the mechanics’ lien law more of a burden and a trap' than a blessing and a help. When materials are contracted for use in a proposed building, when they are delivered in pursuance of such a contract, and when the building is ini fact completed, and there is no *5testimony tending to raise even a suspicion that the materials therefor were elsewhere obtained, or that those contracted for were not used therein, and especially when some of the materials are shown to have actually entered into its construction, it is fair to conclude and say that such materials did in fact go into the building, and that the seller has a mechanics’ lien therefor.”

It is further contended that the persons to whom the material was furnished were not the appellants’ agents and were not authorized to purchase the material on their account. The original order was given by one of the architects for the buildings before the contract was let, but after the letting of the contract the material was furnished to the contractor, and this original order was paid for by the appellants with the exception of a few dollars. The other'material, called extras, was furnished in part while the original contractor was in charge of the construction work, and in part after he had absconded and while the appellants and their servants and employees were in charge. These persons in charge were authorized to construct the buildings, and must have been authorized to obtain material therefor, as the appellants made no provision for material from any other source or at all. Under these circumstances we think that agency either actual or statutory was clearly proved.

The motion for a new trial was properly denied in so> far as it was based on the record before us, and in so far as it was based on newly discovered evidence:, the showing upon which the motion was made does not appear in the record. We therefore cannot consider it. In any event, the only purpose of the newly discovered evidence was to impeach one of the respondent’s witnesses as to the date of the dissolution of a certain partnership, and ordinarily a new trial will not be granted for any such purpose. Furthermore, no showing was made that the date of dissolution, if material, could not have been proved at the trial by other testimony.

We find no error in the record except in the allowance of interest. Through inadvertence: interest was computed on the *6balance due from the 6th day of May, 1901, instead of from the 6th day of May, 1902. It is apparent that this error was not called to the attention of the court below, but the respondent confesses' the error and the item amounting to the sum of $17.32 will be deducted from the judgment. As thus modified the judgment is affirmed, and the respondent will recover its costs on appeal.

Mount, C. J., Fullebton, Hadley, Cbow, and Dunbab, JJ., concur.