33 Wash. 691 | Wash. | 1904
This action was brought to foreclose a materialman’s lien. The lower court sustained a demurrer to the complaint and dismissed the action. Plaintiff appeals.
The facts alleged in the complaint are, substantially, that on March 1, 1902, the defendants Sweeney and wife entered into a contract with George Harwich for the construction of five dwelling houses upon five lots in the city of
“Kotice is hereby given that on the 19th day of March, 1902, the above named claimant, the Seattle Lumber Company, a corporation, at the special instance and request of George Barwick, contractor, and P. J. Donohue, architect, commenced to furnish material, to wit, lumber, to be used upon, and which was actually used in, the construction of those certain five one and one-half story frame dwelling houses, situated on certain lands and premises in King county, state of Washington, described as lots 2, 3, and 4 in block 62, in Kidd’s Addition to the city of Seattle, of which property the owners and reputed owners were Bo Sweeney and Jane Doe Sweeney, his wife, whose true Christian name is unknown, and the furnishing of the said material ceased on the 6th day of May, 1902; that said materials furnished were of the reasonable value of $995.50; that there has been paid on account of the same*694 $706.80, and that there is now due and owing on account thereof the sum of $288.70 and interest from the said 6th day of May, 1902, no part thereof has been paid, and that claimant claims a lien on said property and the whole thereof for the sum of $288.70 and interest as aforesaid.”
Respondent contends that there are three fatal defects in the lien notice, the first being that the notice does not disclose any contractual relations between defendants Sweeney and wife and Barwick and Donohue, at whose instance the materials were furnished, or that defendants Sweeney and wife caused said buildings to be erected. In Warren v. Quade, 3 Wash. 750, 29 Pac. 827, it was held, under § 1667, 1 Hill’s Cpde^ then in force, that the lien notice should state the terms and conditions under which the materials were furnished, and the relation existing between the owner and the builder to whom the materials were furnished, and that it was not sufficient that these facts appear in the complaint. This ruling was followed in several subsequent cases; viz., Tacoma Lumber & Mfg. Co. v. Wilson, 3 Wash. 786, 29 Pac. 829; Heald v. Hodder, 5 Wash. 677, 32 Pac. 728; Fairhaven Land Co. v. Jordan, 5 Wash. 729, 32 Pac. 729; and Collins v. Snoke, 9 Wash. 566, 38 Pac. 161. But in 1893, subsequent to the time of these decisions, the legislature of this state passed a new lien law, the provision requiring a statement of the terms and conditions of the contract was omitted, and a form of lien notice was provided for. § 1667 is now superseded by § 5904, Bal. Code. This latter section provides that a claim for lien substantially in the form provided “shall be sufficient.” The authorities under the old statutes are not in point under the new. The notice in this case is substantially a copy of the form provided for by § 5904, supra, and is therefore sufficient. Young v. Borzone, 26 Wash. 4, 66 Pac. 135, 421.
“The provisions of law relating to liens created by this chapter, and áll proceedings thereunder, shall be liberally construed with a view to effect their objects.”
The object of the lien claim is to give notice to the owner. Where the notice states that the defendants are the owners, this section authorizes the construction that the defendants were the owners at the time the materials were furnished; and where the notice states that defendants were the owners the section authorizes the construction that the defendants are still the owners.
“In every case in which one claim is filed against two or more separate pieces of property owned by the same person, or owned by two or more persons who jointly contracted for labor or material, for which the lien is claimed, the person filing such claim must designate in the claim the amount due him on each piece of property, otherwise the lien of such claim is postponed to other liens. The lien of such claim does not extend beyond the amount designated as against other creditors having liens upon either of such pieces of property.”
The penalty for not designating the amount due on each piece of property is the postponement of the general lien to other liens which do designate the amount due upon a specific property. The effect is not to invalidate the lien notice or the lien. There is no contest of priorities in this ease. The contract for the erection of all the houses upon all the lots was one contract. The lien was clearly authorized under the statute. Wheeler etc. v. Ralph, 4 Wash. 617, 30 Pac. 709; Sullivan v. Treen, 13 Wash. 261, 43 Pac. 38; Phillips v. Gilbert, 101 U. S. 721, 25 L. Ed. 833.
It is next claimed that the lien notice was not filed in time. The complaint alleges that,
“Within ninety days subsequent to the last delivery of said lumber, to wit, on the 4th day of August, 1902, said plaintiff caused to be executed a certain notice and claim of lien . . . a copy of which notice of lien is hereto attached, marked Exhibit A, hereby referred to and made a part of this complaint. (6) That on the same day, to wit, on the 10th day of March, 1902, the said plaintiff caused the said notice and claim of lien to be filed,” etc.
The copy of the notice attached shows that it was filed
The judgment is therefore reversed, and the cause remanded for further proceedings.
Fullerton, O. J., and Hadley, Dunbar, and Anders, JJ., concur.