180 P. 319 | Or. | 1919
Defendants’ first contention is that the complaint fails to state facts sufficient to constitute a cause of action against either of the defendants. Under this division of argument, defendants also submit two assignments of error: Number XLIY. That the court erred in giving to the jury, over the objection and exception of defendants, instruction, to wit:
“If you find for the plaintiff in the particulars complained of, as I have heretofore instructed you, then it will be your duty to determine the fair and reasonable amount it will cost the plaintiff to repair the sewer in the particulars wherein defendant Bandies failed, to the end that plaintiff will have a sewer of the character contracted for, and bring in your verdict accordingly.”
And also assignment Number XLV. That the court erred in giving the instruction to the effect that:
“If you should find that the defendant Bandies failed to lay this sewer in the particulars complained of and that the plaintiff accepted the same without knowledge of such facts, in order to determine the amount, 'if any, the plaintiff is entitled to recover in this case, you have the right to take into consideration*663 the cost to plaintiff of the necessary excavations and work and labor and materials necessary to be employed in making such repairs, as in your judgment from the evidence in this case, shall be required in order to make the sewer correspond with the contract."
It is the main contention of counsel for defendants that the plaintiff cannot recover for the reasons;
First. Under the circumstances presented by the complaint the acceptance of and the payment for the work as completed in accordance with the contract precludes the recovery of damages for patent defects, unless such acceptance and payment were obtained by defendants’ fraud.
Second. The allegations of the complaint failed to state- any facts constituting fraud in the procuring or inducing of the acceptance of payment of the work.
Third. The complaint fails to allege that the city removed the alleged defective work and properly reconstructed the same, stating the expense thereof.
Fourth. That it appears on the face of the complaint that the surety has been released and discharged from all liability.
In order for an acceptance to be a waiver it must be under such circumstances as to show that the party accepting knew or ought to have known that the contract was not fully performed. 6 R. C. L., p. 991, Section 359, where the rule is stated thus:
“Where work is accepted with knowledge that it has not been done according to the contract, or under such circumstances that knowledge of its imperfect performance may be imputed, the acceptance will generally be deemed a waiver of the defective performance. But this rule does not apply to latent defects. The acceptance of work which has been defectively done, the defects being unknown and not discoverable by inspection, does not amount to a waiver of the imperfect performance”: Flannery v. Rohrmayer, 46 Conn. 558 (33 Am. Rep. 36); Van Buskirk v. Murden, 22 Ill. 446 (74 Am. Dec. 163); Brent v. Head, Westervelt & Co., 138 Iowa, 146 (115 N. W. 1106, 16 L. R. A. (N. S.) 801); Ludlow Lumber Co. v. Kuhling, 119 Ky. 251 (83 S. W. 634, 115 Am. St. Rep. 254, and note); Thompson Mfg. Co. v. Gunderson, 106 Wis. 449 (82 N. W. 299, 49 L. R. A. 859); Iaege v. Bossieux, 15 Gratt. (Va.) 83 (76 Am. Dec. 189).
The evidence introduced upon the trial tended to support the allegation of plaintiff’s complaint and to show that soon after the sewer was accepted and Randles, had received his- pay therefor, the sand at many points caved in from the top of the excavation and a large quantity of sand was discovered at the outlets ; that an island of sand was thereby formed in the Necanicum River near where the outlets were. This would cause the ground on top of the sewer to cave in and large holes in several places occurred in the street where the sewer was laid. In many instances, where
That there were about 3,000 feet of the main sewer laid below an elevation of seven feet, which, according to the contract, was required to be laid with a gasket of oakum dipped in hot asphaltum of the proper consistency, and the oakum gasket when thoroughly compacted with a calking iron to fill the bell to one half of its length, after which the joints should be cemented in the manner provided for in the specifications. As a matter of fact, there was no oakum gasket placed in any of the sewer joints at all. The sewer-pipe laid below the elevation of seven feet was laid in the same manner as hereinbefore indicated with an inferior
The evidence also tended to show that there were a number of instances where the sewer-pipe was laid in water. The specifications Required that where water is encountered, it must be drained away before any pipe or concrete is placed in the trench; that Randles, without regard, to this provision, laid the pipes and filled in the cement joints as before indicated, in many instances in running water; that the result was that whatever mortar was placed in the joints was washed out. The proof indicated that Randles designedly and deliberately failed to perform his contract in the manner specified, and perpetrated a fraud upon the city. That the city, officials had no notiée or knowledge of these things, or the fact that the sewer was not constructed according tq the contract at the time of the acceptance; that the contractor deceived the engineer in charge and the inspector; that the pipe being laid in a deep, narrow trench, the defects or failures to cement the joints of the pipe underneath could not be discovered by an ordinary inspection, and the defects should be termed latent; that the city officials believed that the sewer system was constructed in accordance with the contract and did not discover otherwise until 'about the tenth day of January, 1916. It thereupon notified Randles and the surety company to Make the contract good. Randles came several times and made
According to the contract and specifications, neither the engineer nor the inspector was the final arbiter between the parties, it being specially provided in Specification Number 8:
“No inspector shall have the power to waive the obligation of the contractor to furnish good materials or perform sound and reliable work as herein specified; and any failure or omission of the Inspector or Engineer to condemn any defective material or work shall not release the contractor of the obligation to at once tear out, remove and properly reconstrnct the same at his own cost at any time upon the discovery of the defect, and upon receipt of the notice of the Engineer to do so.”
The evidence produced on behalf of plaintiff tended to prove defendant Randles guilty of the fraud, alleged in the complaint, all without knowledge of plaintiff, and that on account of the fraud practiced the sewer was worthless; that plaintiff was thereby induced to and did accept the sewer system under the belief that it was completed according to the terms of the contract ; that Randles not only represented that the work was completed according to the plans and specifications, but after his attention was directed to the condition of the sewer, when he excavated some of the pipe, all that he could on account of the mud around it and reached around under the pipe, he claimed that “there was no trouble with the joints.”
“No part of this sewer shall be constructed in the absence of an inspector, and any work so performed shall be deemed in. violation of these specifications, and the engineer may order the same to be removed by the contractor and reconstructed at once. ’ ’
That the larger part of the sewer was laid in the absence of the inspector; that the inspector and engineer had knowledge of this fact. Therefore, it is contended that this was negligence on the part of the plaintiff which released the surety. This stipulation should be considered with the other provisions of the contract contained in Specification Number 8 to the effect that no inspector shall have power to waive the obligation of the contractor to furnish good material or perform sound and reliable work as therein specified; that any failure of the inspector or engineer to condemn any defective material or work shall not release the contractor of the obligation to properly reconstruct the same at any time upon discovery of the defect, v and upon notice to do so. The fact that work was done in the absence of the inspector or engineer which was not in accordance with the contract, although not objected to either by the inspector or engineer at the time, even if either or both knew the' work 'was being imperfectly done would not be a waiver on the part of plaintiff according to the express terms of the contract.
*673 “Said defendant Eandles performed said work only-in the presence of and under the superintendence and directions of said City Engineer and Inspector and every piece of material and every bit of work furnished, laid and done by said defendant in the prosecution of said work was examined, inspected and approved by said City Engineer and Inspector, and said Engineer and Inspector examined and inspected all of said work and materials while said work was being done and knew how the same was being done and the quality thereof, and they approved and accepted the same.”
And that defendant Eandles performed and completed said work in conformity and accordance with the said contract, plans and specifications. The issue, therefore, was squarely raised as to whether or not the work was done in accordance with the stipulation therefor. We fail to see that negligence on the part of the city engineer or inspector could become material. The surety company in effect claims that by reason of the fact that'Eandles did not construct the sewer in conformity with the requirements of the contract but deceived the engineer and inspector for the city, and made them believe that he did properly construct the system, and defrauded the city, the surety is released. Such claim is not in accordance with the spirit or letter of the bond.
“That if you find from the evidence that defendant Bandies constructed said sewer in accordance with the plans and specifications and that after the sewer was so constructed, it broke down and the joints went to pieced or were broken as alleged in the complaint and the caps or stoppers of the N’s and laterals were' driven out so as to leave the pipes open, but you further find that such breaking or opening of the joints complained of in the complaint were on account of the faulty or defective or unsuitable character of the plans and specifications themselves and.was not due to the faulty or defective material or work of the said de*675 fendant Randles, then the defendants would not be liable for such damage and your verdict in that case would be for the defendants. * * ”
Under the testimony in this case, we think the ruling was correct and that the instructions properly submitted the question to the jury.
Error is predicated upon the refusal of the court to permit John Matson, Randles’ foreman, to testify that the engineer in charge of the work instructed him to leave out the oakum gaskets at the places required by the specifications. The defendants, by their answer, expressly alleged that Randles had performed the contract fully in accordance with the terms and conditions thereof. The court plainly told the jury that:
“If you find from the evidence that defendant Randles laid the pipe in accordance with the contract and specification in the instances I have indicated, then this will end the case and your verdict must be for the defendant.”
The court further charged that:
“If the plaintiff, through its council, at the time it accepted and paid for the sewer, knew that Randles had not performed his contract in these particulars and had not filled these joints accordingly as provided by the specifications, as I have heretofore suggested, and with such knowledge, approved and accepted the work, then plaintiff cannot recover.”
Assignment of error is predicated upon the overruling of the objection of defendants to the following question propounded to Mr. Bell, city engineer, to wit:
“Q. Now, what are the facts as to whether or not you relied upon the statement made to you by Mr. Randles in your acceptance of this sewer? * *
“A. I did.”
In Larson et al. v. Thoma, 143 Iowa, 338, 345 (121 N. W. 1059, 1062), the court there says:
“The witness was further asked whether or not he would have bought that farm if he had not talked with
The question became important as to whether or not the municipality knew of the defect and what it would have done had it known of the same. This evidence was material: United States v. Walsh, 52 C. C. A. 419 (115 Fed. 697).
After a careful perusal of the able and .exhaustive briefs and arguments of the respective counsel, and an' examination of the record,' we find no error. The judgment of the lower court is therefore affirmed.
Affirmed. Rehearing Denied.