255 Mo. 76 | Mo. | 1914
Trial was had in the circuit court of the county of St. Louis, before a jury, resulting in a verdict and judgment in favor of plaintiffs' upon the third count of their petition in the sum of $116,381.35'. The case was tried upon the issues raised by the first and third counts of plaintiffs ’ petition, defendant’s second amended answer and plaintiffs’ reply. This is the second appeal in the case. The opinion upon the first appeal was rendered by Court in Banc and is reported in 241 Missouri at page 112. The pleadings upon the part of the plaintiffs are the •same as they were upon the first trial.
On February 12, 1902, plaintiffs and the defendant company entered into a written contract whereby plaintiffs agreed to do certain grading work upon a tract of land containing about three hundred acres which -the defendant owned and was desirous of having graded and leveled preparatory to dividing the tract into residence lots and offering the same for sale to the public. The contract provided that the amount of grading should not be less than 1,400,000 nor more than 2,100,000 cubic yards of earth. The work was to be accomplished by cutting down the high portions of the tract and depositing the dirt therefrom into the valleys or lower levels of the tract. The work was to be done in a workmanlike manner and in conformity with directions given by Pitzman’s Company of Surveyors and Engineers, as engineers, of defendant company. The tract of land to be graded was approximately three times as, long as it was wide; the long
The contract was silent with reference to the routes over which the dirt was to be hauled and also silent as to what appliances should be used in doing the work. On November 9, 1902, in consideration of certain modifications of the original contract the defendant company, by written agreement, extended the time for completion of the work from November 1, 1902, to July 1, 1903> and provided that the clause providing for the payment to the plaintiffs of the sum of $100 per day for each day that the contract might be finished ahead of time should be canceled but that the modification should not in any wise be taken to limit the right of the defendant company to receive stipulated damages for each day’s delay in completing the work after July 1, 1903. Later (the date is not given) the contract was modified by a further written agreement signed by both parties whereby the time for completion of the work was extended from July 1, 1903, to October 1, 1903, upon the conditions that the plaintiffs agree, upon notice from the engineer in charge, to complete all work on such portions as should be required for actual use and disposition prior to November 1, and as a further consideration of such extension it was agreed that the maximum amount of grading should be increased to 2,250,000 cubic yards, and further provided that the defendant might, in his discretion, have other parties do filling on said land with earth excavated outside of said land. Said written agreement provided that the original contract and
This whole controversy arises over the determination of the length of the average overhaul. Plaintiffs contend that the average haul for the entire work was 2166 feet, which would leave the average overhaul to be 766 feet. Defendant contends that the average length of haul on the entire work was 1660 feet, which would leave the average overhaul 260 feet. Prior to the institution of this suit the defendant company had paid the plaintiffs the total sum of $426,022.70, which was the total sum that the work would amount to, if the average overhaul was 260 feet as contended by defendants. This suit is to recover for the haul of the total yardage the further distance of 506 feet. The work was completed about December 5, 1903. At that time the plaintiffs, had received from the defendants the total sum of $349,525>.10 on account. Mr. Pitzman, one of defendant’s engineers, in charge of the work, made out a final estimate showing the balance which he claimed was due the plaintiffs to be $72,497.60. In this estimate, he finds the average overhaul to be 260 feet. In said estimate he stated to the defendant company that the same was subject to their right to claim liquidated damages, for failing to complete the work on time. Later it was found that the sum of $4000 which plaintiffs had borrowed from a trust company had been erroneously included in the final estimate as a payment on the work and this sum was. added to the final estimate making the balance due, as estimated by the engineer, $76,497.60. The plaintiffs procured the services of an engineer to figure the amount of overhaul and according to his estimate the actual average overhaul was 766 feet, and using that as a basis there was then due plaintiffs $150,431.63, which increased by
In doing the grading work, the plaintiffs moved some of the dirt by means of wagons, teams and scrapers and a part of the dirt by means of two steam shovels and cars, which cars were drawn by a steam engine over a trackway beginning at the west of Skinker Road and running south to the right of way of the Colorado Railroad, thence east along the right of way of said railroad to a point, a short distance west of the southeast corner of said tract of land, at which point the trackway extended in a northeasterly direction, going over the Wabash Railroad’s tracks upon an overhead bridge and over to the low land to the east of the Wabash Railroad where the dirt was deposited. Over this trackway 305',674 cubic yards of dirt were hauled. Plaintiffs contend that the average haul should be ascertained by measuring the respective hauls as they were actually made over the trackway. Defendant claims that the dirt could have been hauled a shorter practical route by team and wagon and that the overhaul should be determined by measuring the haul, not as actually made but by a route over which defendant’s engineer claims the dirt could have been hauled in a practical manner by teams and wagons.
As to the controverted issues, the evidence upon the part of plaintiffs tends to establish the following facts: Plaintiffs informed defendant company prior to entering into the contract that they would use steam
Two conferences were held between plaintiffs and defendant company and their respective engineers. At these conferences, defendant did not claim liquidated damages against the plaintiffs but took the position that they would pay the amount’ of Mr. Pitzman’s final estimate and no more, the only matter of dispute being as to amount of overhaul. During this time, one of the plaintiffs had a conversation with the president of the defendant company in which he said to defendant’s president that they would not accept the amount of defendant’s estimate and intimated that they would likely bring suit. To this defendant’s president replied: “It may suit us just as well if you enter suit, because we have to borrow this $75,000 which we are going to pay you; if we pay you we have
Plaintiffs further testified that no claim was ever made by the defendant company for liquidated damages and that the delay in completing the work was caused by failure of the defendant’s engineer to furnish them the grade stakes within time. That at the time the money was received on February 1, 1904, plaintiffs did not know the manner in which defendant’s capital stock was paid up. Prior to that time, one of plaintiffs, with his attorney, called upon the president of the defendant company to get information about the stock liability but the president of the company refused to give such information. That there was no custom, at St. Louis that grading of this kind should be done by wagons and teams. One of plaintiffs’ witnesses testified that the custom prevailing in St. Louis in reference to measuring hauls was that the haul was measured the way it was actually made, when the hauling was done where an engineer was in charge of the work, unless the engineer made a protest to the contractor concerning the route over which the dirt was hauled.
Defendant’s engineers denied telling plaintiffs that they would measure the haul as actually made. Mr. Pitzman testified that the trackway was laid over the only practical route available at the time it was laid and when plaintiffs submitted to him the plan of the route he said, “There is no objection, I will help you along the best I can. ’ ’ That he did not direct the way they should haul the dirt but made no objection thereto; that it was customary to do this kind of work with wagons and teams and that in measuring the
Mr. Coffin testified that he was. present at the directors’ meetings when the defendant was trying to settle with the plaintiffs and that the discussion was about the overhaul and that there was not much point made about the delay. That it was spoken of but never considered and that the word “compromise” was never used. Another of the defendant’s directors testified that plaintiffs were not present at the board meeting when the question of delay was discussed. Another of defendant’s directors testified that at the conference between plaintiffs and defendant one of
The evidence tending to show a stock liability was circumstantial in its character, that is, there was no direct, positive evidence that any certain person or persons owed for unpaid stock but it is fairly deduct
Instructions three, five and six given by the court at the request of plaintiffs and relating to the issues upon this appeal were as follows:
" 3. The court instructs the jury that the plaintiffs in the third count of the petition are here suing the defendant for an amount, with interest, alleged by plaintiffs to be due them by defendant on account of an alleged balance of 506 feet of average overhaul (out of a total claimed average overhaul of 766 feet) of 2,053,595 cubic yards of earth at three-fourths of a cent per cubic yard for each hundred feet of such overhaul, arising out of the grading of defendant’s property by plaintiffs; and the court instructs you that if you believe from the evidence that in hauling the earth here in question the plaintiffs did the work under the supervision and subject to the direction and control and to the satisfaction of defendant’s engineer in charge and supervision thereof and that the said engineer. knew of the manner in which and the routes along which plaintiffs hauled the excavated earth in question and made no objection thereto, and that the said engineer assisted plaintiffs in the location of the routes along which said earth was hauled, then plaintiffs were entitled to receive compensation based upon the said manner and routes that said earth was so moved, and*97 you will find in favor of the plaintiffs on said third count for the amount, if. any, remaining due them for the reasonable value of the work done as shown by the evidence, and including the said average overhaul in excess of 1400 feet, not exceeding, however, for the said average overhaul the rate of three-fourths of a cent per cubic yard of earth hauled for every 100 feet of average haul in excess of 1400 feet, together with interest thereon at the rate of six per cent per annum from April 19, 1904, the date of filing this suit, even though the jury may believe from the evidence that plaintiffs made a settlement of said claim with the defendant, providing the jury further find from the evidence and under other instructions given you that said settlement is not binding on plaintiffs.
“5. The court instructs the jury that even if they find from the evidence that a settlement was made between plaintiff and defendant when it paid plaintiffs the sum of $76,497.70, yet if the jury further believe from the evidence that prior to such payment the defendant admitted that said sum was due plaintiffs, and that defendant’s president in substance told one of plaintiffs that it would suit him just as well for plaintiffs to sue defendant because it would, have to borrow the money to pay with and that if it was sued that would put off the final payment two or three years, and that by that time defendant might have sold its property and have money to pay plaintiffs off with, or defendant might be busted and a judgment would not hurt it, and if the jury further believe from the evidence that thereupon plaintiffs made investigations as to the financial condition of defendant and ascertained facts sufficient to justify an ordinarily prudent person in believing that there was a reasonable prospect of defendant becoming insolvent and that plaintiffs were induced by the foregoing facts, if you so find the facts to be, to sign the receipt read in evidence, then*98 said settlement is not binding on plaintiffs and the jury-must not find against plaintiffs on account thereof.
“6. The court instructs the jury that even if they believe from the evidence that there was a settlement of plaintiffs claim between plaintiffs and defendant, yet if the jury further believe from the evidence that in discussions preliminary to said settlement the defendant’s president told one of plaintiffs that it would suit him just as well for plaintiffs to sue defendant, because it would have to borrow the money to pay with, and that if it was sued that would put off the final payment two or three years and that by that time defendant might have sold its property and have money to pay plaintiffs off with, or defendant might be busted and a judgment would not hurt it, and if the jury further believe from the evidence that defendant’s capital stock had been paid up with property put in at an amount far in excess of its value, and that because of that fact there were large sums due from solvent stockholders on account of their stock and sufficient to pay plaintiffs’ claim and that that fact was known to defendant’s president when he made the foregoing statement and was concealed by him from plaintiffs, and was not known to plaintiffs, and that the foregoing statement of defendant’s president induced plaintiffs to make said settlement with defendant, then such settlement is not binding on plaintiffs and the jury must not find against plaintiffs on account thereof.”
The following instructions were among others given at the request of the defendant.
“8. You are instructed that with reference to the amount of earth hauled under the contracts mentioned in the evidence, there is no dispute between the parties, the amount of same being 2,053,595 cubic yards.
“9. If you find and believe from the evidence that on and prior to the first day of February, 1904, the plaintiffs were asserting a claim against the defendant for an amount alleged to be due them under the
“10. In determining, under the other instructions of the court, whether defendant was guilty of such false and fraudulent representations and concealments as to justify your finding and believing the plaintiffs’ receipt of February 1,1904, mentioned in the evidence, to be of no force and effect on that account, you are to take into consideration the knowledge, if any, of the plaintiffs, or either of them, or of John Scott, their father, now deceased, at and before the time of the execution of said receipt of February 1, 1904, of the facts and circumstances concerning or connected with the contracts mentioned in the evidence, and the grading thereunder and with the method by which the engineer in said contracts measured the overhaul, and with the
“11. The court instructs you that in determining, under the other instructions of the court, whether the defendant was guilty of such false and fraudulent representations and concealments as to justify your finding and believing they are not bound by the receipt of February 1,1904, in evidence for that reason; you ar6
The following instruction was requested by defendant and was given by the court after modifying the same by omitting therefrom the portion enclosed in brackets:
“12. The court instructs you that, under the laws of the State of Missouri, even though you may find and believe from the evidence that the incorporators of the Parkview Realty & Improvement Company stated in the articles of incorporation that the capital stock of the company had been subscribed and fully paid up in lawful money of the United States, or in cash, nevertheless, under the law of Missouri this means lawful money or its equivalent [and this statement by the incorporators of said company was a statement made to the Secretary of Missouri for the purpose of obtaining a charter for the company, and was not such a statement upon which the plaintiffs had a right to rely]. And you are further instructed that, under the laws of Missouri, the plaintiffs could not look to the incorporators for the payment of any judgment they might secure against defendant, except to the individual incorporators or subscribers to the capital stock — in the several amounts in which their several subscriptions to the capital stock might be found to be unpaid. ’ ’
We have carefully read the evidence introduced upon this, as well as upon the former trial, and in so far as it affects the above issues the evidence was in effect substantially the same upon both trials. Upon the former appeal these same propositions were urged by appellant (respondent then) in support of its contention that plaintiffs ’ nonsuit as to the first and third count of the petition should not be set aside. The authorities now cited by appellant in its brief in support of the above contentions were (with one or two unimportant exceptions) cited by it upon the former appeal in support of the same contention then made and the Court in Banc, after a careful consideration of all the -above propositions, reached a conclusion contrary to appellant’s contentions. We have carefully considered the former opinion (Scott v. Parkview Realty & Improvement Company, 241 Mo. 112), and are unable to discover wherein the conclusions therein reached are incorrect. Under such conditions, the law as declared upon the first appeal is controlling upon this appeal. [Bagnell v. Railroad, 242 Mo. 11, and cases therein cited.]
The last modification of the contract extending the time in which the work was to he completed to October 1, 1903, did not contain a clause reiterating the obligation as to liquidated damages as was done in the first modification. The first modification contained such a provision, clearly showing that at least the parties thought that in order to have the clause as to liquidated damages remain in force after the first extension it was necessary to expressly so declare in the modification made. When this is taken into consideration with the fact that the last modification provided that the maximum amount of yardage which the defendant company could demand that plaintiffs do under the contract was increased by 150,000 cubic yards and “that if portions of the land to be graded should be required for actual use or disposition prior to said November 1st, the said John Scott & Sons agreeing, nevertheless, will upon written notice from the engineer in charge complete
The foregoing opinion of Williams, C., is adopted as the opinion of'the court.