SCIABA CONSTRUCTION CORPORATION vs. CITY OF BOSTON & another; DEPARTMENT OF LABOR AND INDUSTRIES, intervener.
No. 92-P-328.
Appeals Court of Massachusetts, Suffolk
April 14, 1993. - August 23, 1993.
35 Mass. App. Ct. 181
WARNER, C.J., ARMSTRONG, DREBEN, KAPLAN, & PORADA, JJ
The court expressed its views on the merits of a controversy that had become moot, where the matter had been briefed and argued, the issue was of public importance and likely to arise again and evade judicial review, and a decision would probably prevent future litigation between the parties. [185]
Modern Continental Construction Co., Inc.1
The case was initially heard by a panel comprising Justices Dreben, Kaplan, and Porada and was thereafter submitted on the record and briefs to Chief Justice Warner and Justice Armstrong, all of whom took part in the decision of this case in accordance with the provisions of
A municipal commissioner of public works considering bids for a project correctly concluded that an obvious clerical error appeared on one of the submissions and properly awarded the contract to the lowest bidder without considering the item in which the error was made. [186-190]
PORADA, J., dissenting, with whom KAPLAN, J., joined.
A disappointed bidder on a public works project was not entitled to injunctive relief, in the circumstances, for the city‘s inadvertent failure to follow bidding procedures, nor was it entitled to its bid preparation costs where it was not entitled to the award of the contract. [190-191]
PORADA, J., dissenting, with whom KAPLAN, J., joined.
CIVIL ACTION commenced in the Superior Court Department on November 4, 1991.
After proceedings before Barbara A. Dortch, J., a petition seeking relief from an order denying a preliminary injunction was heard in the Appeals Court by Kass, J.
John J. Spignesi for the plaintiff.
William J. Pidgeon, Jr., Assistant Corporation Counsel, for the city of Boston.
Charles E. Schaub, Jr., & William R. Moore, for Modern Continental Construction Co., Inc., submitted a brief.
L. Scott Harshbarger, Attorney General, Peter Waltonen & Sheila L. Morton, Special Assistant Attorneys General, for the intervener, submitted a brief.
DREBEN, J. Sciaba Construction Corporation (Sciaba) filed suit in the Superior Court against the city of Boston (city) and Modern Continental Construction Co., Inc. (Modern), seeking preliminary and permanent injunctions to prevent the city from awarding a contract for the repair of the North Washington Street Bridge to Modern on the ground that the award would be in violation of
The facts are not in dispute. The city solicited competitive bids for the repair of the North Washington Street bridge pursuant to
Upon opening the bids on September 19, 1991, the three lowest bidders were as follows:
| Modern Continental Construction | $2,287,950. |
| Sciaba Construction Corporation | $2,338,200. |
| N.E.L. Corp. | $2,655,462. |
Modern‘s bid contained an error in item No. 860.04 for the painting of a four-inch, reflectorized white line. While Modern listed a unit price of fifteen dollars in words and figures for an estimated quantity of 6,400 linear feet, its extended price was $960, a figure that was also reflected in Modern‘s total bid price. See note 5, infra.
Based upon the prices for the item quoted by Sciaba (twenty-five cents per linear foot) and the other low bidder, N.E.L. Corp. (twelve cents per linear foot), and the city‘s own estimate of ten cents per linear foot, the city‘s commissioner of public works concluded that Modern had made an obvious clerical error in its bid. For this reason he declined to apply the formula. Instead, relying on another provision in the bid specifications that reserved to him “the right to reject any and all proposals, or any Item or Items of the proposal should he deem it to be for the best interest of the City so to do,” the commissioner rejected all bids for the painting of the reflectorized white lines.
The commissioner then awarded the contract to Modern, basing his decision on the following grounds: (1) the painting of the lines involved very minor work not directly connected to the main purpose of the contract, and it could easily be performed by a separate service order or by the city itself; (2) the dollar amount of the repair work was insignificant in relation to the total contract, representing a mere .03% of the entire project; (3) Modern‘s unit price was, on its face, an obvious clerical error; and (4) the rejection of all bids for this item would prevent an unnecessary expenditure of approximately $50,000 in public funds (the difference between Modern‘s and Sciaba‘s bid).
When notified of the city‘s decision, Sciaba filed a protest with the department, and, when advised that the city would ignore the department‘s determination in Sciaba‘s favor, see note 4, supra, Sciaba filed this action. It now appeals from the denial of a preliminary injunction.
While strict adherence to statutory bidding requirements is required in matters of substance, Grande & Son, Inc. v. School Hous. Comm. of N. Reading, 334 Mass. 252, 258 (1956); Gil-Bern Constr. Corp. v. Brockton, 353 Mass. 503, 505-506 (1968), and this is so even in cases where the violation benefits the public, Phipps Prod. Corp. v. Massachusetts Bay Transp. Authy., 387 Mass. 687, 692 (1982), minor deviations from statutory bidding requirements do not compel rejection of the bid or invalidation of a contract.
Absent other considerations, an obvious clerical error that deceives no one does not require rejection of a bid. Fred C. McClean Heating Supplies Inc. v. School Bldg. Commn. of Springfield, 341 Mass. 322, 324 (1960). Thus, in that case the court held that the obvious clerical error of a bidder (West Side) in placing the figure for a deduction in “Alternate A” and writing “none” in “Alternate B,” when the figure should have been placed in “Alternate B,” did not compel rejection of the bid. The petitioner had relied on
Federal executive agencies also permit the correction of clerical errors, albeit by explicit grant of authority. Congress enacted
An analysis of the bid documents submitted by Modern and the other low bidders leaves no question that the city‘s
Sciaba also claims that the city‘s decision to delete the item was based exclusively on extrinsic evidence and that Gifford v. Commissioner of Pub. Health, 328 Mass. 608, 615 (1952), precludes the use of such evidence. That the city‘s conclusion was based solely on extrinsic evidence is refuted by note 5, supra, showing that the error was apparent on the face of the bid. Moreover, Sciaba‘s reliance on Gifford to conclude that the city could not take the other bids or the estimates of its own engineers into account is misplaced. The evidence excluded in Gifford was “private, confidential or se-
In contrast, in this case, the so-called “extrinsic” evidence of the other bids was before the city at the time of the opening of the bids. Such evidence and the estimates in its own files from its engineers could be used by the city in determining that Modern‘s bid contained a clerical error. Contrary to Sciaba‘s contention, there is no basis for challenging that determination. See Capuano, Inc. v. School Bldg. Comm. of Wilbraham, 330 Mass. 494, 496 (1953).6
The question next arises whether the contract provision concerning discrepancies precludes the result reached by the authorities cited earlier involving clerical errors. The clause, as will be remembered, provides: “In the event there is a discrepancy between the unit prices and the total sum of all the Items, the unit prices shall govern.”
Just as the court in Fred C. McClean Heating Supplies Inc. v. School Bldg. Commn. of Springfield, 341 Mass. at 324, rejected the literal and “harsh” construction of the statute as “unreasonable,” we reject the literal and harsh construction
Because we consider this case to fall within the narrow class of cases permitting the correction of obvious clerical errors that deceive no one, it follows that the city was entitled to award the contract to Modern. The city, however, did not do so directly but first omitted item No. 860.04, relying, as we previously indicated, on the provision in the bid documents allowing the commissioner of public works “to reject . . . any Item or Items of the proposal should he deem it to be for the best interest of the City. . . .” That reliance, however, seems questionable under the reasoning of Grande & Son, Inc. v. School Hous. Comm. of N. Reading, 334 Mass. at 258.
In that case the awarding authority had awarded the contract to the lowest general contractor but had deleted from
“The provision for rejecting bids is not intended as a device to be adopted as part of the act of awarding a contract so as to justify making a contract different from that submitted to competitive bidding. If, after bids are opened, the awarding authority could, either with or without negotiation with a selected general contractor, omit portions of the proposed work for reductions in price, the legislative intent to protect the public, all too easily, could be evaded. That the awarding authority, as contended here, had as one of their purposes a reduction in cost is of no consequence. Even the best of motives cannot excuse contravention of the statute” (citations omitted). 334 Mass. at 258.
The same reasoning applies to the bidding procedure under
There was here, however, no attempt to undermine open and honest bidding procedures or to manipulate the bid. To the contrary, the city sought to achieve punctilious compliance with its documents. In the mistaken belief that the bidding documents did not permit it to award the contract to Modern as bid — that is, with the error in item No. 860.04
Sciaba is also not entitled to its bid preparation costs. Paul Sardella Constr. Co. v. Braintree Hous. Authy., 3 Mass. App. Ct. 326, 333-335 (1975), S.C., 371 Mass. 235, 243 (1976). Since Sciaba was not entitled to the award of the contract and, moreover, has not shown “that the result would not have been the same” had the improper deletion not occurred, Sciaba has not shown that it “has been hurt.” Loranger v. Martha‘s Vineyard Regional High Sch. Dist. Comm., 338 Mass. 450, 458-459 (1959).
The appeal is dismissed because it is moot.
So ordered.
PORADA, J. (dissenting, with whom Kaplan, J., joins). While I agree that the appeal is now moot, I do not agree that the city‘s award of the contract to Modern was proper or that Sciaba should be deprived of its bid preparation costs. Unlike the majority, I view the deletion of an item in the scope of the work by the city after the completion of the competitive bidding process as a substantive deviation from statutory bidding procedures. See Grande & Son, Inc. v. School Hous. Comm. of N. Reading, 334 Mass. 252, 258 (1956); Gil-Bern Constr. Corp. v. Brockton, 353 Mass. 503, 505-506 (1968).
Whether a deviation is considered one of substance or a minor technicality, which does not compel rejection of the bid or invalidation of a contract, will depend on whether invalidation is necessary to fulfil the legislative purpose. Phipps Prod. Corp. v. Massachusetts Bay Transp. Authy., 387 Mass. 687, 692 (1982). The objectives of statutory bidding procedures are “to prevent favoritism, to secure honest meth-
I do not agree that the city‘s good faith is relevant to the issue before us. See Gifford v. Commissioner of Pub. Health, 328 Mass. 608, 617 (1952) (absence of bad faith or of corruption does not excuse noncompliance with the procedure established by the Legislature for the award of public contracts); Grande & Son, Inc. v. School Hous. Comm. of N. Reading, 334 Mass. at 258. I also do not agree that the city sought punctilious compliance with its bid documents. The very reason the case is before us is that the city failed to follow the procedure set forth in its bid documents for dealing with the defect in Modern‘s bid, which, as will be remembered, provides:
“In the case of a discrepancy between the prices written in words and those written in figures, the written words shall govern. In the event there is a discrepancy between the unit prices and the total sum of all of the Items, the unit prices shall govern.”
If this formula had been applied, Modern‘s price for the deleted item would have been $96,000, and Sciaba would have been the lowest bidder. The majority seeks to justify the city‘s action by construing the clause to apply only when an
Even if one were to conclude that there was some doubt as to the clause‘s meaning, the best evidence of intent is the city‘s recognition that the clause applied to the defect necessitating their deletion of the item containing the defect from the scope of the work. See Massachusetts Mun. Wholesale Elec. Co. v. Danvers, 411 Mass. 39, 59 (1991) (conduct of the parties after signing the agreement is indicative of intent).
In sum, I conclude that the city‘s invalid deletion of an item in the change of the scope of the work after completion of the bidding process (a point not disputed in the majority opinion) and the city‘s failure to follow its own formula in its bid documents for dealing with the error in Modern‘s bid creates an impression of favoritism, smacks of bid manipulation, and results in disparate treatment of the submitted bids contrary to the legislative intent and spirit of statutory bidding procedures. As a result, I conclude that the preliminary injunction should have been allowed, the award of the contract to Modern was improper, and Sciaba should be entitled to recover its bid preparation costs under the authority of Paul Sardella Constr. Co. v. Braintree Hous. Authy., 3 Mass. App. Ct. 326, 333-335 (1975), S.C., 371 Mass. 235, 243 (1976).
Notes
| ITEM NO. | QUANTITY | ITEM WITH UNIT BID PRICE WRITTEN IN WORDS | UNIT PRICE DOLLARS CENTS | AMOUNT DOLLARS CENTS |
|---|---|---|---|---|
| 860.04 | 6,400 | 4 IN. REFLECTORIZED WHITE LINE (PAINTED) AT FIFTEEN DOLLARS PER LINEAR FOOT | 15 - | 960 - |
| 866.04 | 4,700 | 4 IN. REFLECTORIZED WHITE LINE (THERMOPLASTIC) AT FORTY CENTS PER LINEAR FOOT | 0 40 | 1880 - |
| 867.04 | 2,100 | 4 IN. REFLECTORIZED YELLOW LINE (THERMOPLASTIC) AT FORTY CENTS PER LINEAR FOOT | 0 40 | 840 - |
| 868 | 100 | GORE LINES REFLECTORIZED WHITE (THERMOPLASTIC) AT ONE DOLLAR THIRTY CENTS PER SQUARE FOOT | 1 30 | 130 - |
