231 Mass. 490 | Mass. | 1919
The plaintiff (hereinafter called the owner) entered into a written contract with the Hancock Engineering Company (hereinafter called the contractor) for the erection of a house in Worcester. A bond was given to the owner for the faithful performance of the contract, with the contractor .as principal and the American Surety Company of New York as surety. The condition was that, if the contractor should indemnify the owner against all loss or damage “directly arising by reason of the failure” of the contractor to perform faithfully the building contract, the bond was to be void, “otherwise to remain in full force and effect.”
The contract was dated June 22, 1914. By its terms the house was to be completed November 1, 1914. Without the knowledge of the surety, by agreement of the owner and contractor the time for completion was extended to Christmas, 1914. The surety asked the judge to instruct the jury “That there was no evidence of any waiver by any person authorized to make a waiver for the defendant, the American Surety Company” and “That upon all the evidence there was no waiver by this defendant.” The jury, in answer to a question, found that on December 17, 1914, the surety ratified “the action of the plaintiff in extending the time for completion of the building from November 1, 1914, to Christmas, 1914,” and returned a verdict for the plaintiff.
The obligation assumed by the surety was that the contractor should complete the building on the first of November, 1914. The extension of time to Christmas, 1914, was a substantial change in the contract and as modified it was not the contract for the faithful performance of which the surety bound itself. The agreement for the extension without its knowledge or consent, discharged the surety. Greely v. Dow, 2 Met. 176. Atkins v. Boylston Fire & Marine Ins. Co. 5 Met. 439. Appleton v. Parker, 15 Gray, 173. Warren v. Lyons, 152 Mass. 310. There was no evidence that the surety knew of the modification in the contract extending the time of its performance, either when the change was made or subsequently thereto, before the action was brought.
The plaintiff in his brief contends that the time stipulation of the contract was waived, and to show this he relies on certain statements made December 17, 1914, by Philbrick and Roberts, representatives of the American Surety Company. At that time
Without intimating that the surety could be held to have ratified, the agreement made by the owner and the contractor for their own benefit and convenience, (see, in this connection, New England Dredging Co. v. Rockport Granite Co. 149 Mass. 381, 382,) it is enough to say that when the principle of ratification is applicable in order to becomé effective it must appear that the ratifier had full knowledge of the essential facts of the act or contract to be ratified. Dickinson v. Conway, 12 Allen, 487. Manning v. Leland, 153 Mass. 510, 513.
As the case was tried in the Superior Court and on the excep
The only questions open on this bill of exceptions are these: Was there any evidence for the jury that the surety ratified the action of the plaintiff in extending the time, and should the surety’s request that there was no waiver have been given. In submitting to the jury the question of the ratification and in refusing the surety’s request, there was error of law.
We do not deem it necessary to discuss the question raised by the plaintiff in his brief, that no written motion was made by the surety to direct a verdict in its favor. The request of the defendant surety, that on all the evidence there was no waiver, should have been given and the instructions to the jury were wrong.
Exceptions sustained.