99 Va. 257 | Va. | 1901
delivered the opinion of the court.
In July, 1897, The Citizens Bank of Norfolk entered into an agreement in writing with Trank B. May, a general contractor, for the erection by him of a bank building to cost $95,750.00. In April, 1899, the bank filed its bill in this case alleging that it and numerous tenants had been using and occupying the building since January 19, 1899, though it was not fully completed, there being several matters involving small cost to be attended to. It further alleged that the entire cost of the building had been paid except a balance then in its hands of
An answer, to be treated as a cross-bill, was filed by the appellant, setting up a lien for the sum of $5,595.00 under its contract with the general contractor; and also for the further sum of '$339.23 for extras claimed to have been furnished directly to the bank upon the order of the architect; and alleging that the bank had improperly disbursed part of the building fund, and should be held to account for a much larger sum than that •admitted to be in its hands.
An elaborate report, together with the evidence upon which it was based, was returned, finding that at the time of the institution of this suit there was in the hands of the bank unpaid on the building a balance of $4,444.40, and that, after the completion •of the building according to the contract, the bank had in its hands applicable to unpaid claims the sum of $3,636.2Y, out of which had to be first paid two claims of superior dignity amounting to $1,865.03, and the residue disbursed pro raía among nine remaining claimants including the appellant. A decree was entered overruling all exceptions to this report, and confirming the same, which we are now asked to review.
Adverting to the alleged errors in the order of their assignment, the court is of opinion that it was not error to allow the bank credit for the sum of $808.13 paid by it for work done and
The court is further of opinion that the hank was not properly chargeable with the sum of $1,069.32 in addition to the oirginal contract price of the buildings. That sum represented the price of work not covered or contemplated by the contract which was paid for by the hank as soon as it was done. It would hardly be claimed, if the work in question had been done by a stranger to the original contract, that the hank should he charged with its cost as if done under the original contract. The case is not different because such work was done by the same person who had the larger contract. It was a separate and distinct transaction, outside of and apart from the original building contract, and therefore not to he considered in connection therewith.
The court is further of opinion that there was no error in allowing the hank credit for the notes held by it which had been executed by the general contractor, and endorsed by the several sub-contractors to whom they were payable,- and discounted by the bank for the benefit of the latter. Hor was it error to allow the hank credit for other similar notes taken up by it which were due and payable at other hanks. Hor was it error to allow the hank credit for orders drawn upon it by the general contractor in favor of sub-contractors. So far as can he discovered from
The court is further of opinion that there was no error in crediting the bank with the amount due the White Hardware Company and Cook, Clark & Co., as preferred claims to be paid in full out of the balance due from the bank. These two claims had been perfected under section 2479, and constituted a personal liability upon the bank. The bank -was not liable for more than the price it had agreed to pay for the building, and it had always kept back more than enough to pay those sub-contractors who had given it notice as required by law, and it was entitled to have the balance thus reserved in its hands applied first to the satisfaction of such claims.
Upon -consideration of the whole case, the court is of opinion that there is no error in the decree complained of to the prejudice of appellant, and it must be- affirmed.
Affirmed.