This case concerns the issue of whether the property of the plaintiff, Schooner Harbor Ventures, Inc. (“Schooner Harbor”), was taken by the United States, such that it must pay just compensation under the Fifth Amendment. The United States Court of Federal Claims (“trial court”) granted summary judgment for the Government on the ground that Schooner Harbor had failed to identify a cognizable property interest that had been affected by government action. Because we find that Schooner Harbor did identify a cognizable property interest, namely fee title to land that could not be developed without regulatory compliance, we reverse and remand for further proceedings consistent with this opinion.
BACKGROUND
Schooner Harbor purchased eighty-two acres of land adjacent to the Mississippi Sandhill Crane Natural Wildlife Refuge (“Refuge”) in 2000 for $963,802.51. 1 Shortly thereafter, the United States Department of the Navy (“Navy”) began a search for an appropriate site for development of 188 housing units for Navy personnel and their dependants assigned to Naval Station Pascagoula. The plaintiff’s property, referred to as Site 28, was among those considered in the final stages of the project planning.
To comply with the National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321M347, the Navy was required to prepare an Environmental Assessment. In doing so, the Navy contacted the Daphne, Alabama field office of the United States Fish and Wildlife Service (“FWS”) concerning the proposed development and its potential impact on Site 28. Through a *1361 series of letters, FWS informed the Navy that construction of the housing on the Schooner Harbor property would impact the Mississippi Sandhill Crane. It was determined preliminarily that approval of the project could be obtained, but it would be contingent on appropriate mitigating steps being taken. In particular, approximately ninety acres of replacement wildlife habitat would be required to be added to the Refuge in order to offset the impact on the endangered species.
On August 20, 2001, the Navy requested a formal Section 7 consultation from FWS concerning the project. Section 7 of the Endangered Species Act provides that federal agencies must consult with the Secretary of the Interior to ensure that their actions will not “result in the destruction or adverse modification of habitat of [any endangered] species which is determined by the Secretary ... to be critical.” 16 U.S.C. § 1536(a)(2) (2006). FWS provided a Biological Opinion on February 12, 2002, concluding specifically that the Navy could go forward with the project without harming the cranes because, “[although critical habitat will be impacted in one location ... it will be enhanced, protected, and managed in another location by acquisition of another property of equivalent or better habitat value.” This referred to an unrelated parcel of seventy-seven acres of land that FWS required to be added to the Refuge in order to mitigate the environmental impact.
On April 17, 2002, Schooner Harbor and the Navy contracted for the sale of the property for $1.9 million. Schooner Harbor’s obligations included transferring Site 28 to the Navy and the seventy-seven acre off-site parcel to FWS for addition to the Refuge. On May 3, 2002, Schooner Harbor transferred both parcels to the Government (the Navy and FWS, respectively).
Schooner Harbor subsequently filed the complaint in this case, alleging that FWS’s regulations “effectively deprived [Schooner Harbor] of all productive and beneficial use of the Property by virtue of the requirement to purchase additional off-site property at the same value of the Property at issue in order to sell and develop the Property.” The Government moved for summary judgment, which the trial court granted on two alternative grounds.
Schooner Harbor
Ventures,
Inc. v. United States,
First, the court stated that the “property interest the plaintiff claims was taken in this case is the plaintiffs interest to sell its property to the Navy for the development of a housing project, without conditions or additional financial burden.” Id. at 412. The court considered whether this was a compensable property right, and determined that it was not.
Second, the court considered how the identified property interest had been affected by the relevant government action, which it viewed as the Navy’s purchase of land subject to conditions. Id. at 414. The court found that the Government was acting in its “proprietary” rather than its “sovereign” capacity when it did so. Id. That is, the Navy’s imposition of a term of sale related to the Government’s behavior as a purchaser, not as a sovereign. Because the court characterized the Government’s behavior as commercial, it reiterated that the takings claim must fail. Id. at 414-15.
Schooner Harbor timely appealed to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3) (2006), as this is an appeal from a final judgment of the Court of Federal Claims. The Court of Federal Claims had jurisdiction pursuant
*1362
to the Tucker Act. 28 U.S.C. § 1491(a)(1) (2006). The Tucker Act waives sovereign immunity and provides jurisdiction for certain types of claims, including, as relevant here, where there is a money-mandating provision on which the plaintiff may base its recovery.
Fisher v. United States,
DISCUSSION
“We review the Court of Federal Claims’ grant of summary judgment without deference.”
GHS Health Maint. Org., Inc. v. United States,
The Fifth Amendment prevents the Government from taking private property for public use without just compensation. U.S. Const, amend. V.
We have developed a two-part test to determine whether a taking has in fact occurred. First, as a threshold matter, the court must determine whether the claimant has established a property interest for purposes of the Fifth Amendment.... If the claimant fails to demonstrate the existence of a legally cognizable property interest, the courts [sic] task is at an end.
Am. Pelagic,
If the claimant identifies a cognizable property interest, the court must proceed to the second part of the analysis: “whether the governmental action at issue amounted to a compensable taking of that property interest.”
Am. Pelagic,
The trial court premised its decision on two different grounds. Both were
*1363
predicated on an erroneous understanding of Schooner Harbor’s claimed property interest and a related misidentification of the relevant regulatory government action. The court explained that the “property interest the plaintiff claims was taken ... is the plaintiffs interest to sell its property to the Navy for the development of a housing project, without conditions.”
Schooner Harbor,
Schooner Harbor, however, did not agree that such a right was the relevant interest for the court’s takings analysis. To the contrary, in its response to the motion for summary judgment at issue here, Schooner Harbor stated, “The Plaintiff has never claimed that it acquired a specific right to sell to the Navy without restriction. The Plaintiff asserts however that with its right of alienation and fee simple ownership it had the right to sell to any party.” Resp. to Mot. for Summ. J. at 9, Schooner Harbor, No. 06-CV-00087 (Fed.Cl. Dec. 7, 2007). Thus, Schooner Harbor alleged that the relevant property interest was its fee title to Site 28, and that the relevant government action was FWS’s decision to regulate development and sale of the parcel.
This statement is consistent with Schooner Harbor’s complaint, in which it alleged that it was an owner in fee, and that “[tjhrough the
regulations imposed by the Defendant, USFWS,
the Plaintiff was effectively deprived of all productive and beneficial use of the Property.”
2
Compl. at 6 ¶XXIV,
Schooner Harbor v. United States,
No. 06-CV-00087,
The trial court’s error on this matter appears to stem from two sources. First, in the Joint Statement of Issues of Law the parties agreed that “[wjhether Plaintiff possessed, at the time of the alleged taking, a Fifth Amendment compensable right to sell its property to the United States without any conditions being imposed on the sale” was “an issue of law.” Joint Statement of Issues of Law at 1,
Schooner Harbor
No. 06-CV-00087 (Fed.Cl. July 25, 2007). They did not agree, as the trial
*1364
court stated, that it was “the preliminary issue.”
Schooner Harbor,
The second source of the trial court’s error was a lack of clarity in Schooner Harbor’s arguments. In particular, Schooner Harbor has consistently conflated the right to sell land with the right to develop land. Nothing in Schooner Harbor’s allegations or briefs suggests that either FWS or the Endangered Species Act has anything at all to say about who should own Site 28, or how easily the land should change hands. Thus, the only possible direct limitation on its right of alienation was, as the trial court found, the inability to sell without conditions. Indeed, Schooner Harbor explicitly alleged that it could not sell to the Navy without meeting the Navy’s conditions, and that FWS’s determination of the scope of those conditions constitutes a taking. Compl. at 5 ¶ XIX-XX. The trial court appropriately analyzed and disposed of this “property” right.
However, Schooner Harbor also alleges the right to develop its land, irrespective of any sale. See Compl. at 2 ¶ VI (“development rights were an integral part of the Property’s title and value”); id. at 3 ¶ IX (“development of the Property was not allowed”); id. at 5-6 ¶XXI (“USFWS’ determination under the Endangered Species Act insofar as it establishes requirements ... which preclude the development of the Property ... have affected [sic] the taking of the Plaintiff [sic]”). This alleged regulation of Schooner Harbor’s right to develop Site 28 would have an obvious impact on any subsequent sale, regardless of the purchaser’s identity — a development-restricted parcel commands a lower price. A lower sale price, of course, is not a restriction on the right of alienation, but rather one effect of a regulation on the right to develop. A detailed reading of Schooner Harbor’s position below and on appeal thus reveals that this alleged regulation of the right to develop Site 28 is also asserted as a taking. See Compl. at 2 ¶ VI (“Plaintiff fully expected to develop the Property for sale, and/or sell the Property with full rights of future development.”).
The right to develop one’s land is clearly cognizable, as the trial court acknowledged.
See Schooner Harbor,
Schooner Harbor alleges that FWS prohibited development by threatening enforcement of the Endangered Species Act. Compl. at 3, 5-6 ¶¶ IX-X, XXI-XXIV (alleging that development of Site 28 without mitigation would “result in the invocation of an enforcement of certain sections of the Endangered Species Act as set forth in a letter from [FWS to the Navy]”). In the letter cited by the complaint, FWS stated that ‘private development would require an “incidental take permit” under Section 10 of the Endangered Species Act — that is, that private development would implicate Section 9’s generally applicable prohibition on “take” of an endangered species. J.A. 170; see 16 U.S.C. §§ 1538-1539. Schooner Harbor’s claim, therefore, is that Site 28 could not be developed by anyone given FWS’s factual determination about the effects of the development of Site 28 on the endangered cranes.
Drawing all reasonable inferences in favor of Schooner Harbor, we conclude that Schooner Harbor’s claim does identify a cognizable property interest — its right to develop its land — and that it has plausibly alleged that FWS has, by regulation, affected that right. The trial court noted in passing that FWS had regulated the Navy, as opposed to Schooner Harbor.
Schooner Harbor,
The fact that FWS’s actions took place during negotiations for a sale to the Navy does not change the nature of the fundamental property interest asserted, nor does it change Schooner Harbor’s allegations that it was FWS that “took” its property rights. Assuming, arguendo, that FWS’s evaluation of Site 28 resulted in a sufficiently final and binding conclusion that Schooner Harbor could not develop the property, and that the regulation was sufficiently severe to warrant compensation under the Penn Central factors, the Government could not escape liability by purchasing the property at the lower, development-restricted price. The trial *1366 court’s analysis improperly focused on an inaccurate characterization of the relevant property interest and a related mischarac-terization of the relevant government regulatory restriction — the proper focus is on FWS’s regulation of development (such as it was), not on the Navy’s purchase.
On remand, therefore, the trial court should consider this alleged taking through the frameworks summarized by the Supreme Court in
Lingle v. Chevron U.S.A., Inc.,
An additional consideration may arise on remand. The trial court indicated that because the critical habitat designation occurred in 1977, subjecting the property to certain regulatory restrictions, and Schooner Harbor did not purchase the land until 2000, it “stretches the credulity of the court that plaintiff, as a real estate developer, did not do due diligence and was not aware of the protected status of the land at issue.”
Schooner Harbor,
CONCLUSION
Because the trial court’s grant of summary judgment was based on its misidenti-fication of the asserted property right and its related misunderstanding of the relevant government action, we reverse and remand for proceedings consistent with this opinion.
REVERSED AND REMANDED
COSTS
No costs.
Notes
. In a series of transactions not at issue, it resold approximately 8.15 of those acres for $430,000 in less than a year.
. Schooner Harbor maintained this argument in its briefing on Summary Judgment, including a section entitled "Schooner Harbor Had a Right to Economically Exploit the Land.” Resp. to Mot. for Summ. J. at 6.
. Although the language of the complaint might suggest that a per se taking has been alleged under the framework in
Lucas,
. The statement’s inclusion in the document does imply that it was relevant, but only to one party — the Government.
