57 Neb. 546 | Neb. | 1899
School District 35 of Sherman county undertook to erect a schooliiouse. Plans and specifications were adopted at a district meeting, and the contract for erecting the house was let to Randolph. He built the house according to contract,' it was accepted, and he received the contract price. It was, however, discovered that the designs failed to provide for certain work on the foundations, for certain braces, for window shutters, and for a platform and steps at the door as means of ingress. Randolph, at the request of the district board, supplied these deficiencies and brought this- suit, not on a quantum meruit, but on the special contract with the board, to recover for the extra work. The district court gave him judgment for the price of the shutters, platform and steps, and the district asks a reversal.
However meritorious the claim may be as a moral obligation upon the district, we are satisfied it cannot be sustained, at least through a suit on the special contract
Reversed and remanded.