196 F. 16 | 4th Cir. | 1912
Plaintiffs, appellees, citizens and residents of the state of Indiana, on the 9th day of Eebruary, 1905, entered into a contract with defendant, appellant, a citizen and resident of the state of West Virginia, whereby they contracted to furnish certain material and do certain work in the construction of a 12-story office building, in the city of Wheeling, W. Va., on the land described in the record, of which defendant was the sole owner. Among the provisions material to a determination of the questions presented upon the record are the following: The price to be paid to plaintiffs for the material furnished and work done, contemplated by the contract, was $231,698—
“payments to be made every thirty days on estimates of architects, providing, however, that the work is satisfactory, ten per cent. (10%) of each estimate to be reserved until completion of the contract. The final payment to be made twenty (20) days after the contract is completed and satisfactory to the architects and the owner.”
M. F. Giesey and E. E. Earis were named as the supervising architects “acting as the agents of the owner.” The contractors agreed and bound themselves to have all of the work contemplated by the contract finished and ready to turn over to the owner by December 31, 1905—
“and, in case of a failure, in this particular agreed to pay the owner the sum of fifty dollars ($50) per day, as measured damages for each and every day beyond the 31st day of December, 1905, that the said failure exists, provided, however, that said contractors shall have credit for such days as the architect and owner shall certify at the time, as days when the weather forbids work, and credit for each and every day he is delayed by the owner, if such delay is also certified to by the architects and owner at the time it occurs.”
It is further provided:
“No alterations shall be made in the work shown or described by the drawings or specifications except upon a written order of the architects or owner, and when so made, the value of the work added or omitted shall be computed by the architects, and the amount so ascertained shall be added to or deducted from the contract price. In case of dissent from such award by either party hereto, the valuation of the work added or omitted shall be referred to three (3) disinterested parties, one to be appointed by each of the parties to this contract and the third by the two thus chosen; the decision of any two of whom shall be final and binding, and each of the parties hereto shall pay one-half the expense of such reference.”
A large number of alterations were made during the construction of the building. Some of the material and work, called for by the contract, was omitted. Eor various reasons, not necessary to specify at this time, plaintiffs were delayed in commencing the construction of the building.
“On the 6th day of August, 1007, they c-eased to labor on, or furnish, material for the said building, having then fully completed the construction of said building in accordance with the said contract.”
On the 17th day of August, 1907, they filed with the clerk of the county court of Ohio county an account of the amount due them and a description of the real estate upon which said building was constructed, as prescribed by the statute, etc. On the 21st day of August, 1907, plaintiffs filed their bill in equity in the Circuit Court of the United States for the Northern District of West: Virginia, alleging that there was a balance due them on said building and for extras of $49,725.75. The purpose of the suit is to enforce the lien on said building and lot given by the statute of West Virginia. Attached to the bill is a copy of the contract and exhibits containing an itemized statement of plaintiffs’ claim. Defendant, in due course, filed his answer, in which he admits that plaintiffs on August 6, 1907, ceased to labor or furnish material on said building, but denies that they had then fully completed the construction thereof in accordance with the contract. He denies that the amount claimed for extras is correct, alleges that he is entitled to a credit of $6,329.06 for work omitted, also that he has paid on account of the original contract $2,700 more than he is credited with. He alleges that by reason of delay on the part of plaintiffs from December 31, 1905, to August 6, 1907, to complete the building — being 583 days — he is entitled to recover, as measured damages, $50 per day, making $29,150. Exhibits, specifications, etc., are attached to the answer. The pleadings disclosed a controversy in respect to: (1) The amount due plaintiffs on original contract. (2) The amount due for extras. (3) The amount due defendant for omitted work. (4) The amount due defendant on account of delay.
After taking testimony, the judge proceeded to consider “the matters of principal dispute, involving legal propositions,” and thereupon referred the cause to the master with specific directions in respect to the manner in which, and the principles upon which, the account should be stated. In the opinion of the judge defendant was not entitled to recover any amount for delay. To this ruling defendant excepted. The master filed his report showing the amount due plaintiffs on the original contract and for extras, and amount due defendant for work omitted. The report discloses a most careful and intelligent consideration of the questions referred to the master. Each item of extra and omitted work and material is considered separately, following strictly the direction of the court. The amount found to be due on the original contract was $21,309.50, for extra work $11,-520.89. This amount is found to be subject to a credit, for omitted work, of $3,281.37. A number oí exceptions were filed by defendant. They were considered by the court, and a decree made declaring a balance due plaintiffs of $35,739.49. From this decree defendant prosecutes this appeal based upon 39 assignments of error. The cause was submitted in this court upon briefs and oral argument upon
“Any person having a lien, under or by virtue of this chapter, may enforce the same by filing a bill in chancery in the circuit court of the county in which his account is filed as aforesaid, etc.”
It is earnestly insisted that, because the mechanic’s lien is the creature of the state statute, it can be enforced only in the court prescribed by the statute. It is unquestionably true that, when the Legislature of a state creates a right, it may prescribe in which of its courts the right may be enforced, and may make, within the limitation of its own Constitution, such jurisdiction either exclusive or concurrent. Usually mechanics’ liens are enforced in those courts having jurisdiction of the causa litis, the enforcement of the contract; the lien being regarded as ancillary to the principal remedy. This generally carries actions for the recovery of money claimed to be due on contracts for material furnished or work and labor performed into the courts of law, where the claimant has an adequate remedy for the establishment of his debt. It frequently occurs, however, that questions of priority or conflicting liens are presented in which cases the law court has not the machinery for bringing into the record all interested in the proceeds of sale of the property and so moulding its decrees that the rights of all persons in interest may be protected, their liens transferred to the proceeds of the property, thus enabling the court to bring it to sale under such conditions .that the purchaser will acquire a perfect title and the owners and lienors receive its full value. That the Legislature of West Virginia had this purpose in view is indicated by the provision in the section of the statute which requires the plaintiff to make all other persons having liens parties and permitting any other person acquiring a lien before a decree shall be passed to make himself a party. The statute further provides that, if the original plaintiff fails to establish his claim, the suit shall not be dismissed, but may be prosecuted by any other party, etc. Whether it was the purpose of the Legislature to confer exclusive jurisdiction upon the court of chancery or only to permit the claimant to file his bill in chancery, thereby giving that court concurrent jurisdiction with the law court, it is not necessary for us to inquire. It is significant that the terms used in conferring the right is permissive, and not mandatory. In neither view can we suppose that it was the purpose of the Legislature to divest the jurisdiction of the federal court when the elements of diverse citizenship and the amount prescribed by the statute existed. This jurisdiction is of constitutional origin, and cannot be divested by state legislation. It is elementary learning that in cases such as this the jurisdiction is based not upon the character of the right to be enforced, but the diverse citizenship of the parties. The federal court, in such cases, administers the state law, as found in the state statutes and construed by the state court. The contention of the learned counsel that, because the state statute confers jurisdiction upon the chancery
“The state legislatures certainly have no authority to prescribe the forms and modes of proceeding in the courts of the United States; but, having created a right and, at the same time, prescribed a remedy to enforce it, if the remedv prescribed is substantially consistent with the ordinary modes of proceeding on the chancery side of the federal courts, no reason exists why it should not he pursued in the same form as it is in the state courts. On the contrary, propriety and convenience suggest that the practice should not materially differ when titles to land are the subjects of investigation.”
'Phis rule has been uniformly followed in the federal courts, and has been specifically applied to suits to enforce mechanics’ liens. In Davis v. Alvord, 94 U. S. 545, 24 L. Ed. 283, Mr. Justice Davis says:
“It is a suit in pqnily requiring specific directions for the sale of property, such as are usually given upon the foreclosure of mortgages and sale of mortgaged premises."
And Mr. Justice Field in Sheffield Furnace Co. v. Witherow, 149 U. S. 574, 13 Sup. Ct. 936, 37 L. Ed. 853 says:
“The foreclosure of a mechanic’s lieu is essentially an equitable proceeding.”
Jefferson Hotel Co. v. Brumbaugh, 168 Fed. 867, 94 C. C. A. 279, was a suit in equity to enforce a mechanic's lien. In Healey Ice Mach. Co. v. Green (C. C.) 181 Fed. 890, notwithstanding the state statutes creating the lien gave a right of action at law for its enforcement, jurisdiction in equity in the federal courts was maintained. 191 Fed. 1004. We are of the opinion that the Circuit Court had jurisdiction of the suit. The distinction between this case and the ruling of Judge Keller in Hirsch v. Independent Steel Co., 196 Fed. 104, cited by counsel, is clear.
“Attempts of parties to lie up by contract their freedom of dealing with each other are futile. The contract is a fact to be taken into account in interpreting the subsequent conduct of plaintiff and defendant, no doubt.”
While courts will enforce contracts, as made by the parties, they will require that both parties shall “live up” to them. One may not by a course of conduct induce another to act upon the understanding that there is a waiver of strict performance, thereby obtain an advantage or benefit and repudiate liability for fair compensation by invoking the terms of the contract. To do so is inequitable. Whatever difficulties a court of law may find in dealing with such cases by reason of technical rules of pleading disappear in a court of equity where
“We deem it sufficient to say tliat it must be conceded that, in the rebuilding of this hotel, a number of contracts, indeiJendent of the plaintiffs, were let whereby a large amount of work was to be done and material furnished by the company by and through independent contractors. It must be conceded, also, that the entire completion by plaintiff of his contract work was dependent upon these other contracts, or some of them being completed first. For these conditions, the Hotel Company must be held responsible.”
The opinion proceeds to point out the various causes which, in the course of the construction of a building on which a number of inde
‘■Courts cannot know of these conditions as they actually existed at the time, and the evidence would be very unsatisfactory taken months after tluvt would ¡U tempt to set forth all such conditions. Therefore the courts have laid down a very salutary rule to the effect that they will not attempt to apportion such delays when the causes thereof have been mutual, but will refuse under such circumstances to enforce the penalty.”
An examination of the cases cited in the opinion (Stewart v. Ketelas, 36 N. Y. 388; Heckman v. Pinkney, 81 N. Y. 211; Weeks v. Little, 89 N. Y. 566) disclose that no question in regard to enforcing a contract for liquidated damages is presented. It is because of the difficulty referred to that parties frequently, and especially in building contracts, insert a clause providing for a stipulated sum as measured or liquidated damages. The courts effectuate the intention of the parties as expressed in their contracts, and, subject to certain limitations, hold that amounts so agreed upon are liquidated damages, and not penalties. The principle is discussed and the authorities cited in Charleston Lumber Co. v. Friedman, 64 W. Va. 151, 61 S. E. 815. Mr. Justice Brannon quotes, with approval, the language of the New Jersey court in Monmouth Park v. Willis Iron Works, 55 N. J. Law, 132, 26 Atl. 140, 19 L. R. A. 456, 39 Am. St. Rep. 626:
“Wbore damages for breach of contract are uncertain in amount and not readily susceptible of proof, then, if the parties have expressly agreed upon a sum as tlie measure of compensation for the breach and that sum is not disproportionate to the presumable loss, it may be recovered as liquidated damages. Stipulations for specific or liquidated damages, on breach of a contract to build within a limited time, are enforceable.”
Again it is said:
“Because of the difficulty of ascertaining with certainty the damages-arising from failure to complete working contracts within the stipulated time, the parties to such contracts frequently provide for the payment of a specified amount as liquidated damages for failure to perform the contract in time and the courts have unhesitatingly upheld and enforced such provisions.” 30 Am. & Eng. Enc. 1263.
In Friedman’s Case the court sustained and enforced a contract for the payment of $10 a day for failing to complete a contract by a stipulated date. There is nothing in the circumstances attending this contract, the character of the work, the size and cost of the building, or other facts to take it out of the principle announced in these cases. The defendant is entitled to enforce the contract in this respect and recover the amount fixed as measured damages, unless for some valid legal reason, arising upon the evidence, he is prevented from doing so. The contract in the Jefferson Hotel Case provided that for each day’s delay the contractor was to pay $150, “excepting delays caused by the parly of-the second part.” it is said in that case:
•'The enforcement of penalties is not favored in equity, and they are so enforced only after the demandant therefor has shown that he himself has strictly complied on liis part with all the contract requirements prerequisite to such enforcement.”
This is unquestionably true where the claim made by the defendant is for a penalty. If, however, as in this case, the claim is for meas
“In ttie absence of actual fraud or mistake, a court of equity will not interfere with a contract made between parties competent to contract” (Bank v. Benington Coal & Coke Co., 51 W. Va. 60, 41 S. E. 390); and “it is the duty of the court to eonltrue contracts as they are made by the parties thereto, and to give full force and effect to the language used when it is clear, plain, simple and unambiguous” (Griffin v. Coal Co., 59 W. Va. 480, 53 S. E. 24, 2 L. R. A. [N. S.] 1115).
The question is discussed by the present Chief Justice in Sun Printing & Pub. Ass’n v. Moore, 183 U. S. 642, 22 Sup. Ct. 240, 46 L. Ed. 366, with a wealth of learning, upon both American and English authorities, reaching the conclusion that:
-* “The naming a stipulated sum to be paid for the nonperformance of a covenant is conclusive upon the parties in the absence of fraud or mutual mistake. Parties may, in a case where the damages are of an uncertain nature, estimate and agree upon the measure of damages which may be sustained from the breach of an agreement.”
The learned judge below cited this, and other cases, but was of the opinion that the "principle announced in them did not apply because it appeared that the delay had arisen by the joint and mutual fault of the owner or his independent contractors. It seems that in the Jefferson Hotel Case the court found it impossible to separate .such delays as were caused by plaintiffs from those caused by defendant and its independent contractors; hence refused to allow defendant to recover for any delays. The judge below in this case says:
“But it is insisted that the contract itself here provides, in express terms, for such apportionment of delay, and in this particular differs from the terms of the one in the Jefferson Hotel Case. It seems to me that this cannot change the situation. The law is that courts by reason of the very un-'eertainty, the impossibility to fairly and justly determine the causes of such mutual delays and their effects, will not attempt to apportion. This being true, no private contract, by its terms, can change the law or compel them to do so.”
Two questions are thus presented: Have the parties in this case provided for such apportionment? That is, agreed upon a rule for the guidance of the court? The amount is agreed upon “as measured damages” for each day’s delay after December 31, 1905. If the contract contained no other provision, no duty would be imposed, or power conferred, upon the court, in the absence of evidence of a waiver, to apportion the delays or inquire into their cause. The number of days during which the delay continued, after the period fixed for completion, multiplied by the amount to be paid per day, would fix the amount for which the contractors are liable. Recognizing that there would be days of delay for which the contractors should not be liable, the parties provide that, from the whole number of days of delay, the contractors are entitled to a credit for “the days when the weather forbids work * * * for each and every day they are delayed by the owner, or other contractor employed by the owner.” Thus three classes of delays, for which the contractors are to be credited, are expressly provided. Recognizing, further, that controversies
Modified.