The appellant Bradley Contracting Company holds a contract from the city of New York for the building of the Lexington Avenue subway at East Eighty-sixth street. In the prosecution of this work it was necessary to excavate Eighty-sixth street for a distance eastwardly from Lexington avenue. To do this the contractor removed the pavement, and substituted therefor a pavement of planking. It was proven without contradiction that this work was necessary to the execution of the contract; that it was done with the approval and under the direction of the Public Service Commission representing the city of New York, and that the work was done in the first instance with like approval, and in accordance with sound engineering practice. There are two
Shortly after six o’clock on the evening of June 11, 1914, the plaintiff stepped from the platform of a street surface car on Eighty-sixth street, just east of Lexington avenue. She stepped on one of the planks running longitudinally along the car tracks, and as she did so the plank broke and her foot and leg slipped through. The happening of the accident, the extent of the injuries received and the reasonableness of the verdict are not seriously questioned by the appellants, nor is it claimed that plaintiff was guilty of contributory negligence.
This leaves to be determined only the question of appellants’ negligence, and what we have to consider is the sufficiency of the evidence upon that question.
The mere happening of the accident does not establish the, liability of either defendant, for neither is an insurer of the safety of persons passing over the planked street. Before either can be held responsible for the undoubtedly defective condition of the plank which broke, notice either actual or constructive must be brought home to it that the plank was defective. This is a well-established rule as to the municipality, and is a rule which has frequently been applied in cases like the present to a contractor engaged in work similar to that upon which the contracting company was engaged. Of actual notice to either appellant there is no evidence, so that the sole question left in the case is whether or not either is chargeable with constructive notice. Such notice will generally be found where the defect is visible and apparent, and has been in that condition so long that the city or the contractor is presumed to have seen it, or to have been negligent in failing to see it.
The difficulty with plaintiff’s case is that, while we may
A witness named Kennedy, called by plaintiff, testified that all the planks in the vicinity showed signs of wear, and that planks which have been down even for only a few days will show signs of traffic. He saw the end of the plank after the accident and estimated that it was worn “ maybe an inch or so.” It is clear that this was a mere guess, and not the result of measurement or close observation. He apparently observed no visible defect in the plank before the accident, or at least testified to none.
A witness named Darling, also called by plaintiff, who had likewise been waiting for a car, said that the boards along the track and all around them “ looked good to me.”
These were the only witnesses who testified to the visible condition of the plank before the accident, and nowhere in the case is there any evidence that there was any apparent defect in the plank which could have been discovered upon inspection. Under these circumstances it is clear that the city was not chargeable with negligence. As was held in a recent case (Dougherty v. City of New York, 146 App. Div. 727): “ As the sidewalk was apparently safe, and “the excavation was in connection with subway construction work, the city was not chargeable with constructive notice, and the complaint was properly dismissed as to it.” (See, also, Matthews v. City of New York, 78 App. Div. 422; Farrell v. City of New York, 113 id. 687.)
As to the contracting company a like rule applies. Since the excavation of the street and -temporary planking over the excavation was rendered necessary by its contract with the city, it cannot be charged with maintaining a public nuisance, and that the method adopted and the means
Assuming, as I think we must, that the planking was properly laid in the first instance, the contractor, no more than the city, is to be held liable for a non-apparent defect of which it had no notice, actual or constructive. We have very recently decided in a similar case that the contractor’s duty is no greater than that of the municipality in the care of its streets. (Fithian v. Degnon Contracting Co., 175 App. Div. 386; Carr v. Degnon Contracting Co., 48 Misc. Rep. 531.)
It follows that there was no proof of negligence on the part of either appellant and that their several motions to dismiss the complaint at the end of the whole case should have been granted.
The judgment and order should be reversed and the complaint dismissed as to both appellants, with costs to said appellants in this court and the court below.
Clarke, P. J., Dowling, Smith and Page, JJ., concurred.
Judgment reversed, with costs and complaint dismissed, with costs.