Lead Opinion
A right to indemnity may rest on the express contractual provisions between two parties and would therefore be triggered by a breach of that contract.
We further find that a genuine issue of material fact remains as to whether Fox & Associates did, in fact, breach its contract with Schenkel & Shultz, and also reverse as to Fox & Associates’s counterclaim. However, because we conclude that Schenkel & Shultz knew or should have known of its injury more than three years before filing its direct claims of negligence and professional malpractice, breach of contract, and breach of warranty, we affirm the trial court’s grant of summary judgment in favor of Fox & Associates on those claims.
On 24 November 1998, the Charlotte-Mecklenburg Board of Education (“the school board”) contracted with Schenkel & Shultz to design a new vocational high school. The contract required Schenkel
In the spring of 2001, contractors, subcontractors, and other consultants began to question the adequacy of the structural steel design prepared by Fox & Associates, who, after being notified of the issues, reviewed its design and determined certain errors had occurred. Thereafter, Fox & Associates prepared and submitted remedial designs, which required additional work by the steel fabricators and erectors on-site to correct the errors. As a result, several multi-prime contractors incurred increased costs and invoiced the school board for payments exceeding three million dollars.
On 3 October 2001, the school board sent Schenkel & Shultz a letter stating that Schenkel & Shultz would be “held responsible for the cost of corrective work along with the cost required to accelerate the schedule due to delays caused by the corrective work.” The following day, Schenkel & Shultz notified Fox & Associates by letter that it would “look to [Fox & Associates] and [its] insurance carrier for full restitution of this cost.”
On 5 February 2002, Schenkel & Shultz sent Fox & Associates another letter asserting that it intended to hold Fox & Associates liable for any damages associated with deficiencies in the structural steel design. Additionally, Schenkel & Shultz maintained that, “Pursuant to the . . . agreement between [Schenkel & Shultz and Fox & Associates] . . ., [Schenkel & Shultz] hereby demands that [Fox & Associates] defend, indemnify and hold harmless [Schenkel & Shultz] in connection with any such claims.”
After failed mutual attempts to resolve the matter out of court, Schenkel & Shultz brought an action against Fox & Associates on 1 October 2004, alleging negligence and professional malpractice, breach of contract, breach of warranty, and indemnification. In response, Fox & Associates moved to dismiss and counterclaimed for breach of contract due to failure to pay, and thereafter moved for judgment on the pleadings. The school board, in turn, brought an action against Schenkel & Shultz for negligence and professional
On 25 February 2005, after converting Fox & Associates’s motion to dismiss to a motion for summary judgment, the trial court granted summary judgment to Fox & Associates and dismissed with prejudice Schenkel & Shultz’s direct claims for negligence and professional malpractice, breach of contract, and breach of warranty, finding that such claims were barred by the statutes of limitations. Thereafter, Fox & Associates moved for summary judgment as to Schenkel & Shultz’s remaining claim for indemnification and its own counterclaim for breach of contract. On 9 August 2005, the trial court granted Fox & Associates’s motion as to both claims and ordered Schenkel & Shultz to pay Fox & Associates the contractual amount.
Schenkel & Shultz now appeals both orders of summary judgment, arguing that the trial courts erred by (I) dismissing its direct contract, tort, and warranty claims on the basis of the statutes of limitations; (II) granting summary judgment to Fox & Associates on the claim for indemnification; and, (III) granting summary judgment to Fox & Associates on its counterclaim for breach of contract.
I.
Schenkel & Shultz first argues the trial court erred by holding that the applicable statutes of limitations barred its direct claims under contract, tort, and warranty. We disagree.
Claims of breach of contract, negligence and professional malpractice, and breach of warranty are all governed by a three-year statute of limitations. See N.C. Gen. Stat. § 1-52(1) (2005) (breach of contract); N.C. Gen. Stat. § 1-52(5) (2005) (“any other injury to the person or rights of another, not arising on contract and not hereafter enumerated”); N.C. Gen. Stat. § 1-52(16) (2005) (“for personal injury or physical damage to claimant’s property”). In most cases, the statute of limitations begins to run when the claim accrues, which generally occurs at the time of the breach. See Miller v. Randolph,
The accrual of the cause of action must therefore be reckoned from the time when the first injury was sustained. . . . When the right of the party is once violated, even in ever so small a degree, the injury, in the technical acceptation of that term, at once springs into existence and the cause of action is complete.
Mast v. Sapp,
Nevertheless, a statutory “discovery rule” offers a claimant additional time in certain contract or negligence actions to have the opportunity to discover the harm before the three-year statute of limitations begins to accrue. See N.C. Gen. Stat. § 1-52(16) (2005) (“for personal injury or physical damage to claimant’s property, the cause of action . . . shall not accrue until bodily harm to the claimant or physical damage to his property becomes apparent or ought reasonably to have become apparent to the claimant, whichever event first occurs.”); N.C. Gen. Stat. § 1-15(c) (2005) (“a cause of action for malpractice arising out of the performance of or failure to perform professional services shall be deemed to accrue at the time of the occurrence of the last act of the defendant giving rise to the cause of action”).
Here, Schenkel & Shultz argues that a genuine issue of material fact remains as to when the causes of action began to accrue, namely, when the harm was complete or either became apparent or ought reasonably to have become apparent. Schenkel & Shultz points to its complaint, filed 1 October 2004, which asserts that the school board notified Schenkel & Shultz of its belief that there were numerous problems with the structural steel design of the project “[beginning in October 2001.” However, in the 25 February 2005 order granting summary judgment, the trial court found that
[I]t has been established ■ by uncontroverted evidence that [Schenkel & Shultz] had actual notice and/or reason to know of*263 its claims arising out of any alleged negligence and professional malpractice, breach of contract and breach of warranty by [Fox & Associates] in connection with the structural steel design on the Project no later than August 9, 2001, a date more than three years prior to the filing of Plaintiff’s complaint.
This finding was based on the trial court’s “consideration of the pleadings, exhibits thereto, the Affidavit in Opposition to Motion for Judgment of the Pleadings filed by [Schenkel & Shultz] and the attachments thereto, and the arguments of counsel.” Included in those documents was an 8 May 2001 letter from Schenkel & Shultz to the construction project manager, “acknowledging] receipt of your letter dated May 3, 2001 regarding concerns raised by your structural steel subcontractor about the integrity of the structural steel design on this project” and noting that Fox & Associates had “decided to reexamine their complete structural steel design on this project.” Additionally, the record contains a letter from the project manager to Schenkel & Shultz, dated 9 August 2001, notifying Schenkel & Shultz of problems with the structural steel design in a specific part of the school being constructed.
Nonetheless, Schenkel & Shultz contends that the causes of action began to accrue not when the design was negligently provided or when it was informed of the potential steel design problems, but when it was actually harmed by Fox & Associates’s conduct. Thus, Schenkel & Shultz asserts that the accrual began in October 2001, when the school board first notified Schenkel & Shultz that it would be held responsible for the cost overruns and delays, and Fox & Associates declined to indemnify Schenkel & Shultz for the damages.
In a similar action against an architect for negligence arising out of a construction project, this Court held that the “date of the accrual of a cause of action is deemed to be the date of discovery of the defective or unsafe condition of a structure, and . . . the action must be brought within three years thereafter.” Quail Hollow East Condominium Ass’n v. Donald J. Scholz Co.,
Such is not the case here, where Schenkel & Shultz was promptly notified of Fox & Associates’s alleged negligence and malpractice and was on notice of a possible breach beginning in the spring of 2001. The 8 May 2001 and 9 August 2001 letters fall outside of the three-year statutes of limitations for the direct claims alleged in its complaint filed on 1 October 2004. The letters indicate that Schenkel & Shultz knew or had reason to know of the harm done to the project and the resulting breach of the underlying contract and warranty. Such knowledge would begin the accrual of the three-year statutes of limitations for Schenkel & Shultz’s direct claims.
Accordingly, we find that no genuine issue of material fact remains as to whether Schenkel & Shultz’s direct claims were barred by the statutes of limitations. We therefore affirm the trial court’s order of summary judgment as to Schenkel & Shultz’s claims of negligence and professional malpractice, breach of contract, and breach of warranty.
II.
Schenkel & Shultz next argues that a genuine issue of material fact remains as to whether Schenkel & Shultz has a right to express contractual indemnity, indemnity implied-in-law, or indemnity implied-in-fact.
We agree that viewing the evidence in the light most favorable to Schenkel & Shultz, the record indicates that a genuine issue of material fact remains as to whether the contract in this case expressly provides, through its incorporation by reference to a separate contract, for the right to indemnity. See Martin County v. R.K. Stewart & Son, Inc.,
Here, Schenkel & Shultz and Fox & Associates signed a “Standard Form Agreement Between Architect and Consultant,” which provides in Paragraph 1.1.2 of Article 1, “Consultant’s Responsibilities,” that
The Consultant’s [Fox & Associates’s] services shall be performed according to this Agreement with the Architect [Schenkel & Shultz] in the same manner and to the same extent that the Architect [Schenkel & Shultz] is bound by the attached Prime Agreement to perform such services for the Owner [the school board]. Except as set forth herein, the Consultant [Fox & Associates] shall not have any duties or responsibilities for any other part of the Project.
(Emphasis added). The school board and Schenkel & Shultz likewise signed a “Standard Form Agreement Between Owner and Designer,” in which Paragraph 1.7 specifies that “[t]he Designer [Schenkel & Shultz] shall be responsible for any error, design inconsistencies or omissions in the drawings, specifications, and other documents” and that “[t]he Designer [Schenkel & Shultz] will correct, at no additional cost or charges to the Owner [the school board] any and all errors and omissions in the drawings, specifications, and other documents prepared by the Designer [Schenkel & Shultz].” Paragraph 12.4 of the Agreement further provides that
*266 In the event a claim, suit, or cause of action is made against the Owner [the school board] . . . for . . . loss or damage resulting solely from any negligent act or omission of the Designer [Schenkel & Shultz] or out of the Designer’s [Schenkel & Shultz’s] breach of this Agreement, the Designer [Schenkel & Shultz] agrees to defend and hold the Owner [the school board], its agents, employees, servants, representatives, successors and assigns harmless and indemnified from and against any loss, costs, damages, expenses, attorneys fees and liability with respect to such claim, suit, or cause of action.
(Emphasis added). Thus, the Prime Agreement did expressly provide for a right to indemnity, and the contract between Schenkel & Shultz and Fox & Associates did bind the parties “in the same manner and to the same extent” as the Prime Agreement.
Additionally, when an agreement is ambiguous and the intention of the parties is unclear, interpretation of the contract is for the trier of fact. Silver v. N.C. Bd. of Transp.,
Here, Schenkel & Shultz filed its claim for indemnity before the school board instituted its action against Schenkel & Shultz for costs and damages incurred as a result of steel design errors. That action is still pending in federal court. Thus, the statute of limitations has not yet tolled against Schenkel & Shultz for its claim for indemnity against Fox & Associates.
Though we find an issue of fact exists regarding Schenkel & Shultz’s claim for express contract indemnity, we reject Schenkel & Shultz’s contentions for indemnity under the theories of contract implied-in-fact and contract implied-in-law.
As to a contract implied-in-fact, to determine if a right to indemnity exists, “we look to [the parties’] relationship and its surrounding circumstances.” Kaleel,
Regarding a contract implied-in-law, this Court has described indemnity through a contract implied-in-law as “a rather discrete legal fiction,” but has nonetheless stated that such a claim “arises from an underlying tort, where a passive tort-feasor pays the judgment owed by an active tort-feasor to the injured third party.” Id. at 39,
In sum, because a genuine issue of material fact remains as to the intention of the parties to provide for a right to indemnity by incorporation by reference and the “flow-through” contractual provision, we reverse the trial court’s order of summary judgment as to Schenkel & Shultz’s claim for express contract indemnity. However, we uphold the trial court’s order of summary judgment regarding Schenkel & Shultz’s claims for indemnity under the contract theories of implied-in-fact and implied-in-law.
III.
Lastly, Schenkel & Shultz argues that the trial court erred in granting summary judgment to Fox & Associates on its counterclaim, when Fox & Associates breached its contract with Schenkel & Shultz. Fox & Associates’s counterclaim alleged Schenkel & Shultz breached the contract by failing to pay Fox & Associates the money due for services performed pursuant to the contract. The trial court granted summary judgment in favor of Fox & Associates, awarding the company $37,787.50. We agree with Schenkel & Shultz and accordingly reverse the trial court’s order on this issue.
The record contains substantial evidence that Fox & Associates’s steel design was defective, including numerous letters offered as exhibits that demonstrated various parties’ concern with the structural integrity of Fox & Associates’s steel design. Accordingly, we believe a genuine issue of material fact exists whether Fox & Associates breached its contract with Schenkel & Shultz by supplying a defective structural steel design for the project. We therefore find that the trial court erred in granting summary judgment in favor of Fox & Associates on its counterclaim, and we reverse.
Affirmed in part, reversed in part.
Notes
. See Kaleel Builders, Inc. v. Ashby,
. This case was removed to federal court on 17 February 2005. Schenkel & Shultz filed a third-party complaint against Fox & Associates in the action, and the district court dismissed that complaint following the two entries of summary judgment against Schenkel & Shultz on its four actions against Fox & Associates in state court. See Charlotte-Mecklenburg Bd. of Educ. v. Schenkel & Shultz, Inc., No. 3:05-CV-69,
. Procedurally, we note in passing that specific assignments of error are not required “where . . . the sole question presented in [one party’s] brief is whether the trial court erred in granting summary judgment in favor of [the other party]. The appeal from the judgment is itself an exception thereto.” Vernon, Vernon, Wooten, Brown & Andrews, P.A. v. Miller,
Here, Schenkel & Shultz assigned as error the trial court’s grant of summary judgment denying its claim for indemnity on three different grounds: (1) express contract; (2) contract implied-in-fact; and, (3) contract implied-in-law. As such, the assignments of error were proper in questioning whether a genuine issue of material fact remains as to any of these three bases.
Moreover, we observe that the dissent’s assertion that Schenkel & Schultz’s “failure to preserve or argue the lack of an expert witness as a ground to grant summary
. The dissent cites to Candid Camera Video World, Inc. v. Mathews,
Again, however, we note that despite the dissent’s approach to the instant case solely as a professional negligence action, indemnity would also be required if a breach of contract were found.
Concurrence Opinion
concurring in part, dissenting in.part.
The majority’s opinion correctly affirms the trial court’s order of summary judgment on Schenkel & Shultz, Inc., formerly known as Schenkel & Shultz Architects, P.A.’s (“plaintiff’) claims for negligence and professional malpractice, breach of contract, and breach of warranty and reverses the trial court’s order granting summary judgment regarding Hermon F. Fox & Associates, RC.’s (“defendant”) counterclaim.
The majority opinion’s conclusion that, “because a genuine issue of material fact remains as to the intention of the. parties to provide for a right to indemnity by incorporation by reference and the ‘flow-through’ contractual provision” and reversal of the trial court’s order granting defendant’s motion for summary judgment regarding plaintiff’s claim for express contractual indemnity is error.
I. Failure to Assign Error
Plaintiff argues the trial court erred in granting summary judgment in favor of defendant on its indemnity claim. Defendant argued four separate grounds in support of dismissing plaintiff’s indemnity claim in its motion for summary judgment:
3) [Defendant] now seeks the dismissal of the Derivative Claim pursuant to Rule 56 on the grounds that there are no material issues of fact and that [defendant] is otherwise entitled to judgment as a matter of law. Specifically:
a) There is no express right to contractual indemnification between [defendant] and the Plaintiff;
b) There is no justification for an implied-in-fact indemnification between [defendant] and Plaintiff;
c) [Defendant] and Plaintiff, as engineer and supervising architect, do not satisfy the active-passive framework required for common law indemnification; and
d) Without an expert witness to establish [defendant’s] professional standard of care and breach thereof, Plaintiff cannot establish liability as a matter of law.
A. Lack of Expert Witness
On appeal, defendant argues plaintiff failed to designate an expert witness prior to expiration of the deadline and cannot satisfy its
The trial court’s summary judgment order does not specify upon which ground summary judgment was granted, and states, “There are no genuine issues of fact material to Plaintiffs claim for indemnification against Defendant and that Defendant is entitled to judgment as a matter of law.” Plaintiff failed to assign error or argue reversal of the trial court’s summary judgment order due to its failure to provide an expert witness to prove defendant failed to meet the applicable standard of care. This failure on plaintiff’s indemnity claim alone supports affirming the trial court’s order.
I. Standard of Care Required
“The standard of care provides a template against which the finder of fact may measure the actual conduct of the professional. The purpose of introducing evidence as to the standard of care in a professional negligence lawsuit ‘is to see if this defendant’s actions “lived up” to that standard[,]’ ” and this is generally established by expert testimony. Associated Indus. Contr’rs, Inc. v. Fleming Eng’g, Inc.,
The scope of appellate review is limited to consideration of the assignments of error set forth in the record on appeal and argued in appellant’s brief. N.C. R. App. 10(a) (2006); N.C. R. App. 28(a) (2006). Plaintiff failed to set forth any argument in its appellate brief to excuse its failure to designate an expert witness.
Plaintiff’s brief only addresses three of the four grounds defendant argued to grant summary judgment. Plaintiff’s failure to designate an expert witness supports the trial court’s grant of summary judgment in favor of defendant. Plaintiff’s assignment of error is not preserved or is abandoned and should be dismissed.
II. Lack of an Expert Witness
The majority’s opinion holds a genuine issue of material fact exists whether the contract between plaintiff and the school board provided for the indemnification of plaintiff by defendant by incorporation-by-reference and the flow-through contractual provision. Presuming an “indemnity” provision exists in these contracts, sum
The “indemnity” provision plaintiff relies upon states:
In the event a claim, suit, or cause of action is made against [the school board] and/or [the school boards’] representatives for any personal injury, including death, or property damage (other than to the work itself), or other loss or damage resulting solely from any negligent act or omission of the [plaintiff] or out of [plaintiffs] breach of this Agreement, [plaintiff] agrees to defend and hold [the school board] . . . harmless and indemnified from any loss, costs, damages, expenses, attorneys fees and liability with respect to such claim, suit, or cause of action.
(Emphasis' supplied). Even if this “indemnity” provision requires defendant to indemnify plaintiff, plaintiff cannot establish negligence liability as a matter of law without expert testimony to establish defendant’s professional standard of care and breach thereof. See Handex of the Carolinas, Inc. v. County of Haywood,
Plaintiff failed to disclose his expert witnesses within the time required. If defendant’s duty to indemnify arises “out of [plaintiff’s] breach of the Agreement,” with the school board, expert testimony is required to establish the breach. The trial court’s order granting defendant’s motion for summary judgment on plaintiff’s indemnification claim should be affirmed on the merits.
III. Contractual Indemnity
The majority’s opinion holds the trial court’s order granting defendant’s motion for summary judgment regarding plaintiff’s indemnification claim should be reversed because a genuine issue of
Plaintiff argues that defendant is contractually bound to indemnify it because plaintiff had contractually agreed to indemnify the school board. As noted earlier, the contract between plaintiff and the school board provides, in part, that:
In the event a claim, suit, or cause of action is made against [the school board] and/or [the school boards’] representatives for any personal injury, including death, or property damage (other than to the work itself), or other loss or damage resulting solely from any negligent act or omission of the [plaintiff] or out of [plaintiff’s] breach of this Agreement, [plaintiff] agrees to defend and hold [the school board] . . . harmless and indemnified from any loss, costs, damages, expenses, attorneys fees and liability with respect to such claim, suit, or cause of action.
The contract between plaintiff and defendant does not include this covenant or any express contractual provision for defendant to indemnify plaintiff. Plaintiff relies on Section 1.1.2 of its contract with defendant to argue the above language was “incorporated by reference” or implied into its contract with defendant. Section 1.1.2 of the contract between plaintiff and defendant provides:
[Defendant’s] services shall be performed according to this Agreement with [plaintiff] in the samé manner and to the same extent that [plaintiff] is bound by the attached Prime Agreement to perform such services for [the school board]. Except as set forth herein, [defendant] shall not have any duties or responsibilities for any other part of the project.
Plaintiff drafted the contract with defendant and failed to reference, include, or bargain for any indemnification by defendant. See Silvers v. Horace Mann Ins. Co.,
“Courts strictly construe an indemnity clause against the party asserting it.” Hoisington v. ZT-Winston-Salem Assocs.,
In interpreting a contract of indemnity, the court should give effect to the intention of the parties. But where the contractual language is clear and unambiguous, the court must interpret*274 the contract as written. Indemnity against negligence must be made unequivocally clear in the contract, particularly in a situation where the parties have presumably dealt at arm’s length.
Candid Camera Video,
A court is not free to incorporate, imply, or write into a “clear and unambiguous” contract covenants and conditions the parties themselves did not include. Id.; see Klein v. Insurance Co.,
“Where the language of a contract is clear and unambiguous, the court is obligated to interpret the contract as written, and the court cannot look beyond the terms to see what the intentions of the parties might have been in making the agreement.” Renfro v. Meacham,
The majority’s opinion correctly states, “a right to indemnity may rest on the express contractual provisions between two parties.” Here, the contract between plaintiff and defendant clearly and unambiguously does not contain an express contractual provision requiring defendant to indemnify plaintiff. No provision contained in the contract between the parties requires defendant to indemnify or hold plaintiff harmless for its negligence.
The trial court properly interpreted the contract and correctly determined it did not “unequivocally” provide for defendant to indemnify plaintiff. Candid Camera Video,
IV. Conclusion
The majority’s opinion correctly affirms the trial court’s order of summary judgment dismissing plaintiff’s claims for negligence and professional malpractice, breach of contract, and breach of warranty, and reverses summary judgment for plaintiff on defendant’s counterclaim.
Plaintiff’s failure to preserve or argue its lack of an expert witness as a ground to grant defendant’s motion for summary judgment
Alternatively, because the majority’s opinion addresses the merits of plaintiffs assignment of error, the trial court properly granted defendant’s motion for summary judgment. Plaintiff cannot establish negligence liability as a matter of, law without an expert witness. Handex of the Carolinas, Inc.,
Summary judgment on plaintiff’s indemnity claim should also be affirmed because the contract plaintiff drafted and relies on does not “unequivocally” provide for indemnification by defendant. See Candid Camera Video,
I vote to affirm the trial court’s order granting defendant’s motion for summary judgment and dismissing plaintiff’s indemnification claim. I respectfully dissent.
