Lead Opinion
Opinion
This personal injury lawsuit presents two issues for resolution. First, is a postaccident warning alerting consumers to take safety precautions in using a product admissible in a strict liability action against a manufacturer? Second, may a trial court utilize a remittitur to reapportion liability among the parties if it concludes that the jury’s apportionment is not supported by the evidence and that the damage award is excessive only to the extent that it reflects an improper apportionment?
I.
The facts are not in dispute. At the time of the accident, respondent, Duane Schelbauer, was a journeyman ironworker. He was employed by Pre
When Schelbauer arrived at the job site, the only construction left to be done on the addition was the roof. The job entailed fastening preformed roofing panels onto underlying structural components called purlins. The roofing panels were covered with a protective oil coating to prevent rusting and corrosion during shipping and storage.
The oil coating was originally applied by Bethlehem Steel Corporation which supplied the steel rolls to Butler. During the rolling and forming process, Butler often removed oil from steel surfaces which were excessively oiled and added oil to panels which were insufficiently сoated. Butler’s intention was that the panels leave the factory and arrive at the construction sites with a uniform oil coating.
Butler did not employ an inspector to examine the panels for excessive oil nor did it include any warning in its dealer information materials of the danger associated with possible oil excesses. Prior to Schelbauer’s accident, Butler had received no complaints of any accident occurring as a result of any excess oil or slippery condition of the roofing panels.
Schelbauer had not previously laid roofing which required fastening panels by clips. When he first reported to the work site on November 4, 1977, he received no specific instructions as to the proper methоd for fastening the roofing panels. Instead, he was simply directed by Pre-Fab’s foreman to “fall in” with the work crew as a fastener operator. Schelbauer watched one of his fellow workers and learned how the clips were placed on the purlins at the end of each panel to keep the panels aligned as they were being fastened. In fastening the clips onto the purlins, Schelbauer would place his left foot on a purlin and his right foot on a panel which had already been fastened. He would then bend at the waist and hold a clip in his left hand while fastening it with a screw gun which he held in his right hand.
Although the roofing was being laid on a flat surface, it was 25 feet above the ground. Schelbauer and his fellow workers were aware that the protective oil coating on the panels made them slippery and difficult to walk on. The only precaution which Schelbauer or any of the other fastener operators took while they were laying the roofing materials was to walk slowly and carefully on the panels.
Schelbauer’s injuries required 12 days of hospitalization and 8 months of recuperation at home, first in bed, then in a wheelchair. Subsequently, he was retrained as a building inspector and eventually returned to work 14 months after his accident. He experienced continuing problems from the injuries and four months later left his job to undergo surgery on his foot. Following the surgery, he wore a cast and participated in recuperative therapy. He was then rehospitalized for further treatment of his back. At the time of trial, he had not yet returned to work but was being retrained as a draftsman.
On March 14, 1978, Schelbauer filed a complaint against the general contractor, the owner of the building, Butler and various Does. The complaint included causes of action against Butler for breach of warranty, negligence, and strict liаbility in tort for a product defect. By July 1980, the actions against all defendants other than Butler had been dismissed.
Schelbauer’s action against Butler was tried before a jury beginning in November of 1980. During the trial, Schelbauer introduced into evidence a copy of Butler’s 1978 dealer information literature in which a warning had been added after Schelbauer’s accident.
On December 14, 1980, the case was submitted to the jury on both strict liability and negligence theories. The court instructed the jury that strict liability could be imposed on the manufacturer if its product had either a design or a manufacturing defect which was the proximate cause of the injuries. The jury was also instructed that the manufacturer could be found liable for negligence if it failed to exercise reasonable care in the manufacture or inspection of the product or if it failed to warn of a dangerous
The following day, the jury returned its special verdict in Schelbauer’s favor. It found that Butler was both strictly and negligently liable for Schelbauer’s injuries. It also found that neither Schelbauer nor his employer were contributorily negligent. The jury calculated the total amount of damages suffered by Schelbauer to be $865,000.
A judgment in Schelbauer’s favor in the amount of $697,500 (the аmount of the jury verdict less the amounts received in settlement from the other defendants) was entered on December 18th. The next day, notice of entry of judgment was mailed to the parties.
On December 31st, Butler filed a notice of intention to move for a new trial. The grounds stated for its motion were excessive damages, insufficiency of the evidence to justify the verdict that neither Schelbauer nor his employer were contributorily negligent, and two errors of law including the court’s ruling that evidence of Butler’s postaccident warning was admissible.
On February 17, 1981, after a hearing on Butler’s motion for a new trial, the trial court issued an order conditionally granting Butler’s motion for a new trial. Under this order, the motion would be denied if Schelbauer consented to а 15 percent reduction of his award.
On February 25, 1981, Schelbauer filed a written consent to the remittitur, and the court’s denial of Butler’s motion for a new trial went into effect. This appeal by Butler from both the judgment and the denial of the motion for a new trial followed.
II.
The first issue to be addressed is whether a postaccident warning is admissible as evidence in a strict liability case under the rule established by this court in Ault v. International Harvester Co. (1974)
In Ault, supra,
As this court explained in Ault, the purpоse of section 1151 ’s exclusionary rule is to avoid deterring individual tortfeasors from making improvements or repairs after an accident has occurred. While section 1151 may serve this function in typical negligence actions, it “plays no comparable role in the products liability field. ” (Ault, supra,
In addition, as this court noted in Ault, the application of the exclusionary rule in the strict liability context would be contrary to the public policy of encouraging distributors of mass-produced goods to market safer products. (Ibid., citing Note, Products Liability and Evidence of Subsequent Repairs (1972) Duke L. J. 837, 845-852.) Moreover, given the purpose of section 1151 and the difference between negligence and products liability actions, the express limitation of the section to causes of action for “negligence” or “culpable conduct” must have been deliberate. (Id., at p. 121.) Therefore, this court “decline[d] to judicially extend the application of the section to litigation founded upon [the strict liability] theory.” (Id., at p. 118.)
The rule adopted by this court in Ault was applied in Burke v. Almaden Vineyards, Inc. (1978)
The plaintiff in Burke sought to introduce evidence that four years after her accident, defendant had placed a warning on its bottles which cautioned consumers to point the cork away from people when opening. The trial court had ruled that evidence of the subsequent warning was not inadmissible under section 1151. On appeal, the reviewing court agreed with the trial court’s application of the Ault rule to a postaccident warning in the strict liability context. “As negligence or culpability is not a necessary ingredient in an action based upon strict liability against a manufacturer, the exclusionary rule of section 1151 does not apply to that field. (Ault v. International Harvester Co. (1974)
In Robbins v. Farmers Union Grain Terminal Ass’n (8th Cir. 1977)
In upholding the trial court’s admission of this evidence, the Eighth Circuit reasoned: “We have applied the Ault rationale in allowing proof of post-occurrence design modification and to a subsequent remedial instruction, and find no reason to bar its applicability to Rule 407 since Rule 407 is, by its terms, confined to cаses involving negligence or other culpable conduct. The doctrine of strict liability by its very nature, does not include these elements. See Ault v. International Harvester Co., supra and Passwaters v. General Motors Corp.,
Several other state courts which have similar rules of evidence precluding admissibility of postaccident warnings to prove negligence or culpable con
The rationale of Ault applies as clearly to postaccident warnings as it does to subsequent product repairs or improvements. Accordingly, the exclusionary rule of section 1151 was never intended to preclude admission of postaccident warning evidence in a strict liability action. The trial court’s ruling was correct.
III.
The second issue to be addressed is whether a trial court may use a remittitur in an order for a new trial to reapportion liability among the parties.
Ordinarily, a trial court has complete discretion in ruling on a motion for a new trial. Its ruling will not be disturbed absent an abuse of discretion. (Jiminez v. Sears, Roebuck & Co. (1971)
Butler points to Code of Civil Procedure section 662.5
Section 662.5 specifically statеs that the procedural device of remittitur is to be utilized only when a new trial is warranted solely on the grounds
The statutory requirement that use of remittitur be limited to those cases where jury error is confined to the issue of damages is express and unequivocal. This court has consistently adhered to this interpretation of section 662.5. (See, e.g., Hasson v. Ford Motor Co. (1982)
Schelbauer argues that since appellate courts recognized the power of trial courts to use a remittitur before the enactment of section 662.5, trial courts are not bound by the limitation of that section.
It is true that the use of remittiturs predates the enactment of section 662.5. Indeed, in Hughes v. Hearst Publications, Inc. (1947)
It is also correct that trial courts have traditionally exercised the authority to reduce excessive punitive damage awards, both before the power of remittitur was codified (see, e.g., Cotton v. Hallinan (1962)
What Schelbauer’s argument fails to recognize, however, is that even under the common law rule, use of remittiturs was uniformly confined to cases in which an excessive damage award was the only error in the jury’s verdict. (See, e.g., Hughes v. Hearst Publications, Inc., supra,
Schelbauer contends that since calculating punitive damages necessarily involves an assessment of a defendant’s “culpability,” the use of a remittitur to reapportion liability is “largely indistinguishable” from the use of a remittitur to reduce excessive punitive damages. However, section 662.5 expressly confines the use of a remittitur to reduce excessive damages and does not authorize its use beyond that limited context. The Legislature has set the boundaries beyond which a jury verdict may not be invaded by the use of a remittitur. This legislative prerogative should be respected.
Therefore, Butler’s contention that the trial court erred in its use of the remittitur is correct. A remittitur may not be used to condition a new trial order if a damage award is excessive only because it reflects an improper apportionment of liability. Accordingly, the trial court’s use of remittitur under these circumstances was an abuse of its discretion.
The only issue which remains to be decided is whether, devoid of the remittitur provision, the trial court’s order granting a new trial on all the issues was appropriate. Butler argues that since the trial court did not limit the order granting a new trial if the remittitur were not accepted, a new trial on all the issues is warranted. It further contends that since the trial court found substantial error in one aspect of the jury verdict, retrial
A reviewing court should not modify an order granting a new trial on all issues to-one granting a limited new-trial “unless such an order should have been made as a matter of law.” (Baxter v. Phillips (1970)
As the court’s order explains, the trial court found that there was insufficient evidence to justify the verdict “with respect to the issues of Plaintiff’s contributory negligence and the negligence of Plaintiff’s employer . ...” In the trial court’s view, the damages were excessive “in the sense (but not otherwise)” that they reflected the jury’s finding of no negligence on the part of Schelbauer or Pre-Fab. (Italics added.) In its statement of reasons, the court further expressed its opinion that Butler was at least partially liable for Schelbauer’s damages by stating that the jury “clearly should have apportioned fault among plaintiff, the employer and the defendant Butler Manufacturing Co.....” The statement of reasons expressly declared that the damages were excessive “only in the sense that the error with respect to contributory negligence and the employer’s negligence affected the amount of the damages.”
The order clearly indicates that the trial court (1) concurred with the jury’s special verdicts that Butler was liable to some extent and that the total damages sustained by Schelbauer were $865,000, and (2) disagreed only with the jury’s apportionment of liability.
Upon review of the evidence, there is ample support for the lower court’s conclusion that Butler was liable to some extent for Sсhelbauer’s injuries. The record reflects that the metal panels were covered with enough oil to make them slippery, that the method of affixing the panels to the buildings required workers to walk on them, that Butler did not adequately inspect the panels for excessive oil, and that the panels were sold without any warning cautioning consumers as to their dangerousness.
There was also sufficient evidence to support the trial court’s determination that both Schelbauer and Pre-Fab were also negligent. In his testimony, Schelbauer admitted that he was fully aware of the thick oil coating on the
Similarly, the record shows that Pre-Fab had previous experience with the panels and was well aware of the thick oil coating and of the danger of this condition to employees. However, Pre-Fab neither wiped the panels nor employed any safety methods to protect its workers from further accidents. There was testimony that Pre-Fab failed to instruct Schelbauer on a method for fastening the panels to the roof which was safer than the somewhat risky method he learned by imitating fellow workers.
Also, the record supports the jury’s special verdict as to the total amount of damages sufferеd by Schelbauer. The damage award was fully supported by the testimony of Schelbauer’s expert witness. The record adequately supports the trial court’s determination that the jury properly decided all the issues it addressed with the exception of the apportionment of liability.
There is no reason to subject the parties and the courts to the expense and delay of retrial of those issues on which the jury and the trial court agreed and which are supported by the evidence. Where, as here, the trial court has reviewed the jury’s special verdicts and has properly concluded that the jury’s apportionment of damages is erroneous but that the damage award is incorrect only to the extent that it refleсts an improper apportionment of liability, the trial court should have limited its new trial order to that issue. Accordingly, the new trial order is modified to limit the new trial to the issue of apportionment of liability.
A similar modification of a lower court order was made in Sharp v. Automobile Club of So. Cal., supra,
The court in Sharp rejected the defendants’ argument that the jury’s passion or prejudice in assessing the proper amount of exemplary damages must have permeated the jury’s consideration of the issue of whether exemplary damages should be awarded. The court noted that it had the benefit of the trial court’s evaluation that this had not beеn the case and that exemplary damages were appropriate. (Id., at p. 654.) Therefore, the court exercised its power to modify the lower court order to limit the issues on retrial. (Ibid.)
Other jurisdictions have also separated damage issues from liability issues for purposes of limiting new trials where retrial of the entire case was not warranted. (Caldwell v. Piggly-Wiggly Madison Co. (1966)
Under these circumstances, it is proper for this court to exercise its authority under section 43
IV.
The order which denied Butler’s motion for a new trial on the basis of Schelbauer’s consent to the improper remittitur is vacated. The valid order
Mosk, J., Kaus, J., Broussard, J., Reynoso, J., and Grodin, J., concurred.
Notes
The postaccident document on “Care of Building Panels” included the following language: “Occasionally, panels will be shipped that have a heavy oil coating. Reports of heavy oil coatings are rare and usually occur during the warm summer months. It is generally thought this is due to the material being subjected to higher temperatures in transit and at the job site than it is during in-plant storage, resulting in some flowing of the oil after shipment. The oil flowing from the bundles can stain wall panels and/or concrete. Panels should be checked on receipt so that if wiping of panels is necessary, it can be done without disruption of other erection activities as well as avoiding possible wall or concrete staining. Wiping may be a necessary safety precaution. . . . [¶] “Warning: Panels With Protective Oil Coatings Are Slippery. Proceed With Caution. Wipe Clean if Necessary.”
The court’s order read, in full, as follows:
“Defendant Butler Manufacturing Company’s motion for new trial is hereby granted, but on the condition that if Plaintiff shall serve and file, on or before March 9, 1981, a written consent to a reduction in the amount of damages by $129,750.00 (so that the resulting judgment, exclusive of costs, shall be $735,250.00 rather than the $865,000.00, awarded by the jury), then the motion for new trial is denied.
“This granting of the motion is on the ground of the insufficiency of the evidence to justify the verdict with respect to the issues of Plaintiff’s contributory negligence and the negligence of Plaintiff’s employer, and also on the ground of excessive damages in the sense (but not otherwise) that if the jury had found contributory negligence on the part of Plaintiff and negligence on the part of Plaintiff’s employer (as I believe they should have), then the damages actually awarded to Plaintiff would be less than under the verdict as rendered.
“The foregoing ruling contemplates contributory negligence of at least 5% and negligence of Plaintiff’s employer of at least 10%.
“The court’s specification of reasons will be filed within ten days.”
The day after this order was filed, the trial court issued a “correction” of the remittitur amount specified in the original order. This second order explained that the court’s first calculation was incorrect because it was based upon the amount of the jury’s verdict and failed to reflect the settlement amounts already paid by the codefendants. This second order did not, however, amend any other aspect of the original order.
On February 27, 1981, the court filed its statement of reasons further elaborating the basis for its order. The statement of reasons provided in relevant part: “The jury found no contributory negligence of the plaintiff and no negligence of plaintiff’s employer. But the evi
“. . . I am satisfied that the jury clearly should have found contributory negligence, as well as negligence of the employer, and also that such negligence of plaintiff and negligence of the employer were proximate causes of plaintiff’s injuries. The jury clearly should have apportioned fault among plaintiff, the employer and the defendant Butler Manufacturing Co.; it was unreasonable to assign all fault to Butler alone.
“. . .In such a case it is possible to say, therefore, that the jury’s error has had the effect of increasing damages beyond the amount which would have resulted from the verdict if that error had not been made. For this reason, it was pointed out in the order granting the motion for a new trial that excessive damages was one of the grounds, but only in the sense that the error with respect to contributory negligence and the employer’s negligence affected the amount of the damages.”
Section 1151 provides: “When, after occurrence of an event, remedial or precautionary measures are taken, which, if taken previously, would have tended to make the event less likely to occur, evidence of such subsequent measures is inadmissible to prove negligence or culpable conduct in connection with the event. ”
All further references to section 1151 refer to this Evidence Code provision.
Rule 407 provides in relevant part: “When, after an event, measures are taken which, if taken previously, would have made the event less likely to occur, evidence of the subsequent measures is not admissible to prove negligence or culpable conduct in connection with the event. ...”
The Advisory Committee’s note to rule 407 states that the federal rule is comparable to section 1151. (2 Weinstein & Berger, Weinstein’s Evidence (1975) p. 407-3.)
All subsequent statutory references are to the Code of Civil Procedure unless otherwise indicated.
Butler has also challenged the verdict entered pursuant to the remittitur because Schelbauer consented to the remittitur after the court’s jurisdictional period had expired. According to section 660, “the power of the court to rule on a motion for a new trial shall expire 60 days from and after the mailing of notice of entry of judgment by the clerk of the court . . . .” Butler argues that although the court’s conditional order was filed within the statutory period, Schelbauer did not accept the remittitur until after the 60-day period had expired. Consequently, Butler asserts, Schelbauer’s consent to the remittitur is void, the condition was not met, and the new trial order must be enforced.
Butler contends that this rule of law is “clear” from Jehl v. Southern Pac. Co. (1967)
An argument similar to Butler’s was fully evaluated and rejected in Chodos v. Superior Court (1964)
The Chodos reasoning was reevaluated and affirmed after Jehl in Alberton v. Superior Court (1968)
This court agrees with “the legal soundness and the practical desirability” of the Chodos rule. Accordingly, as long as the trial court issues its order on the new trial motion within the 60-day period prescribed by section 660, it may exercise discretion in setting reasonable time limits for the plaintiff to accept a conditional remittitur.
Here, the trial court issued its order conditionally granting Butler’s new trial motion within the 60-day limit. By its terms, Schelbauer was given less than three weeks to serve and file his acсeptance. This relatively short time period was not unreasonable. Therefore, this challenge to the remittitur must be rejected.
Section 43 provides in relevant part: “The Supreme Court, and the courts of appeal, may affirm, reverse, or modify any judgment or order appealed from, and may direct the proper judgment or order to be entered, or direct a new trial or further proceedings to be had.”
Concurrence Opinion
While I concur with the majority, I have one caveat to add to my agreement with regard to section II of the opinion. I join in that part of the opinion under authority of Ault v. International Harvester Co. (1974)
In any event, I wish to emphasize a point impliсit in the majority opinion that merely because section 1151 may not bar introduction of evidence regarding postaccident warnings, such evidence is subject to the court’s complete discretion to “exclude evidence if its probative value is substantially outweighed by the probability that its admission will . . . (b) create substantial danger of undue prejudice, of confusing the issues, or of misleading the jury.” (Evid. Code, § 352; see 2 Weinstein & Berger, Weinstein’s Evidence (1975) ¶ 407[03] at p. 407-14 & fn. 7 [“The most desirable approach is to treat products liability cases as governed by Rule 403 [analogous to § 352] rather than Rule 407 [analogous to § 1151], thereby giving the judge
On February 7, 1984, the opinion was modified to read as printed above.
Retired Associate Justice of the Supreme Court sitting under assignment by the Chairperson of the Judicial Council.
