Scheflow v. . PierceScheflow v. . Pierce
It wоuld seem that the court overruled the demurrer as to the ground that plaintiff could not maintain this action, and the defendants are not appealing. In a case almost exactly like this it was held that “The beneficiaries of the contract, though not a party or privy thereto, may maintain an аction thereon.”
Gastonia v. Engineering Co.,
In
Supply Co. v. Lumber Co.,
Our decision in
Gorrell v. Water Co.,
The contract of the defendant Pierce stipulates (section 17) that he will give a surety bond “conditioned to securе the faithful performance of this contract, the payment for all materials purchased and used under this contract, the payment of wages of laborers employed by said contrаctor on the works, and the liens which may arise therefrom.” Said contractor subsequently made the contract with the plaintiff as a subcontractor, and the bond of the surеty stipulates that Pierce, the contractor, “shall in all things stand to and abide by, and well and truly observe, do, keep, and perform all and singular the terms, covenants, conditions and agreements in said contract, on his part.” Eevisal, 2019, gives to all subcontractors and laborers a lien for “labor donе or material furnished, which lien shall be preferred to the mechanic’s lien now provided by law.”
As is said in
Gastonia v. Engineering Co.,
Though no lien can be filed against the town of Tarboro, it would be liable, under Eev., 2016, to laborers and materialmеn, and, under Eev., 2019, for labor done and material furnished to the extent of any balance-due the contractor and unpaid at the time of the notice. The city, in its-contract with Pierce, required him to give the bond for compliance with his contract in all respects, which, of course, included laborers and material, and supplies, under Eev., 2016, and what shall be due the subcontractors for work and labor done (Eev., 2019).
The first clause in the contract with Pierce is, that hе should “furnish, at his own expense, all the material, labor, and equipment necessary to do the work.” He furnished the same, but not at his own expense, fora great part of the labor done on the job is yet unpaid for, including this, plaintiff, and the condition of the bond is broken. It would be strange-if the plaintiff, who did practically all the wоrk on the job, should not have recourse to the bond for the amount due him, solely because he did. the work with a machine instead of with his own hands or by hiring-laborers to work with their hands.
The defendant surety company cites cases such as
Boiler Works v. Surety Co.,
43 L. R. A. (N. S.), 162, where it was held that a subcon
*94
“tractor could not file a claim for the repairs on a steam shovel which had been used by him. Also,
Public Works Co. v. Yonkers,
Lohman v. Peterson,
This plaintiff’s claim is simply for the work and labor done, as subcontractor, at the stipulated rate. It is admitted by the demurrer, of course, that the balance due.him by the contractor is the amount alleged, for which the plaintiff has obtained judgment against said contractor in this action.
The contract of Pierce with the city being to do that very work, and the contract with the surety company being that he shall faithfully perform all thе provisions of his contract, which includes this very trenching which the plaintiff has done, and which said Pierce contracted to “furnish at his own expense,” it follows that the plaintiff is entitled to sue as beneficiary under the contract, and to recover of the surety company the balance due by Pierce for the execution of such work by the plaintiff. The identical point presented in this case was decided in
Lester v. Houston,
“3. The constitutional provision for giving to mechanics and laborers liens for their work, and the statutes enacted in pursuance thereof j and .also giving liens for materials furnished, extend to and embrace contractors who do not themselves perform the labor or furnish the materials used, but procure it to be done through the agency of others.”
This was cited with approval by
Allen, J.,
in
Mfg. Co. v. Andrews,
The judgment sustaining the demurrer should be
Reversed.