97 S.E. 167 | N.C. | 1918
This is an action against the defendant Pierce, the town of Tarboro, and the National Surety Company as the surety for the faithful performance of the contract by the defendant Pierce to do certain sewerage work and pipe-laying in the streets of said town. Soon after the execution of said contract and the bond of the surety, the plaintiff and said Pierce entered into a contract by which the plaintiff was to excavate the sewer trenches, using a trench machine for that purpose, with a competent operator on it, furnishing the fuel, oil, and repairs, and operating the machine to do the work. The plaintiff was to receive for said work a stated sum per foot, according to the depth of the trenches cut.
The plaintiff began work under his contract and cut a great number of trenches of varying depths. That the balance due him for the work done on the contract is $1,350.85 is not disputed. The defendant Pierce failed to pay this balance, alleging that he is financially unable, and the town of Tarboro and the National Surety Company base their refusal upon the ground that they are not liable therefor and that the bond executed by the surety company does not cover the plaintiff's claim. The defendant Pierce failed to answer, and judgment by default final was entered against him. The town and the surety company demurred. The court, it seems, overruled the demurrer as to the plaintiff's right to maintain the action direct on the bond, but sustained the demurrer that the plaintiff's claim was not covered by the bond, and the plaintiff appealed.
It would seem that the court overruled the demurrer as to the ground that plaintiff could not maintain this action, and the defendants are not appealing. In a case almost exactly like this it was held that "The beneficiaries of the contract, though not a party or privy thereto, may maintain an action thereon." Gastonia v. Engineering Co.,
In Supply Co. v. Lumber Co.,
Our decision in Gorrell v. Water Co.,
The contract of the defendant Pierce stipulates (section 17) that he will give a surety bond "conditioned to secure the faithful performance ofthis contract, the payment for all materials purchased and used under this contract, the payment of wages of laborers employed by said contractor on the works, and the liens which may arise therefrom." Said contractor subsequently made the contract with the plaintiff as a subcontractor, and the bond of the surety stipulates that Pierce, the contractor, "shall in all things stand to and abide by, and well and truly observe, do, keep, and perform all and singular the terms, covenants, conditions and agreements in said contract, on his part." Revisal, 2019, gives to all subcontractors and laborers a lien for "labor done or material furnished, which lien shall be preferred to the mechanic's lien now provided by law."
As is said in Gastonia v. Engineering Co.,
Though no lien can be filed against the town of Tarboro, it would be liable, under Rev., 2016, to laborers and materialmen, and, under Rev., 2019, for labor done and material furnished to the extent of any balance due the contractor and unpaid at the time of the notice. The city, in its contract with Pierce, required him to give the bond for compliance with his contract in all respects, which, of course, included laborers and material, and supplies, under Rev., 2016, and what shall be due the subcontractors for work and labor done (Rev., 2019).
The first clause in the contract with Pierce is, that he should "furnish, at his own expense, all the material, labor, and equipment necessary to do the work." He furnished the same, but not at his own expense, for a great part of the labor done on the job is yet unpaid for, including this plaintiff, and the condition of the bond is broken. It would be strange if the plaintiff, who did practically all the work on the job, should not have recourse to the bond for the amount due him, solely because he did the work with a machine instead of with his own hands or by hiring laborers to work with their hands.
The defendant surety company cites cases such as Boiler Works v. SuretyCo., 43 L.R.A. (N.S.), 162, where it was held that a *94
subcontractor could not file a claim for the repairs on a steam shovel which had been used by him. Also, Public Works Co. v. Yonkers,
Lohman v. Peterson,
This plaintiff's claim is simply for the work and labor done, as subcontractor, at the stipulated rate. It is admitted by the demurrer, of course, that the balance due him by the contractor is the amount alleged, for which the plaintiff has obtained judgment against said contractor in this action.
The contract of Pierce with the city being to do that very work, and the contract with the surety company being that he shall faithfully perform all the provisions of his contract, which includes this very trenching which the plaintiff has done, and which said Pierce contracted to "furnish at his own expense," it follows that the plaintiff is entitled to sue as beneficiary under the contract, and to recover of the surety company the balance due by Pierce for the execution of such work by the plaintiff. The identical point presented in this case was decided in Lester v. Houston,
"3. The constitutional provision for giving to mechanics and laborers liens for their work, and the statutes enacted in pursuance thereof, and also giving liens for materials furnished, extend to and embrace contractors who do not themselves perform the labor or furnish the materials used, but procure it to be done through the agency of others."
This was cited with approval by Allen, J., in Mfg. Co. v. Andrews,
The judgment sustaining the demurrer should be
Reversed. *95