Scanlon v. Northwood

147 Mich. 139 | Mich. | 1907

Carpenter, J.

January 27, 1904, plaintiff and defendant executed a written contract whereby the former agreed to do the mason work, the lathing, and plastering of a house, to be built for the latter, for the sum of $500. June 21, 1904, while the work was progressing, and after plaintiff had received $270, the parties executed another writing whereby, in consideration “of fear that the contract price * * * viz., $500.00, would not be sufficient to compensate him” (plaintiff), defendant agreed to pay plaintiff “such sum of money after the contract price is exhausted, as will insure to him after the payment of all help employed by him * * * the usual or going day wages paid to others for performing like work.” Plaintiff having completed the work brought this suit to recover compensation.

1. The important question is whether the writing of June 21st constituted a binding contract. The circuit judge held that it did. Defendant contends that this holding was erroneous upon the ground that, plaintiff being obligated to do the work for $500, there was no consideration for his (defendant’s) agreement to pay more than $500. The testimony of plaintiff — and this testimony was corroborated by another witness and was not contradicted— tends to prove that, immediately before that writing was *141made, the parties had a conversation in the course of which plaintiff informed defendant that he “would not work any longer on the old contract.” This brings the case within the principle of Blodgett v. Foster, 120 Mich. 392, and compels us to hold that there was a consideration for defendant’s agreement. See, also, Goebel v. Linn, 47 Mich. 489; Moore v. Locomotive Works, 14 Mich. 266.

2. Defendant contends that plaintiff’s testimony above stated tended to vary the terms of the writing of June 21st, and was therefore inadmissible. We think this testimony was admissible under the familiar rule which permits the consideration of a written agreement to be proved by parol testimony. 17 Cyc. p. 648.

3. Defendant also contends that the trial court erred in not leaving to the jury the question of the existence of a consideration for defendant’s agreement. Defendant did not request the trial judge to submit this issue to the jury, and, as already indicated, the testimony of plaintiff relative to the consideration was corroborated and undisputed. Under the circumstances we think it was not error for the court to dispose of it as a fact conclusively established.

4. It is contended that the trial court should have permitted the jury to determine whether the work was done under the old contract or under the contract of June 21st. This contention is made because plaintiff testified that defendant claimed, after the new contract was made, that he (plaintiff), was working under the old*contract. It is quite clear that plaintiff did not assent to this claim of defendant and that the claim was unwarranted.

5. The trial court charged the jury:

“ It isn’t a question of whether he built the building according to the contract (the original contract) * * * because that contract was waived when this (the contract of June 21st) was signed.”

It is claimed that this was erroneous, because it had a tendency to induce the jury to believe that plaintiff was not bound to comply with the original contract, whereas *142“the first consideration was, Could the work have been performed within the contract price of $500 and net Scanlon day wages?” We think this criticism unwarranted. The statement under consideration, indicating (and very properly indicating) as it does that the rights of the parties are governed by the contract of June 21st, clearly implies — as that contract fairly construed provides — that plaintiff is not entitled to additional compensation if $500 is sufficient.

No other question demands consideration.

Judgment affirmed.

Montgomery, Ostrander, Hooker, and Moore, JJ., concurred.
midpage