Opinion by
Phil Savitz instituted an action in assumpsit against Fred Gallaccio and Frank Reale, individually and trading as Western Construction Company, to recover ten weeks salary under a written contract of employment. The jury returned a verdict in favor of plaintiff. Defendants’ motions for judgment n.o.v. and for a new trial were refused, and judgment was entered on the verdict. This appeal followed.
The contract in question was prepared by appellants’ attorney, and was executed by the parties in November 1951. It set forth that appellants had entered into an agreement with the City of Philadelphia to construct a sewer on Castor Avenue; that they were desirous of obtaining additional working capital, and that appellee had a sum sufficient to meet their needs; that appellants were seeking the services of an experienced and competent general superintendent to super *592 vise the construction of the sewer, and that appellee enjoyed “a valuable reputation for being a competent supervisor of that type of construction work which has been gained as a result of 40 years’ experience”. By the terms of the contract appellee loaned appellants $14,000.00, which sum was to be repaid no later than the date of final settlement by the City, and appellants agreed to employ appellee as general superintendent of the sewer job at a salary of $150.00 per week. The employment was to commence at such time as construction of the sewer was started and to continue until the sewer had been completed and was accepted by the City. The contract also contained a bonus provision not here involved.
The sewer job commenced in February 1952. At that time, appellee was hospitalized as the result of an accident. According to appellee’s testimony, he talked with appellants daily and advised them about the work. However, appellants testified that it was necessary for them to employ another superintendent during this period. Appellee testified that appellants requested him to come to work as soon as possible and insisted that he start in May, even though he was still on crutches. This was denied by appellants, who testified that, when appellee appeared at the job, he was seeking work and they orally agreed to employ him at $150.00 a week for an indefinite period. It is undisputed that appellee actually did start to work on May 28, 1952, and that he was paid a salary at $150.00 per week. He testified that the job was then twenty percent completed. On November 5, 1952, appellee was informed that appellants could not use him any more. At that time the job was ninety percent completed. During the period from May to November, appellee was the only superintendent on the job. Neither the appellants, the City Engineer, the City Inspector, nor *593 any other person complained to appellee that the work was being done improperly. However, appellants introduced considerable testimony tending to show that appellee was unfit to act as a superintendent. Appellee testified that he made no effort to secure other work after his discharge because, at that time of the year, employment as a superintendent was impossible to obtain.
Appellants first contend that appellee’s “failure and incapacity” to begin work caused them to change their position by the employment of another superintendent, which “evidences conclusively” that they elected to regard appellee as having breached the written contract. They base this argument upon section 282 of the Restatement, Contracts, set forth in the footnote.
1
Assuming that there was a “breach” by the appellee, the question whether appellants elected to rescind was a factual issue for the jury to determine. While appellee’s physical incapacity might have been utilized by appellants to relieve them from performance, the evidence justified the jury in finding that appellee provided, and appellants accepted, advisory service while appellee was in the hospital; further that, during the entire period of appellee’s hospitalization, appellants took no steps to complete rescission of the contract by offering to repay the loan so as to restore appellee to his previous status. See
Fowler v. Meadow
*594
Brook Water Co.,
Appellants next contend that, since the sole issue pleaded by appellee was unlawful discharge, it was error for the trial judge to admit evidence concerning that portion of the contract dealing with the loan; further that this evidence was “malicious and tended to inflame prejudice and confuse the jury”. No objection was made at trial to the admission of the entire Avritten contract. A party offering a paper in evidence must offer the whole of it just as it is, and, if it requires explanation, the burden is upon him to explain:
McMichael v. Tucker,
Appellants next contend that appellee’s failure to seek other employment bars him from recovery. They rely upon Comment d to section 336 of the Restatement, Contracts, which states in substance that if an injured party fails to make a reasonable effort to mitigate damages, with the result that his harm is greater than it would otherwise have been, he cannot recover the avoidable and unnecessary increase. Appellants attempted to show that jobs for superintendents were available in the Philadelphia area. The testimony in this connection was conflicting and contradictory. The trial judge expressly charged, as requested by appellants, that, “if the jury believes from the evidence in the case that plaintiff might by the exercise of reasonable diligence have secured other similar employment at the same rate of pay, then the jury must find that no damages are due the plaintiff”. Furthermore, the trial judge had previously charged, quoting from
Speier v. Locust
Laundry,
Appellants next contend that the verdict “was manifestly capricious and contrary to the clear weight of evidence in quantity and quality in that plaintiff did not competently and skillfully perform under his agreement to supervise defendants’ sewer construction and therefore appellants properly discharged him”: and further “that the verdict was capricious, perverse and improper”. The granting of a new trial on the ground that the verdict is against the weight of the evidence is peculiarly for the court below, and its decision is not a matter for review on appeal in the absence of palpable abuse of discretion:
Yago v. Pipicelli,
Appellants’ final contention is “that the trial court committed basic reversible error in failing to instruct the jury on established methods of factual determination, such as quantity and quality of evidence, interested and disinterested witnesses, credibility of witnesses, the nature and weight of expert testimony, the shifting of burden of proof and the meaning of preponderance of evidence”. Although there is merit in appellee’s position that this contention was not raised in the lower court,
Megliss v. Bartoletta,
159 Pa. Su
*597
perior Ct. 308,
Judgment affirmed.
Notes
“In promises for an agreed exchange a promisor is discharged from the duty of performing his promise if the return performance has become impossible by the death or physical incapacity of some person whose action is requisite, or if the promisor materially changes his position because such a person’s condition makes it probable that he will either be unable to perform the requisite action or able to perform it only at the risk of causing death or serious iUness, provided that the promisor has not himself wrongfully caused the death, incapacity or personal condition or assumed the risk of it”.