194 Iowa 152 | Iowa | 1922
The contract in suit was as follows:
“This agreement made and entered into this 11th day of April, 1918, at Des Moines, Iowa, by and between Frank Cram
Hauls of 1 mile or less $.40 per yd. of 3000^
“ “ 2 miles .55 “ “ “
“ “ 3 “ .70 “ “ “ “
“ 4 “ .85 “ “ “
“ £i 5 ££ for sand .90 “ ££ ££ ££
££ ££ 5 “ for gravel 1.00 ££ ££ ££ ££
over the even mile to be classed as the nearest quarter mile and for each quarter mile over the even mile to be rated at an additional four cents per yard up to the five-mile haul when each quarter mile will be rated at five cents per yard above the five-mile rate.
“The party of the first part agrees to make payments for hauling each week to the party of the second part at above rates.
“The party of the second part does hereby agree to haul one thousand yards of sand or gravel each month for six consecutive months or more beginning with May 1, 1918, and the party of the first part agrees to supply at least one thousand yards each month for the time mentioned above.
“The party of the first part further agrees to have six hundred yards of the one thousand yards of sand or gravel in the four or five-mile hauls or a ton mileage equal to above amount.
£ £ The party of the first part further agrees to keep the private road from the sand and gravel bins to the main public road in condition for heavy hauling and also agrees to arrange that all sand and gravel will not have to be handled by hand.
“It is further agreed by both parties hereto that the hauling of the sand and gravel to the new Savery Hotel job or the storage pile for same shall not be over the five-mile rate nor less than five-mile rate.”
At the time this contract was entered into, the plaintiff was the owner of a Denby 2-ton truck, and was negotiating for the purchase of another truck, known in the record as the Masters 6-ton truck, which purchase was later completed. These
. It appears that there was a section of private road extending from the public highway to the defendant’s sand bins. The condition of this road furnishes the nub of the controversy. The defendant undertook by the contract to keep this section of road “in condition for heavy hauling.” This road was located on the river flats, and was peculiarly susceptible to weather conditions. The plaintiff made a start about May 15th upon the performance of his contract, and presented himself with both trucks at the sand bins for that purpose. His large truck, after being loaded, mired down upon the road in question, and had to be unloaded. A day or two later, a further attempt was made, with practically the same result. The evidence is sufficient to show that the road was not in a suitable condition to carry a 6-ton load; and that it was not put in such condition, if at all, for a considerable period of time. Overflows of the river' followed a short time later, which naturally deferred all efforts at putting the road in condition. After the two attempts here noted, and before any substantial repair of the road had been made by the defendant, the plaintiff declared a breach of the contract, and abandoned it. He sues for the breach, and claims as his measure of damages the profit which he would have made upon the contract if he had been permitted to perform it.
Quite a volume of evidence has been devoted to the suitability of the large truck for use in the performance of the contract. Because it was large, it was to some degree unwieldy. It was a so-called semitrailer truck: that is to say, a two-wheeled trailer was attached to the main chassis of the truck, and the load was distributed over the wheels of the trailer and over the rear wheels of the truck proper. Because of the two pivots which were rendered necessary by such a combination, the truck was unwieldy for the purpose of backing into position at the bins. It is contended also that a 6-ton weight was beyond the contemplation of the defendant in entering into the contract, because trucks of such weight-carrying power were not in general use. "We have no occasion to dwell upon the details of this feature of the controversy. The evidence for the plaintiff was sufficient to show that the defendant knew of his negotiations
As an abstract legal proposition, loss of profits does afford a proper basis for the measure of damages for breach of contract, provided that the profits claimed are not remote, and are of such a nature as are capable of proof by reasonably certain evidence, and provided further that the evidence given in proof thereof is reasonably definite and certain. Hichhorn, M. & Co. v. Bradley, 117 Iowa 130; Rule v. McGregor, 117 Iowa 422; Gibson v. Fischer, 68 Iowa 29; Taft v. Tiede & Co., 55 Iowa 370; Huntington v. Haish Co., 190 Iowa 1197.
The authorities relied on by the appellant (Morgan v. Sutlive Bros., 148 Iowa 318; Howard v. Brown, 168 Iowa 410; Howe Mach. Co. v. Bryson, 44 Iowa 159; Winne v. Kelley, 34 Iowa 339) were all cases where the profits were remote, or were of such a nature as to be incapable of reasonably certain proof, or where the evidence actually offered failed to measure to that standard. All unliquidated damages are, in a sense and to a degree, uncertain and indefinite. They are subject to much exaggeration in the estimates of witnesses, and likewise subject to be unduly minimized by contrary witnesses. But the jury is deemed to be capable of weighing exaggerations and of ascertaining the approximate damage, provided that the data before them upon which the damages are predicated are sufficiently definite and certain to shut out the field of mere conjecture and speculation.
In Morgan v. Sutlive Bros., 148 Iowa 318, 330, 331, cited by the appellant, the rule as to loss of profits is stated as follows:
“The rule as to loss of profits is that they are not to be rejected as being necessarily uncertain and speculative, but, when they are in fact uncertain and speculative in a given case, they cannot be considered, because incapable of adequate proof. This qirestion is quite fully discussed in Hichhorn v. Bradley, 117 Iowa 130. See, also, Howe v. Bryson, 44 Iowa 159; Winne v. Kelley, 34 Iowa 339; Bank v. Thurman, 69 Iowa 693; Manufacturing Co. v. Creamery, 120 Iowa 584; Wakeman v. Wheeler,
In the case above cited, the damages were predicated upon the failure to furnish certain rubber spools. The only measure of damage claimed was the expected profits to be realized upon a resale of the spools after further labor had been expended upon them. The proposed resale would be an enterprise separate and distinct from the contract of the manufacturer to furnish them, and would involve the consideration of many uncertain elements and contingencies wholly outside of the terms of the contract alleged to have been breached; whereas, in the ease before us, the data relied upon by the plaintiff are sufficiently definite to enable an approximate estimate as to each one, and from such estimate the amount of the damages could be ascertained by the very terms of the contract itself. Our conclusion is that this assignment of error is not well taken.
It does appear from the evidence that, after the plaintiff had declared a breach by the defendant, he abandoned further attempts to use the road, and in that sense abandoned the contract, and very soon thereafter sold his truck. If there was a breach of the contract by the defendant in the respect claimed by plaintiff, it was of such a nature as to prevent or greatly retard the plaintiff from carrying out his own contract. He had
The argument for appellant that, “in order to recover for the profits as damages, plaintiff must show that he was, at all times during the life of the contract, able, ready, and willing to carry out the contract,” is not applicable to a damage case. If the plaintiff were suing for specific performance, this argument would be apropos. The further argument for appellant that, after the plaintiff had disabled himself from further performance of the contract, he could claim only the value of the services rendered prior thereto, or perhaps the damages aecru-
III. The foregoing disposes of the principal questions discussed by appellant in argument. Several requested instructions were presented by the appellant in the court below. Except as to the questions which we have here discussed, the substance of such requested instructions was included in those given by the court. Some other minor errors are assigned, most of which pertain to items of evidence. We find none of them well taken. The judgment below is, accordingly, — Affirmed.