118 P. 203 | Or. | 1911
delivered the opinion of the court.
The only question involved is whether or not the lien notices were filed within the time limited. In order to create a lien, the original contractor must, within 60 days after the completion of his contract, and all other claimants must within 30 days after the completion, alteration, or repair of a structure, or after he has ceased to furnish materials therefor, file with the clerk a claim, etc., Section 7420, L. O. L. Neither of the claimants herein being an original contractor, it is insisted that the notices were not filed within 30 days after the completion of the building, or after the claimants ceased to furnish materials therefor, and such being the case an error was committed in foreclosing the alleged liens.
D. B. Fleckinger, an architect, who prepared the plans and specifications of the building and supervised its construction, testified that Ridgen did not do any work on the house after August 1, 1909, asserting that it was completed at that time, and that about two weeks thereafter Mrs. Legg accepted the building and paid the contractor the remainder due. This witness says he did not accept the house because of inferior workmanship, but. that Mrs. Legg acquiesced in the defective handiwork, contrary to his orders. That, in order to connect a boiler to be installed in the building with a range, Ridgen was required to extend a pipe through a wall, which work he never performed, saying:
*216 “The owner and the contractor had mutually agreed to cut it out entirely from the plans and specifications.”
Fleckinger, on cross-examination, in referring to the performance of labor after August 14, 1909, when the building was accepted by the owner, testified as follows :
“I employed the subcontractors to come on and finish some work that didn’t seem to be incorporated in Ridgen’s contract, and which from his standpoint he refused to do.”
He further stated upon oath that after Mrs. Legg paid for constructing the house, he had this piece of pipe put through the wall, but could not state whether it was in August or September, 1909. H. C. Ross, whose employe put in the pipe to connect the range and the boiler, in fixing the time when the work was done, testified as follows:
“To the best of my recollection, it was in October; I could not say without looking up the records.”
On cross-examination he was asked:
“Do you know what time in October you did this work?”
And he replied:
“Not without getting the records.”
Q. “Don’t know whether it was the middle or fore part of the month. It may have been after the middle of October ?”
A. “It may have been.”
Q. “Was any one living in the house when you did this work ?”
A. “My understanding is there was a tenant in both apartments. I was not at the house, but I do remember the tenants ringing up and complaining that the work was incomplete, and wanting to know if I had the contract.”
S. C. Jagger, an electrical engineer whose employee wired defendant’s building, testified that on October 7, 1909, Ridgen notified him that the wiring in the attic
“Rigden was on the job at the time.”
This witness says he remembers the day this work was done because of having received from a customer a sum of money, the payment of which was noted at that time in his daybook. No daybook was produced, however, to substantiate the fact. Mrs. Legg testified that the light on the newel post was put in long prior to the time stated,, but that the switch in the bedroom might have been put in later. Her daughter, Bessie, testified that she never saw Ridgen at the building after the settlement had been consummated on August 14, 1909.
The house was substantially completed when it was completed, and the lien claimants by vigilance could have
Reversed: Suit Dismissed: Rehearing Denied.