On November 19, 1895, the judge of the superior court of Sonoma county issued the alternative writ of the court directed to the defendants, the common council of the city of Santa Rosa, commanding them to advertise, as required by law, for bids for the lighting of the streets and public buildings and other public places of said city, and to show cause why a. peremptory writ of mandate should not issue requiring them so to act.
A demurrer to the original petition was sustained and ten days
A verified, amended petition was filed and a verified answer was filed. The cause was tried by the court, and judgment went for defendants dismissing the writ. Plaintiff appeals from the judgment and from the order denying its motion for a new trial.
It is sought to compel the defendants to advertise for sealed proposals for lighting the city and to let a contract under such advertisement. The action is brought under an act approved March 26, 1895 (Stats. 1895, p. 191), section 1. The act provides that “before any city .... shall enter into any contract for the lighting of its streets .... the city council .... shall advertise for bids for such lighting,” etc. Section 2 provides that “all contracts .... shall be let to the lowest bidder,” the city reserving the right to reject all bids. Section 3 provides how the bids are to be submitted, and that when a bid is accepted the city shall enter into a contract embodying the specifications, etc., “but no contract shall be made for a longer period than one year .... and shall go into effect within six months after the bid is approved.” Respondents contend that, while injunction might lie if the council was lighting the streets since the act of 1895, without a contract, appellant has not shown any defined legal right in itself nor a corresponding duty devolved upon the council which they have refused to perform; that there must be a specific act specifically demanded of defendants, and that no such demand is alleged or proven. The sixth finding of fact is: “That plaintiff, since the third day of July, 1894, prior to commencing the suit, requested defendants to proceed and let a contract for lighting the streets of the city of Santa Rosa, but did not demand that said council proceed in any specified manner, and did not specify what acts defendants should perform in connection with the letting of said contract. That defendants did refuse to comply with plaintiff’s said request, and have not since the third day of July made any contracts for lighting said streets.” Finding XIV is: “That the plaintiff subsequently to July 31, 1894, and after the twenty-sixth day of March, 1895, demanded of said common council and of the members thereof that they have the lighting of the streets and other public places
The act of March 26, 3895, is a part of our statute law of which defendants had notice. It was not incumbent upon plaintiff to embody in a formal demand all the provisions of the act or to specifically point out the steps demanded to be taken. It was enough, so far as the demand was concerned, to make it upon the council, as the court found was done.
Upon the proposition that the courts have no power to compel a contract to be entered into, respondents cite Splivalo v. Bryan,
The first question then is, Has the council determined that the streets of Santa Rosa shall be lighted? This can be answered only by referring to the proceedings disclosed in the record. In 1891 the council made a contract with plaintiff to light the streets by thirty or more arc electric lamps for three years from August 1st of that year. On July 3, 1894, it resolved to enter into a contract for three years from August 1, 1894, with the Merchants’ Lighting Company, to light the streets with arc electric lamps in such number as the council might determine, and the formal written contract provided for thirty-five or more. This contract not having been signed by the mayor or anyone for the city, the council made a temporary arrangement on July 31st with this company to furnish such lights as might be required. On November 17, 1894, it rescinded the action of July 3d. On May 14, 1895, a motion to shut off the street lights was defeated. The council ever since July 31, 1894, has been approving bills rendered for lighting the streets. The practical situation seems to be that there was no completed contract en-i tered into on July 3d; that the contract of July 31st was temporary, and by the terms of the offer was to continue only during the pendency of the injunction suit, and is therefore terminated, and there is now no contract, but the council refuses to advertise for bids under the act of 1895, and the law is being evaded (whether purposely or not cannot be said) by simply assuming to pay for the service under the contract of July 3d.
The council when this action was brought was and presumably is now in effect mating contracts from day to day to light the streets. The proceedings show with sufficient clearness that the council have determined that the city should be lighted by arc electric lamps, and there is no valid binding contract standing in the way of proceeding under the act of 1895 to let this service as therein provided. It would be an impeachment of
Respondent contends that the only remedy is by injunction to stop an illegal payment of the warrants, but that no relief can be given by mandamus. It was held in Eby v. School Trustees,
It is recommended that the judgment be reversed and the motion for a new trial be granted.
Belcher, C., and Searls, C., concurred.
For the reasons given in the foregoing opinion the judgment is reversed and the motion for a new trial is granted.
Garoutte, J., Van Fleet, J., Harrison, J.