delivered the opinion of the court.
The Grant Brothers Construction Company recovered judgment in the District Court of the Territory of Arizona for $9,061 for the loss of its property by fire on June 6, 1907, between Bouse and Phœnix, Arizona, while in course of transportation on the railroad operated'by the Santa Fe, Prescott & Phoenix Railway Company, the plaintiff in error. The judgment was entered upon a verdict of a jury, a motion for a new trial was denied, and the judgment was affirmed by the Supreme Court of the Territory, 13 Arizona, 186.
The Railway Company had been engaged in building, westerly from its main line, a branch railroad known as the Arizona and California Railroad. For this purpose it entered into a contract with the Construction Company for the necessary grading. The property in question consisted of the camp and grading outfit, and supplies, belonging to the Construction Company, which had been used by it in this work, and was being removed by reason of its completion. At the time in question the branch line was operated regularly only as far as Bouse and the property was loaded on cars “at the front” or end of track, about twelve miles west of that station, to be carried to Phoenix. The superintendent, foremen and about fifty workmen of the Construction Company were taken on the cars at the same place for the same destination.
The cars were hauled by the Railway Company to Bouse (where explosives and hay were unloaded), and were there attached to a regular train which brought them to a point known as the A. and C. Junction, where the Arizona and California line joined the main line of the
The A. and C. Junction is described as being in an open desert, without a station agent or inhabitants, and without water or fire apparatus. The cars were left without a watchman in charge. The reason given by the conductor for leaving them at this point was that there was no room for the cars at Wickenburg. There was no explanation of the cause of the fire, the only suggestion, as to this, being that before the fire occurred one train passed by, between four and five o’clock in the morning.
At the close of the evidence the Railway Company requested the trial court to direct a verdict in its favor. This request was refused and exception taken; and the sustaining of this ruling is assigned as error. It is contended by the Railway Company that, under its contract with the Construction Company, it was exempt from all liability and, further, that even assfiming it to be liable for negligence there was a total failure of proof in that respect.
The principal question relates to the scope and validity of the provision of the contract between the parties as to the liability of the Railway Company.
The facts are these: In November, 1904, the Railway Company issued a call for proposals for the grading of the roadbed, clearing right-of-way, making necessary canals, etc., of the Arizona & California Railroad, for a distance of about forty miles. The Construction Company made a
This contract, after providing for the performance of the described work of grading, etc., contained the following terms with respect to the transportation of supplies, camp and grading outfit and employés of the Construction Company, which were the samp as those set forth in the call for bids:
“14. Water will be delivered in cars at the end of the track at the rate of One' Dollar and Fifty Cents ($1.50) per 1000 gallons and supplies will be hauled to End of Track, both in' the usual manner of construction trains, subject to delays, etc., incident thereto. All risk of loss or damage to be borne by the Contractor.
“15. The Company will furnish a rate of one cent per ton mile from all points on the S. F. P. & P. Road and leased roads for the Contractor, on Camp and Grading Outfit and supplies, corral supplies, etc., except explosives and commissary goods, and return to original shipping points at same rates, on completion of the work. All movements of goods at less than tariff rates to be at consignee’s risk of loss and damage.
“16.'The Company will also furnish the Contractor’s employés ... a rate of one cent per passenger mile, . . . and return those who have worked until the completion of contract at the same rate. Passengers carried at less than tariff rates will be required to assume all risk of accidents to person and baggage. The plan of movement of these' employés and freight is to be according to rules of the General Freight and Passenger Agent.
“17. The Company will also secure for the Contractor similar rate's over the Santa Fe Company’s Coast Lines, on Camp and Grading Outfit, in carload lots, both to and from the work, and for workmen going to the work in lots of five (5) or more.”
It was under these conditions that, in June, 1907, the Railroad Company, — the grading having been done — took up the men, outfit and supplies of the Construction Company at the end of the track for the purpose of transporting them to Phoenix.
It is alleged in the complaint- that the transportation of the property was to be at the contract rate of one cent per ton mile and it is undisputed that this was less than the tariff rates of the Railway Company accorded to the general public.
It is the established doctrine of this court that common carriers cannot secure immunity from liability f-or their negligence by any sort of stipulation.
Railroad Company
v.
Lockwood,
Manifestly, this rule has no application when a railroad company is acting outside the performance of its duty as a common carrier. In such case, it is dealing with matters involving ordinary considerations of contractual relation; those who choose to enter into engagements with it are not at a disadvantage; and its stipulations even against liability for its own neglect are not repugnant to the requirements of its public service. The rule extends no further than the reason for it. It is apparent that there may be special engagements which are not embraced within its duty as a common carrier although their performance may incidentally involve the actual transportation of persons and things, whose carriage in other circumstances might be within its public obligation.
Baltimore & Ohio
&c.
Railway Co.
v.
Voigt,
Thus in
Baltimore &
Ohio. &c.
Railway Co.
v.
Voigt, supra,
it was held that an express messenger in charge of
In constructing, improving or repairing its road, and in building its extensions and branches, the railroad company is providing facilities for its service as a common carrier, but of course is not acting as such. It may do the work itself, if it chooses, or it may make it the subject of contract with another. In the latter case it simply employs an appropriate agency. The haulage by the railroad company of the men, appliances and supplies, required by the contractor for the purpose of the construction or improvement, to or from the point on its line where the work is to be done, is merely incidental to the work itself. The cost of such haulage is obviously an item of expense which must be taken into account in fixing the
Usually, necessity or proper convenience requires an undertaking by the railroad company, as to such transportation, which it would be under no obligation to assume in any event as a common carrier. Men and supplies- must be put down and taken up at points on the line where there is no regular station and where the railroad company would not' be bound to accept or to discharge freight or passengers. In a case, like the present one, of the grading of an extension or branch line, it is convenient that the track, laid as the roadbed is prepared for it, should be utilized for the hauling of men and materials to a point as near as possible to the work, although such track is not open to the public and the railroad company as a common carrier has assumed, as yet, no obligation for general transportation over it. This was obviously contemplated in the contract in question; and a construction of the contract, so as to make it apply only to the hauling of camp and grading outfit to stations to which the company was regularly doing business, is wholly inadmissible. The original proposals stated that the Railway Company hoped “to keep the end of the track within four miles of the nearest grading camp.” The contract itself provided that water and supplies should “be hauled to end of track, both in the usual manner of construction trains.” And, after providing for the reduced rates for outfit, supplies and employés from all points on the line of the Railway Company and for the return of the same to original shipping points at the same rates on completion of the work, the intent is shown by the pro
It is clear that in dealing with transportation of this character over its own road, in connection with construction or improvement, a railroad company is not acting in the performance of its duty as a common carrier, and the arrangement for free or reduced-rate carriage for the necessary materials and men use.d in the work, when it is a. part of the contract, entered into in good faith and not as a subterfuge, is not obnoxious to the provisions of law prohibiting departures from the published tariffs, for the reason that such an agreement lies outside the policy of these provisions. See Matter of Railroad-Telegraph Contracts, 12 I. C. C. Rep. 10, 11.
The parties then were free to make their own bargain as to this transportation and the liability which should attach to it. There is no rule of public policy which denies effect to their expressed intention, but on the contrary as the matter lies within the range of permissible agreement, the highest public policy is found in the enforcement of the contract which was actually made. Undoubtedly,, it
We entertain no doubt as to what the parties meant. The limitations upon the liability of the Railway Company were first fully stated in the call for proposals and when the bid was accepted in accordance with the terms of the call, the same limitations were inserted in the contract. Thus,, it was provided with respect to the supplies to be hauled to the end of track, “All risk of loss or damage to be borne by the Contractor;” again, as to the camp and grading outfits and supplies; “All movements of goods at less than tariff rates to be at consignee’s risk of loss and damage;” and with regard to the employes; “Passengers carried at less than, tariff rates will be required to assume all risk of accident to person and baggage.” Further, in the supplemental agreement, it was stipulated: “the Company shall assume no obligation or risk in case of accident or damage to men and supplies.” When we consider the circumstances of the parties and the objects of the contract, we cannot escape the conclusion that these reiterated statements evidence the intention to deal comprehensively with
all
the risks incident to the transportation, not excluding the obvious risk of loss by reason of some neglect in the
It will be observed that the limitation from liability was to apply to the workmen as well as to the goods. We do not need to inquire as to the effect of such an exemption in the case of a workman who had not assented to it. But the provisions as-to the workmen throw light upon the intent of the parties with respect to the property. In the supplemental contract both men and supplies were grouped in one stipulation for immunity. The Railway Company, however, would not have been liable in any event for injuries to the workmen save in case of negligence; and in bargaining for a limitation of liability .as to the workmen, they evidently had negligence in view. The .word “accident” in this connection was manifestly used in its popular sense and not as limited to occurrences beyond the
This point was recognized by the court in
Railroad Company
v.
Lockwood,
The question as to the fair interpretation of language such as is used in the present case, where the railroad company is acting outside the performance of its duty as a common carrier was considered by the Circuit Court of Appeals in the Second Circuit in
Long
v.
Lehigh Valley
We see no ground whatever for the conclusion that it was not the intention of the parties to give the Railroad Company immunity from negligence in the case of the workmen, and in view of the provisions and purpose of the contract it cannot be held that they had a different intention with respect to the camp and grading outfit and supplies. When they agreed that all movement of this property at less than tariff rates should be at the risk of the Construction Company and later in the supplemental contract that the Railway Company should
It is therefore unnecessary to discuss the assignments of error which are based upon the ruling of the court with respect to the submission to the jury of the question of negligence. Our conclusion is that, upon the facts disclosed at the trial, the Railway Company was entitled to a direction of a verdict in its favor, and the judgment sustaining the recovery by the Construction Company must therefore be reversed.
The judgment is reversed and the case remanded to the Supreme Court of the State of Arizona as the successor of the Territorial Supreme Court, for such further proceedings as may not be iúconsistent with this opinion.
