SCWW owned a wastewater treatment facility in Santa Paula. GCES, a subsidiary company owned by SCWW, operated a trucking unit that transported wastewater. SCWW and GCES applied for insurance coverage with Allied. In their insurance application and related correspondence, SCWW and GCES represented that they did not accept, process, transport, or discharge hazardous waste.
Allied issued a $2 million "Primary Environmental Liability Policy" and a $5 million umbrella policy. The policy covered " 'environmental damage' " or " 'emergency response expenses' " arising out of a " 'pollution incident.' " The policy also contained an "intentional noncompliance" provision, which excluded coverage for damages resulting from the "intentional disregard of or deliberate willful or dishonest noncompliance" with law or regulations.
After obtaining coverage, a GCES vacuum truck exploded at the SCWW facility when a truck driver mixed wastewater with a chemical (sodium chlorite). Chemical spillage from the explosion spontaneously combusted and caused a fire. SCWW submitted a claim to Allied to cover the cleanup costs. Allied did not pay the claim.
The parties entered mediation and reached a partial settlement including a "Payment Term Sheet." The Payment Term Sheet provided that Allied would pay $2.5 million to SCWW, but if Allied obtained a judgment that it was not obligated to pay SCWW's damages under its policy, then SCWW would reimburse Allied. Allied paid the $2.5 million.
SCWW sued Allied for failing to pay damages up to the policy limit. Allied filed a first amended cross-complaint against SCWW and GCES for declaratory relief, reimbursement of defense costs and expenses, unjust enrichment, fraud, rescission, and unlawful business practices.
Allied filed applications for a right to attach order and writ of attachment against both SCWW and GCES for $2.5 million plus costs and interest based on an express contract (the Payment Term Sheet) and implied contract theories of unjust enrichment and rescission.
The trial court granted the applications, finding that Allied "established the probable validity of its implied contract and rescission claims." Specifically, it found the evidence supported the "applicability of the 'intentional noncompliance' policy exclusion, and the existence of hazardous waste discharge prior to the policy application." The court issued writs of attachment against both SCWW and GCES.
DISCUSSION
Prejudgment Attachment
SCWW and GCES contend the trial court erred in granting the applications for prejudgment attachment because Allied did not establish the probable validity of its claims. We disagree.
A party seeking a prejudgment attachment must demonstrate the probable validity of its claim. ( § 484.090, subd. (a).) Probable validity means that "more likely than not" the plaintiff will obtain a judgment on that claim. (§ 481.190.) An order granting an application for a prejudgment attachment is directly appealable. (§ 904.1, subd. (a)(5).) A trial court's finding on whether a plaintiff established probable validity is reviewed for substantial evidence. ( Lorber Industries v. Turbulence, Inc. (1985)
Unjust Enrichment
Allied established the probable validity of its unjust enrichment claim. Where an insurer pays an amount not covered under its policy, it has a right of reimbursement that is implied-in-law under an unjust enrichment theory. ( Buss v. Superior Court (1997)
Allied had a right of reimbursement because the intentional noncompliance policy exclusion applied. Under this exclusion, if the damages (i.e., cleanup costs) resulted from SCWW and GCES's intentional noncompliance with law and regulations, then Allied was not obligated to pay damages.
Moreover, SCWW and GCES failed to comply with law when they concealed chemicals from inspectors. Employees testified that they consolidated and cleaned chemical totes before inspections to hide the presence of unreported chemicals at the facility. Employees removed labels from chemical totes that identified their contents or indicated they were hazardous materials. SCWW's environmental compliance manager admitted that he ordered employees to move unreported chemicals to a trucking yard before an inspection in order to hide them from the inspectors. The storage of these chemicals at the trucking yard violated SCWW's lease with the City of Santa Paula.
The cleanup costs resulted from SCWW and GCES's intentional noncompliance
Because the evidence supports the trial court's finding that the intentional noncompliance exclusion applies, the trial court properly found that Allied established the probable validity of prevailing on its unjust enrichment claim.
Rescission
Although the unjust enrichment claim alone is sufficient to support an order for prejudgment attachments, Allied also established the probable validity of its rescission claim. Misrepresentation or concealment of a material fact in connection with an insurance application is grounds for rescission of the policy. ( Ins. Code, § 359 ; Superior Dispatch, Inc. v. Insurance Corp. of New York (2010)
Substantial evidence supports the finding that SCWW and GCES misrepresented and concealed this material fact. The evidence showed that SCWW and GCES accepted, processed, and transported wastewater regardless of whether it tested positive as hazardous. For instance, before Allied's policy was in effect, SCWW ordered a wastewater sample to be retested after it tested positive for "corrosivity." The proper action was to identify the wastewater as hazardous and reject it, but SCWW ordered the sample to be retested. In another instance, when SCWW retained a lab to produce reports to send to regulatory agencies, it ordered the lab not to send any reports of wastewater samples with a pH level above 12.5 (which indicated hazardousness). Other evidence shows that SCWW accepted and transported wastewater knowing that it exceeded a pH of 12.5.
Additionally, the evidence shows that SCWW discharged wastewater that it knew was hazardous. SCWW's environmental compliance manager admitted that he altered lab results of wastewater that was discharged into pipelines connected to the Oxnard water treatment facility to reflect levels of pollutants below the pollutant discharge limit.
The evidence shows that SCWW and GCES's misrepresentations both preceded and followed the effective date of coverage.
SCWW and GCES claim the trial court erred in its ruling on the rescission claim because Allied did not assert a separate claim of rescission in its applications for an attachment. But Allied expressly stated that it based its applications for prejudgment attachment "under two implied contract theories: unjust enrichment and rescission."
We also reject SCWW and GCES's claim that the trial court erred in finding they discharged hazardous waste because there was insufficient evidence that wastewater was in fact hazardous. This claim is forfeited because it was not raised in the trial court. ( Tudor Ranches , supra ,
No Express Contract or Condition Precedent
SCWW argues that Allied cannot prevail on implied contract theories because the same subject matter is addressed in an express contract (i.e., the Payment Term Sheet). ( Wal-Noon Corp. v. Hill (1975)
The trial court did not err in granting the applications for prejudgment attachment based on implied contract theories even if an express contract covers the same subject. First, SCWW and GCES cannot assert the existence of an express contract when they successfully argued for the exclusion of that contract from evidence. Under the invited error doctrine, a party cannot challenge a court's finding made at its insistence. ( Jentick v. Pacific Gas & Electric Co. (1941)
SCWW and GCES also claim that the order granting the applications for prejudgment attachment was improper because a judgment of noncoverage was a condition precedent. This claim lacks merit. The purpose of a writ of attachment is to ensure payment will be recovered if judgment is entered. Allied is only required to establish the "probable validity" of its claims. Whether Allied's claims are "actually valid" is determined in a subsequent proceeding and not affected by the court's order on the applications for prejudgment attachment. (§ 484.050, subd. (b).) An attachment remedy would be useless if it required the court to first decide the merits and issue a judgment.
SCWW and GCES's reliance on Robinson v. Varela (1977)
Prejudgment Interest
SCWW and GCES contend that prejudgment interest should be calculated from the date of the judgment awarding reimbursement, and not from the date Allied paid $2.5 million. This claim is forfeited, because no objection to prejudgment interest was made below. ( Tudor Ranches , supra ,
DISPOSITION
The order is affirmed. Allied shall recover its costs on appeal.
We concur:
GILBERT, P.J.
YEGAN, J.
Notes
Further unspecified statutory references are to the Code of Civil Procedure.
Although GCES is not a party to the Payment Term Sheet, GCES raises the issue of its nonsignatory status for the first time in its reply brief on appeal. Failure to raise a timely objection forfeits the argument. (Tudor Ranches, Inc. v. State Comp. Ins. Fund (1998)
