37 N.J.L. 1 | N.J. | 1874
The opinion of the court was delivered by
From the statement of the facts now before us, it appears that, at the time the contract in question was made, a plan of the bridge, mentioned in it, was exhibited and referred to by the parties. The principal item in dispute, is for certain work which it was alleged was done in consequence of alterations made in this plan, and the question of law raised before us is, whether the proof of this plan, and of its'subsequent alteration, was legitimate. The ground of objection to it was, that the written contract did not refer to any plan of a bridge, and was intelligible and complete in itself. The rule invoked, is that which forbids the introduc
The doctrine is of admitted force and importance, but it does not apply to the facts of the present case. The evidence objected to has no tendency to impair the force or alter any of the terms of the written agreement. Its office is merely to apply that agreement to its subject matter. The plaintiffs obligated themselves to do the work on a draw bridge — but such bridge was not described, either in a general or particular manner, in the instrument. It is certainly no part of the express stipulation that the plaintiffs will do the work on any kind of a bridge which the defendant may choose to put up; and the introduction of such an obligation, by intendment, would be most forced and unreasonable. If A should agree to build for B at a certain price, a house, it would hardly be intended that it was the understanding that the promisee could require the construction of a building according to his fancy. In this class of cases contracts are, upon their face, incomplete, and do not become perfectly intelligible until, through the medium of parol evidence, they are connected with the subject to which they relate. In the present instance the writing does not mark out the kind of bridge to be built; it cannot rationally mean any structure at the will of the defendant; and the consequence is, the evidence, to which objection is made, cannot be said either to impair or modify its stipulations. To make this testimony objectionable, it would be necessary to say that this contract bound the plaintiffs to do all the work on a bridge such as the defendant, in its discretion, might determine to have put up. It is not likely that such a contract ever has been or ever will be made; it is clear the terms of the present instrument will not bear such an interpretation. The bridge to which the work appertained not being defined in writing, it became entirely legal to define it by the parol proof. Such evidence is generally necessary to show what it is the parties are contracting about. For such purpose, testimony of this kind has been often admitted. In Macdonald v. Longbottom,
With respect to the matters of fact discussed, it appears to me that the referee, from the proofs before him, had the right to draw the inferences and make the findings contained in his report. The action of the referee is to have the weight of a verdict, and attributing to it such weight, it is clear there is no ground on which it can be disturbed.
The rule should be discharged, with costs.