Opinion
Introduction
Plaintiffs David and Diane Sanchez appeal from a summary judgment granted in favor of defendants Swinerton & Walberg Company and Coan Construction Company, Inc. We affirm.
*1464 Statement of Facts
Defendant Swinerton & Walberg Company was the general contractor for construction of the Los Angeles Times Olympic Production Facility. Defendant Coan Construction Company, Inc. (Coan) was the concrete subcontractor. As subcontractor, Coan poured walkways, an entrance ramp, a stairway and a landing at the entrance of the facility. These structures were open to the air. It is undisputed that defendant Swinerton generally complied with the project’s plans and specifications. 1 There is no evidence as to whether defendant Coan complied with the plans and specifications for the concrete structures. Upon completion of the project, the facility was accepted by the owner.
On February 10, 1992, roughly two years after the facility was completed, plaintiff David Sanchez went to the Olympic Production Facility. It had been raining recently. Plaintiff walked up the stairs, across the landing and through the entrance into the transportation office. After taking three or four steps inside the building, he slipped and fell. The fall resulted in serious injury.
For some time prior to plaintiff David Sanchez’s accident, employees and agents of the owner had noticed that, whenever it rained, water accumulated on the landing, which sloped toward the building entrance. The water formed ponds with depths of one-half inch. The water also tended to run toward the entrance. In an effort to divert the water, sandbags were placed along the landing. Nonetheless, water sometimes migrated into the entryway. None of the owner’s employees or agents informed either defendant of this problem until after plaintiff David Sanchez was injured.
Contention
Plaintiffs contend the trial court erred in granting summary judgment, in that there is a triable issue of material fact as to defendants’ liability for plaintiffs’ injuries. For the reasons set forth below, we disagree.
Discussion
Summary judgment properly is granted if there is no question of fact and the issues raised by the pleadings may be decided as a matter of law.
*1465
(Code Civ. Proc., § 437c, subd. (c);
Mars
v.
Wedbush Morgan Securities, Inc.
(1991)
To secure summary judgment, a moving defendant may prove an affirmative defense, disprove at least one essential element of the plaintiff’s cause of action
(Albert
v.
Southern Pacific Transportation Co.
(1994)
The moving defendant bears the burden of proving the absence of any triable issue of material fact, even though the burden of proof as to a particular issue may be on the plaintiff at trial.
(Los Angeles County-U.S.C. Medical Center
v.
Superior Court
(1984)
The court must consider presumptions and draw inferences from the facts adduced where the inference is the only reasonable one which may be drawn. (See
Unjian
v.
Berman
(1989)
In determining the propriety of a summary judgment, the reviewing court is limited to facts shown by the evidentiary materials submitted, as well as those admitted and uncontested in the pleadings.
(Sacks
v.
FSR Brokerage, Inc.
(1992)
Formerly, as a general rule, after a contractor had completed a building and the owner had accepted it, the contractor was not liable to third persons for injury caused by the condition of the work done even though negligent in performing the contract. The rule first appeared in
Boswell
v.
Laird
(1857)
An exception to the general rule, as applied to contractors who construct structures, first was enunciated in
Johnston
v.
Long
(1943)
In
Stultz,
the Supreme Court applied to manufacturers the rule enunciated in
MacPherson
v.
Buick Motor Co.
(1916)
Hale
v.
Depaoli
(1948)
In
Schifano
v.
Security Building Co.
(1955)
The next important statement of the pertinent principles appears in
Hogan
v.
Miller
(1957)
In
Hogan,
the plaintiff was injured while opening a window in the building where she was employed.
(Hogan, supra,
In
Dow
v.
Holly Manufacturing Co.
(1958)
That the defect is latent goes to the dangerousness of the condition, for, without knowledge of the defect, one cannot guard against it. As the court noted in Dow, “[g]as heaters have the inherent capacity for great harm unless they are properly made and installed, especially since their defects are usually concealed from the occupant of the building and the deadly gas . . . gives no warning of its presence.” (Dow v. Holly Manufacturing Co., supra, 49 Cal.2d at pp. 727-728.)
In
Stewart
v.
Cox
(1961)
While the court presents
Stewart
as a third party liability case, that characterization is possible only because the negligent subcontractor was not in privity of contract with the owner. The court had destroyed the privity barrier in
Dow
v.
Holly Manufacturing Co., supra,
*1470
Chance
v.
Lawry's, Inc.
(1962)
None of the post-owner-acceptance third party liability cases cited above have been overruled or disapproved. Indeed,
Hale
and
Hogan
were cited recently in
De Lima
v.
Magnesite Waterproofing & Refinishing
(1987)
The asserted defect in this case, as revealed by plaintiffs’ own answers to interrogatories, is that the defendants “constructed and poured concrete and performed labor on [the landing at the top of the entrance stairway] not confirming [sz'c] to the plans and specifications prepared by the architect for said landing. This negligence resulted in water ponding and accumulating on the landing, which water was a cause of Plaintiff David Sanchez’s slip and fall accident. Furthermore, the defective construction of the landing resulted in water draining from the landing into the transportation office floor on which Mr. Sanchez fell, which was another cause of Mr. Sanchez’s slip and fall accident.” In other words, defective construction of the landing allowed water to pool on the landing and to drain into the transportation office, thus creating a dangerous condition. Plaintiffs do not allege, and there is no evidence, that the defective construction of the landing created any danger when water was not present.
The uncontradicted evidence shows that water formed ponds on the landing. These ponds had a depth of one-half inch. In these circumstances, the presence of standing water and the manner in which it drained into or toward the transportation office would have been obvious and apparent to any reasonably observant person, as would the danger that the water might create slippery surfaces and cause one to slip and fall. In the context of a patent defect, the word “patent” “ ‘refers to the patency of danger and not merely to exterior visibility.’ ”
(Halliday
v.
Greene, supra,
In fact, it is undisputed that the dangerous condition was observed by the owner’s agents, and the risk it entailed was appreciated, on several occasions preceding plaintiff David Sanchez’s accident. Even if the defect initially could have been considered latent, once it was discovered, it became patent. (Cf.
A & B Painting & Drywall, Inc.
v.
Superior Court
(1994)
Inasmuch as the defective condition that was reasonably dangerous to life and limb was not latent, the contractor and subcontractor had no liability to a third person injured thereby after the owner’s acceptance of the structure.
(Hale
v.
Depaoli, supra,
33 Cal.2d at pp. 230-231;
Hogan, supra,
Even if one assesses duty by applying the balancing factors articulated in
Biakanja
v.
Irving, supra,
The judgment is affirmed.
Ortega, J., and Vogel (Miriam A.), J., concurred.
Notes
It was not clear that this evidence pertained only to general compliance, as opposed to specific and detailed compliance, until plaintiffs presented their evidence in opposition to the summary judgment motion. Evidence that defendants complied with the plans and specifications made a prima facie case that they were not negligent, thus shifting the burden of proof to plaintiffs.
(Hunter
v.
Pacific Mechanical Corp.
(1995)
Plaintiffs assert prejudice from the trial court's purported consideration of a letter to which it had sustained objections. The letter in question was written by the owner to the contractor after plaintiff’s injury to apprise the contractor of the defect. It thus provided no evidence of anyone’s knowledge before the injury, and properly was excluded as irrelevant. When one reads the trial court’s minute order granting summary judgment and considers context, it is clear the court did not use the contents of the letter in reaching its decision, but merely noted that, had the letter been considered, it would not have been evidence of the contractor’s actual prior knowledge of the defect.
