80 P. 1076 | Cal. | 1905
This is an action to foreclose the lien of an assessment for street-improvement work. Plaintiff had judgment, and defendants appeal from an order denying their motion for a new trial.
1. It is contended by defendants that the resolution of intention to order the work done was invalid for several reasons. Assuming that all the objections made to the resolution are available to defendants on the record before us, we are of the opinion that there is no merit in any of them.
The property upon which it is sought to enforce a lien fronts on Twenty-ninth Street between Noe and Sanchez streets, in San Francisco. It is claimed that the evidence introduced by defendants shows that at the date of the resolution this portion of Twenty-ninth Street had once been macadamized, and was then in good order. It also appeared that within six months prior to such date the said block, excepting only the lot of defendants, which has a frontage of fifty-five feet, had been paved with bituminous rock, and that granite curbs had been laid thereon by the property-owners under private contract.
There is no claim that such block had ever been accepted by the city as a completed and fully constructed street. (See Street Improvement Act, sec. 20.)
Under these circumstances, the board of supervisors passed the resolution of intention. It included street work of various kinds upon other streets than Twenty-ninth Street, but so far as applicable to Twenty-ninth Street, it expressed the intention *637 of the board as follows, viz.: "That granite curbs be laid on Twenty-ninth Street, between Sanchez and Noe streets where not already laid, and that the roadway thereof be paved with bituminous rock where not already paved, except that portion required by law to be kept in order by the railroad company having tracks thereon."
It is urged that the board had no power to order a street that had once been macadamized to be paved with bituminous rock.
We find no such limitation upon the power of the city council expressed in the law relative to street improvements. By section 2 of the act, as it existed at the date of these improvements, it was provided that "Whenever the public interest or convenience may require, the city council is hereby authorized and empowered to order the whole, or any portion, either in length or width, of the streets . . . of such city, graded or regraded to the official grade, planked or replanked, paved or repaved, macadamized or remacadamized, graveled or regraveled, . . . and to order any other work to be done which shall be necessary to complete the whole or any portion of such streets . . . and it may order any of said work to be improved." (Stats. 1891, p. 196.)
It may be that after a street has been fully constructed and accepted by the city council as a completed street, as provided in section 20 of the act (Stats. 1885, p. 160), the council has no power to further improve the same at the expense of the property-owners, but that question is not here involved and is not decided. Until such acceptance it is clear that the council has full power to determine whether work of any class designated in section 2 of the act is required upon any street, or portion of a street, by the public interest or convenience, and to order the same done in the manner provided by the act. The mere fact that work of some other class than that ordered has already been done on the street cannot affect this power. Although once macadamized, the public interest or convenience may require that a street be paved with bituminous rock. The determination by the board of supervisors that the public interest or convenience does so require is conclusive, at least in the absence of fraud.
Under the provisions of the statute (sec. 7, subds. 10, 11, Stats. 1891, p. 204), the board properly excepted from the *638
order work of the same class already done at the expense of the owner. The fact that such work had already been done upon a greater part of the line of the contemplated improvement, as designated in the resolution of intention, and that the resolution, therefore, in effect, affected only a minority of the frontage, is immaterial. In McDonald v. Conniff,
The exception of "that portion required by law to be kept in order by the railroad company having tracks thereon," did not render the resolution void. The requirement of the law as to street-railroad corporations in this regard is to be found in section 498 of the Civil Code, and is as follows, viz.: "To plank, pave, or macadamize the entire length of the street used by their track, between the rails, and for two feet on each side thereof, and between the tracks, if there be more than one, and to keep the same constantly in repair, flush with the street, and with good crossings." The exception, therefore, sufficiently described the portion of the street which was excepted from the effect of the resolution for that reason; as definitely, as did the exceptions "where not already laid" and "where not already so paved" describe the portions excepted because of work already done. (Dowling v. Hibernia etc. Soc.,
We think that there can be no doubt, under the provisions of our law, that the supervisors had the right to except such *639 portion of the street as was required by law to be kept in order by the railroad company at its own expense, and, so far as we know, was so being kept in order.
The fact that the resolution of intention included work of various kinds upon other streets, does not render it invalid.(Bates v. Twist,
2. It is contended that the certificate of the engineer is void, because it does not conform to the requirements of section 34 of the Street Act (Stats, 1891, p. 206). We find nothing in the law requiring a certificate of the city engineer under the circumstances of this case. (See O'Dea v. Mitchell,
3. It is contended that the bid for the work and contract were void for certain specified reasons, but these objections are not available to defendants. The making of a valid bid and the execution of a valid contract were alleged by plaintiff, and the court found that these allegations were true. The bill of exceptions contains no specification of insufficiency of evidence to sustain the findings in these respects. We have, however, considered the objections on their merits, and find nothing in them.
It is further urged that the return of the warrant was not signed by the superintendent of streets. It was signed, in behalf of the contractor, by the person who had made the demand, and was verified by his oath. This appears to have been a compliance with the law in that regard. (Street Act, sec. 10.)
4. The return very clearly shows that demand for payment was publicly made upon the premises assessed in full accord with the requirements of section 10 of the Street Act.
This disposes of all points made by defendants. There was nothing in the evidence offered by them to overcome the prima *640 facie case made by plaintiff by the introduction in evidence of the assessment, diagram, warrant, return, and engineer's certificate.
The order denying a new trial is affirmed.
Shaw, J., and Van Dyke, J., concurred.