San Francisco Distribution Center, LLC (“San Francisco Distribution”) appeals final summary judgment entered in favor of Stonemason Partners, LP (“Stonemason”) on its claim for breach of contract. For the reasons that follow, we affirm.
In January 2012, San Francisco Distribution entered into a contract with Stonemason' to buy a commercial property in Miami Beach for $5,250,000.00. The effective date of the contract was January 16, 2012, and San Francisco Distribution was required to close within forty-five days of the effective date. Under the terms of the contract, San Francisco Distribution, was required to pay a total deposit amount of $400,000, to be held in escrow by Wells Fargo. The contract provided that in the event of a default by San Francisco Distribution:
Seller (Stonemason) may either (1) retain all deposit(s) paid or agreed to be paid by Buyer as agreed upon liquidated damages, as consideration for the execution of this Contract, and in full settlement of any claims, upon which this Contract will terminate or (2) seek specific performance. If Seller retains the deposit, Seller will pay the Listing and Cooperating Brokers named in Paragraph • 12 fifty percent of all forfeited deposits retained by Seller (to be split equally among the Brokers) up to the full amount of the brokerage fee.
San Francisco Distribution’s broker was Thomas Martino, who also served as the closing agent. When San Francisco Distribution failed to close, Stonemason demanded the $400,000 deposit amount as liquidated damages per the contract, but was told by Martino that the deposit had been returned to San Francisco Distribution.
In its amended answer to the complaint, San Francisco Distribution admitted that the contract did not close but asserted, in its affirmative defenses, that Stonemason was not entitled to the $400,000 deposit because it had subsequently sold the property to another buyer for $200,000 more than the San Francisco Distribution contract price, and that therefore, Stonema
Stonemason moved for summary judgment against San Francisco Distribution on the breach of contract claim. After a hearing, the trial court granted Stonemason’s motion for summary judgment and entered final judgment against San Francisco Distribution in the amount of $400,000 plus interest, attorney’s fees and costs.
San Francisco Distribution does not dispute that it failed to close the transaction as required by the contract. Neither does it dispute the existence of the liquidated damages clause and its failure to make the required deposit in a total amount of $400,000. Instead, Stonemason argues that summary judgment was improperly granted because the liquidated damages clause:
1. Is unenforceable because the contract provided Stonemason with alternative remedies of liquidated damages or specific performance; and
2. Is unconscionable in light of the fact that Stonemason subsequently sold the property for an amount that exceeded the original purchase price.
Alternative Remedies of Liquidated Damages or Specific Performance Renders Provision Unenforceable
San Francisco Distribution’s first argument — that the liquidated damages clause is unenforceable because it gave Stonemason the option between liquidated damages and specific performance — appears to be based on the Florida Supreme Court case of Lefemine v. Baron,
In Hyman v. Cohen,
The Supreme Court established a test to determine when a liquidated damages provision will be found enforceable, and when it should be found unenforceable as a penalty clause. First, in order to uphold the provision, “the damages consequent upon a breach must not be readily
In Pappas v. Deringer,
San Francisco Distribution argues by analogy that Lefemine should apply to the clause at issue because claims for specific performance ultimately result in a suit for damages. We do not agree with this contention. A -suit, for specific performance seeks equitable relief that requires the breaching party to perform its obligations under the agreement, and is not, as San Francisco Distribution suggests, to be considered the simple equivalent of a claim for damages and therefore governed by Lefemine and Cortes. The argument advanced by San Francisco Distribution has been rejected by our sister court. See Mineo v. Lakeside Village of Davie, LLC,
Lefemine also requires that “the sum stipulated to be forfeited must not be so grossly disproportionate to any damages that might reasonably be expected to follow from a breach .... ” Lefemine,
Liquidated Damages Clause Unconscionable Because Stonemason Sold the Property for a Higher Pnce and Therefore Suffered No Damages
San Francisco Distribution also contends that the amount of liquidated damages is unconscionable, in light of the fact that Stonemason ultimately sold the property to a subsequent buyer for more than the original contract price, and therefore suffered no damages. We affirm on this issue as well.
San Francisco Distribution’s no-damages argument rests on the premise that a subsequent buyer paid $5.45 million, $200,000 more than the original contract price. While perhaps superficially appealing, such an argument looks solely at the ultimate sales price, ignoring the contractual provision itself and other aspects of potential damages consequent to a buyer’s breach. Such a determination would invite speculation in assessing what 'a 'certain piece of real property might ‘be worth weeks, months or even years after a contract is signed. See Hutchison v. Tompkins,
In Hot Developers, Inc. v. Willow Lake Estates, Inc.,
We hold that the liquidated damages clause at issue in this case is not a “penalty clause” but rather, an enforceable liquidated damages clause which gave the seller an option, upon buyer’s breach, between enforcing the contract by specific performance or by forfeiture of the deposit as liquidated damages. We further hold that neither the amount of the deposit, as a percentage of the purchase price, nor the sale to a subsequent buyer in an amount that exceeded the original contract price, rendered the clause unenforceable.
Affirmed.
Notes
. It appears that San Francisco Distribution had actually paid only $100,000 of the contractually-required $400,000 deposit.
. The complaint alleged several counts against Martino, but those are not relevant here as Martino is not a party to this appeal. The case against Martino remains pending below.
. The contract with the new buyer was not executed until May 30, 2012, after the lawsuit had already been filed. The sale closed on August 8, 2012 for a purchase price of $5,450,000.00.
. The case against Martino is still pending below.
. The determination to be made is whether damages were readily ascertainable at the time of the contract, not whether damages were readily ascertainable at the time of the breach. See Valenti v. Coral Reef Shopping Ctr.,
. San Francisco Distribution continued' to assert on appeal that the damages were readily ascertainable at the time of the breach, ignoring the fact that, as held in Hutchison and Valenti, the relevant timeframe for this determination is the time of the contract. , See also, Bradley v. Sanchez,
. San Francisco Distribution’s argument' also overlooks the seller’s carrying costs during this timeframe, and the fact tiiat, under the terms of the contract at issue, 50 percent of the forfeited deposit was to be distributed in equal amounts to the brokers involved in the transaction.
. Talcing San Francisco Distribution's argument to its logical conclusion, in order for Stonemason to "keep” the security deposit without it being characterized as a "windfall,” the subsequent sales price would actually have to be no more than $4,850,000 (i.e., the original sales price of $5,250,000 less the $400,000 deposit "kept” by Stonemason). Presumably, San Francisco Distribution would have made the same argument pressed here, even if the eventual sales price had been $5,150,000, an amount $100,000 less than the original contract price.
