San Antonio Masonry & Tool Supply, Inc. v. Epstein & Sons International, Inc.San Antonio Masonry & Tool Supply, Inc. v. Epstein & Sons International, Inc.
OPINION
Opinion by
San Antonio Masonry & Tool Supply, Inc. (“Masonry”) appeals from a take nothing judgment rendered against it in its suit for foreclosure of a mechanic’s lien, recovery on a bond, and quantum meruit. Masonry contends that the trial court erred in granting summary judgment for Epstein & Sons International, Inc. (“Epstein”) and Fidelity & Deposit Company of Maryland (“Fidelity”) because: (1) its suit to foreclose a mechanic’s lien and recover on the bond was not time barred under the Texas Property Code; and (2) factual issues preclude summary judgment on its quantum meruit claim.
Factual and PROCEDURAL Background
Masonry is a supplier of masonry material, tools, and equipment for the construction industry. Epstein is a corporation that engages in commercial construction projects throughout the United States. In this instance, Epstein served as the general contractor for HEB Grocery Company in the construction of a dispatch office building and trailer return center in San Antonio, Texas. In connection with that construction project, Epstein entered into a subcontract with San Antonio New Age, Inc. (“New Age”). In the course of performing under the subcontract, New Age purchased supplies from Masonry under an open account agreement. When New Age failed to fully pay for the purchased items, Masonry filed and recorded a mechanic’s lien on January 17, 2001 in the amount of $9,820.58. 1 In response, Epstein filed a bond as indemnity against Masonry’s mechanic’s lien on July 24, 2001. Fidelity served as the surety on the bond. Masonry subsequently filed suit against New Age and its president, J.B. Gonzalez, asserting a claim based on a sworn account and breach of contract. In the same petition, Masonry sued Epstein based on quantum meruit. On April 14, 2003, Masonry amended its petition adding for the first time causes of action against Epstein and Fidelity for foreclosure of its mechanic’s lien and recovery on the bond.
While the lawsuit was pending, Epstein and Fidelity filed a traditional summary judgment motion and motion for severance asserting that Masonry’s suit to foreclose the mechanic’s lien and recover on the bond was barred by limitations. Epstein also moved for summary judgment on the quantum meruit claim. The trial court granted summary judgment, without specifying the basis, and rendered a take nothing judgment in favor of Epstein and Fidelity. 2 Masonry timely filed this appeal.
Standard of Review
We review a summary judgment
de novo. Natividad v. Alexsis, Inc., 875
S.W.2d 695, 699 (Tex.1994);
Valores Corporativos, S.A. de C.V. v. McLane Co.,
945
Limitations
Masonry first contends that the trial court erred in granting summary judgment because its lawsuit to foreclose the mechanic’s lien and recover on the indemnity bond was not time-barred under the plain language of the Texas Property Code. We agree.
As a general rule, when a supplier like Masonry is not paid for labor or materials consumed in construction of improvements on real property, it may place a mechanic’s lien against the property pursuant to the Texas Property Code. Tex. Prop.Code Ann. § 53.021 (Vernon Supp.2004-05). Suit must then be filed to foreclose the lien within the time period set forth by statute. Tex. Prop.Code Ann. §§ 53.157, .158 (Vernon Supp.2004-05). Specifically, in order to foreclose a statutory mechanic’s lien, a lawsuit must be filed within two years after the last day a claimant may file the lien affidavit as provided by statute, or within one year after completion, termination, or abandonment of the work under the original contract under which the lien is claimed, whichever is later. Tex. PROP. Code Ann. § 53.158(a) (Vernon Supp.2004-05). Here, the parties do not dispute the adequacy and timing of the notices and lien affidavits presented by Masonry with respect to its mechanic’s lien, and they do not dispute that the deadline for Masonry to file its lien affidavit was April 15, 2001. 3 Therefore, under section 53.158(a), Masonry had two years from April 15, 2001 to file suit. The record confirms Masonry filed suit to foreclose the lien in its amended petition on April 14, 2003. Accordingly, Masonry’s suit to foreclose the lien was timely filed.
Masonry also claims that the trial court erred in granting summary judgment because its lawsuit to recover on the indemnity bond was not time-barred. The applicable statutory provision reads, “A party making or holding a lien claim may not sue on the bond later than one year after the date on which the notice is served or after the date on which the underlying lien claim becomes unenforceable under Section 53.158.” Tex. Prop.Code Ann. § 53.175(a) (Vernon Supp.2004-05). Epstein and Fidelity argue that the first part of the statute controls, citing the case of
Stolz v. Honeycutt, See Stolz v. Honeycutt,
Epstein and Fidelity fail to recognize that section 53.175(a) is worded in the disjunctive; the use of the word “or” plainly contemplates two alternative time periods in which to initiate a suit to recover on the bond.
See Texas A & M Univ. at Corpus Christi v. Hamann,
In this case, Masonry’s suit to foreclose its mechanic’s lien and recover on the bond was filed on April 14, 2003, which is before the date on which the underlying lien claim became unenforceable under section 53.158(a) of the Texas Property Code. Accordingly, Masonry timely filed its action on the bond under the second alternative limitations provision set forth in the statute. Tex. Prop.Code Ann. § 53.175(a). Summary judgment cannot be sustained on limitations grounds.
Quantum Meruit
Finally, Masonry argues that disputed fact issues preclude summary judgment on its quantum meruit claim against Epstein. Epstein responds that summary judgment was properly granted because it established, as a matter of law, that an express contract exists covering the masonry materials in dispute. Therefore, Masonry may not recover on a quantum meruit theory for the value of those materials. We agree.
Quantum meruit is an action independent of any contract, based on an implied agreement to pay for benefits rendered and knowingly accepted.
Vortt Exploration Co. v. Chevron USA, Inc.,
Here, Epstein and Fidelity provided the trial court with evidence that an open account agreement existed between Masonry and New Age through the affidavit and sworn statement of account of Robbin Bostick, Vice President of Masonry. Copies of six invoices covering the masonry supplies at issue were also submitted as summary judgment evidence. Those invoices showed that the masonry supplies were sold to New Age, shipped to the attention of New Age at the project location, and were to be paid for by New Age. Finally, Epstein and Fidelity submitted
Masonry argues, without citing us to any authority, that while these documents may constitute “some evidence” of a contract between New Age and Masonry, they do not constitute “conclusive evidence” of an express contract sufficient to defeat Masonry’s quantum meruit claim against Epstein. We disagree. Although pleadings generally do not constitute summary judgment proof, if a plaintiffs pleadings contain judicial admissions negating a cause of action, summary judgment may properly be granted on the basis of the pleadings.
See Brooks v. Ctr. for Healthcare Serv.,
Conclusion
We affirm the trial court’s summary judgment in favor of Epstein on Masonry’s quantum meruit suit because we conclude that an express contract covered the masonry materials for which Masonry sought recovery. However, because we also conclude that Masonry’s suit to foreclose its mechanic’s lien and recover on the indemnity bond is not barred by limitations, we reverse the trial court’s summary judgment in favor of Epstein and Fidelity on those claims, and remand to the trial court for further proceedings consistent with this opinion.
Notes
. Masonry prepared and notarized a "Notice of Filing Lien Affidavit and Fund Trapping letter from Derivative Claimant to Owner and Original Contractor,” an "Affidavit Claiming Lien,” and a "Sworn Statement of Account” regarding the unpaid funds due them for the masonry supplies.
. At the time summary judgment was granted, the causes of action against New Age and J.B. Gonzalez were severed, allowing the summary judgment to become final.
. The summary judgment evidence showed Masonry last delivered material to the HEB project site on December 4, 2000. Indebtedness to a subcontractor who has furnished materials accrues on the last day of the last month in which the material was furnished. Tex. Prop.Code Ann. § 53.053(c) (Vernon Supp. 2004-05). Therefore, in this case, the indebtedness accrued December 31, 2000. The deadline for filing the lien affidavit is the 15th day of the fourth calendar month after the day on which the indebtedness accrues; or, in this case, April 15, 2001. Tex. Prop.Code Ann. § 53.052(a) (Vernon Supp.2004-05).
. "A suit on a sworn account under Rule 185 presupposes a contract performed by one party who sues the other party for performance of his obligations.”
Evans Adver. Agency, Inc. v. Morphew,