257 F. 255 | 8th Cir. | 1919
Action at law by the United States of America against Isaac N. Salyers and National Surety Company, commenced May 19,-1913, for the use of Indiana Quarries Company, under Act of Congress of August 13, 1894 (28 Stat. 278, c. 280), as amended by Act of Rebruary 24, 1905 (33 Stat. 811, c., 778 [Comp. St. § 6923]), requiring bonds by contractors on public buildings for the payment of labor and material. (The Quarries Company will hereafter be referred to as plaintiff.)
After the action had been commenced on behalf of the plaintiff, several parties intervened, alleging the furnishing of labor and material. By written stipulation of the parties the action was tried, in June, 1917, to the court without a jury, and resulted in judgments in favor of the plaintiff and the interveners; claim of plaintiff being reduced, however, by certain counterclaims by defendant Salyers, the contractor.
By the present writ of error it is- sought to reverse the judgment in favor of plaintiff. Specifications of error relied upon are as follows:
Rirst. Error in permitting the plaintiff to amend its petition in November, 1916, and in receiving evidence under said amendment.
The building for which the material was furnished was completed May 21, 1912, and, as stated, the action was cofnmenced May 19, 1913, which was within the year provided by the statute. In its original petition plaintiff alleged that it had furnished certain stone to the contractors which had been used and not paid for; the value of the stone furnished was alleged to be $5,000, and the amount der manded was also $5,000. By the first amendment to the petition, filed June 20, 1916, plaintiff alleged that it had furnished to the con
The method adopted by defendant in preserving its rights was appropriate. The filing of the amendment did not cut off the defense. Railway v. Wyler, 158 U. S. 285, 295, 15 Sup. Ct. 877, 39 L. Ed. 983.
The bond required by the statute above cited performs a double function: First, to secure to the government a faithful performance on the part of the contractor; secondly, to protect persons from whom the contractor obtáins labor and materials. U. S. v. Nat. Surety Co., 92 Fed. 549, 34 C. C. A. 526; U. S. v. Rundle, 100 Fed. 400, 40 C. C. A. 450. And the statute is to be liberally construed to effect the purposes within its scope. Ill. Surety Co. v. John Davis Co., 244 U. S. 376, 37 Sup. Ct. 614, 61 L. Ed. 1206; U. S. v. Lowrance, 252 Fed. 122, - C. C. A. -.
But, while the statute creates a new cause of action, it does so upon the terms named in the statute.
“The right of action given to creditors is specifically conditioned upon the fact that no suit shall he brought by the United States within the six months named, for it is only in that event that the creditors shall have a right of action and may bring a suit in the maimer provided. The statute thus creates a new liability and gives a special remedy for it, and upon well-settled principles the limitations upon such liability become a part of the right con*258 íerred and compliance with'them is made essential to the .assertion and benefit of the liability itself.” Texas Cement Co. v. McCord, 233 U. S. 157, 162, 34 Sup. Ct. 550, 552, 58 L. Ed. 893.
Among the limitations in the statute is that of 12 months for bringing suit or filing claims. Texas Cement Co. v. McCord, 233 U. S. 157, 34 Sup. Ct. 550, 58 L. Ed. 893; Ill. Surety Co. v. Peeler, 240 U. S. 214, 36 Sup. Ct. 321, 60 L. Ed. 609; U. S. v. Boomer, 183 Fed. 726; Baker Contract Co. v. U. S., 204 Fed. 390, 122 C. C. A. 560; Eberhart v. U. S., 204 Fed. 884, 123 C. C. A. 180. The claims of the various persons furnishing labor or material are assignable. Title Co. v. Crane Co., 219 U. S. 24, 31 Sup. Ct. 140, 55 L. Ed. 72; U. S. v. Rundle, 100 Fed. 400, 40 C. C. A. 450; Title Co. v. Puget Sound Works, 163 Fed. 168, 89 C. C. A. 618. And each claim is separate and represents a distinct cause of action. Title Co. v. Crane Co., 219 U. S. 24, 35, 31 Sup. Ct. 140, 55 L. Ed. 72; Ill. Co. v. Peeler, 240 U. S. 214, 225, 36 Sup. Ct. 321, 60 L. Ed. 609.
The tests to determine whether two causes of action are identical are fully stated in Whalen v. Gordon, 95 Fed. 305, 313, 37 C. C. A. 70, 79. Among those tests are:
“Will tlie same evidence support both? And will a judgment against one bar the other?”
Applying the first test to the instant case, it is plain that to support the cause of action stated in the original petition and in the petition as first amended, in addition to the formal proof of the giving of the bond and the completion of the contract and settlement thereunder, evidence was necessary (1) that the stone supplied "had been furnished to the defendant; (2) that it had been furnished by the plaintiff; (3) that it had not been paid for. To support the cause of action set up by tire amendment of November, 1916, in addition to the formal proof mentioned, evidence was necessary: (1) That the stone supplied had been furnished to defendant; (2) that it had been furnished by the Perry Company; (3) that it had not been paid for; (4) that the Perry Company had assigned its claim to the plaintiff prior to the expiration of one year from the completion of the contract and “settlement” ; (5) that plaintiff was still the owner of the claim. Ill. Surety Co. v. Peeler, 240 U. S. 214, 225, 36 Sup. Ct. 321, 60 L. Ed. 609. It is clear, therefore, that evidence was needed to support tire cause of action set up in the amendment different from and in addition to what was needed to support the cause of action set up either in the
Finally, this amendment does not effect a mere substitution of parties plaintiff, nor of change of capacity in which plaintiff seeks recovery, so as to be within the scope of the decisions. Railway v. Wulf, 226 U. S. 570, 33 Sup. Ct. 135, 57 L. Ed. 355, Ann. Cas. 1914B, 134; McDonald v. Nebraska, 101 Fed. 171, 41 C. C. A. 278; In re Griggs, 233 Fed. 243, 147 C. C. A. 249; Franklin v. Conrad Stanford Co., 137 Fed. 737, 70 C. C. A. 171. But we have here an instance where the plaintiff having two causes of action has stated but one of them in his original petition, although the amount demanded is large enough to_ cover both of his causes of action, and then seeks by amendment to set up facts vital to a-nd constituting the second cause of action. An amendment setting up such new and second cause of action will not relate back to the date of the original petition, but will be governed by its own date, and if the bar of the statute of limitations or a bar to the right to maintain such new cause of action has intervened, the new cause of action must fail. Texas Cement Co. v. McCord, 233 U. S. 157, 34 Sup. Ct. 550, 58 L. Ed. 893; Ill. Surety Co. v. Peeler, 240 U. S. 214, 225, 36 Sup. Ct. 321, 60 L. Ed. 609; Baker Contract Co. v. U. S., 204 Fed. 391, 122 C. C. A. 560; Eberhart v. U. S., 204 Fed. 884, 123 C. C. A. 180.
The second specification of error relied upon reads:
“Error in permitting the witnesses Hagan and King to testify concerning the contents of the boohs of account of Alexander King & Co., for the reason that said testimony was incompetent, irrelevant, not the best evidence, and no proper foundation therefor had been shown.”
Rule 11 of this court (188 Fed. ix, 109 C. C. A. ix) reads in part as follows:
“When the error alleged is to the admission or to the rejection of evidence, the assignment of errors shall quote the full substance of the evidence admitted or rejected.”
Rule 24 (188 Fed. xvi, 109 C. C. A. xvi), relating to briefs, contains the same provision.
There is no compliance, and no attempt at compliance, with these rules on the part of the plaintiffs in error, either in the original assignments of error filed or in the specification of errors relied upon, set out in the brief, or in the subsequent “argument” contained in the brief. Because of this failure to comply with the rules, the second specification of error will not be considered.
“Final settlement under tbe contract to which you refer was authorized May 21, 1912.”
In our opinion both pleading and proof were sufficient. Ill. Surety Co. v. Peeler, 240 U. S. 214, 36 Sup. Ct. 321, 60 L. Ed. 609; U. S. v. Robinson, 214 Fed. 39, 130 C. C. A. 432; Pederson v. U. S., 253 Fed. 622, - C. C. A. -.
The fifth assignment of error relates to finding of fact in regard to counterclaim of the defendant Salyers. The sixth relates to finding of fact in regard to the claims of the interveners. The seventh to a ruling of the court refusing to appoint an architect to measure the number of cubic feet of stone in the building. They have all been examined, and no reversible error found.
Because of error in allowing the amendment of November, 1916, to the petition and the introduction of evidence thereunder, judgment is reversed, and a new trial ordered.