154 Iowa 630 | Iowa | 1912
Appellant assigns twenty-eight grounds of reversal. We will not attempt to deal with them in detail. The plaintiff was a building contractor. The defendant was a hardware dealer in Story City, whose store building had burned down. On June 22, 1909, a contract was entered into between them, whereby the plaintiff undertook to construct, according to plans and specifications, upon the premises of the defendant, a store building at the cost of $6,640, all to be completed by October 1st following. Plaintiff immediately entered upon the execution of the work. Thereupon it was discovered that the partition wall of the adjoining owner extended over on defendant’s premises from six to sixteen inches. A controversy arose between defendant and the adjoining owner.which lasted for some weeks, and which finally resulted, through course of arbitration, in taking down such parition wall and rebuilding the same. This controversy resulted in the suspension of all work by the plaintiff in the execution of his contract, and such suspension continued until the rebuilding of such partition wall was finished in the latter part of October. Thereupon the plaintiff proceeded with the execution of his contract and worked until the 12th day of December, on which day winter set in with a sudden storm, and plaintiff was unable to further resume work until March following. He brought this suit, claiming certain items of damage resulting to him by reason of delay. The defend
The defendant filed counterclaim for damages, based, principally upon three specifications of breach of the contract: (1) Failure to properly “anchor” the ends of the floor joists in the partition wall. (2) Failure to make the height of seven feet to the basement story. (3) Failure to make basement cement floor of the required thickness of four inches. At the close of the evidence, the trial court withdrew the counterclaim. Complaint is made of such order, and we will give our first attention to this question.
II. Turning, now, to the plaintiff’s cause of action, it is argued that there was no evidence in support of the claim that the defendant was responsible for the delay in the performance of the work. The contention is that the plaintiff voluntarily agreed to the delay. The evidence was in conflict at this point. The question therefore was for the jury. It is also urged that the plaintiff lacked in reasonable diligence on his own part in prosecuting the work, and that he could have shortened the delay if he had chosen to do so. But this question, also, was for the jury, with the clear preponderance of evidence, in our judgment, in favor of the plaintiff at this point.
Exceptions to rulings on evidence are argued by appellant. We find no error in that regard. What we have already said in the foregoing paragraphs is quite determinative of these exceptions. We are not greatly impressed with the merits of the plaintiff’s case as a whole, and we would have been quite as well satisfied with an adverse verdict. But the issues as framed belonged to the jury under the evidence, and the verdict must be sustained.
The judgment below must therefore be affirmed.