[¶ 1] E.F.H., Inc., Peter and Patrick Hughes (collectively, the Hugheses), and the Town of York appeal from a judgment entered in the Superior Court (York County, Fritzsche, J.) vacating the decision of the York Zoning Board of Appeals (ZBA) which had authorized the Hugheses to complete a motel expansion. The Hughes-es contend that the Superior Court erred in holding that (i) the Sahls and the Crafts, owners of residential property near the motel, had standing to sue; and (ii) the ZBA erred in determining that the Hugheses’ right to complete construction had vested. Because there is sufficient evidence in the record to support the ZBA’s determination that the Hugheses’ right to complete construction of the motel had vested, we vacate the judgment.
I. CASE HISTORY
[¶ 2] E.F.H., Inc. owns and operates the Cuttysark Motel located on Long Beach Avenue in York. Peter and Patrick Hughes are shareholders in E.F.H., Inc. The Sahls and the Crafts own residential property across the street from the motel. Their properties and the motel do not share a common boundary.
[¶ 3] In 1991, the Town issued a shore-land permit
1
and other permits to allow construction activities at the motel. The shoreland permit contained no expiration date. In 1995, the Town encouraged and approved phased construction of the motel project to minimize the impact of the construction on the Town. The Town Code Enforcement Officer (CEO) testified that phasing the project was “very attractive” to the Town because it allowed more work
[¶ 4] On November 4, 1997, the Town amended its zoning ordinance to require that work on all shoreland permits issued before May 9,1992 had to be completed by November 5, 1998. 2 The Hugheses determined that they could not start and finish Phase II under the new deadline. In October 1998, the CEO advised the Hugheses to delay work on the project and to seek administrative relief from the ZBA.
[¶ 5] In December 1998, the Hugheses filed an application with the ZBA seeking a determination either that the CEO erroneously interpreted the amended ordinance, or that the ZBA grant them a variance from the ordinance’s requirements. In February 1999, the ZBA conducted a public hearing at which the Hugheses’ counsel, the CEO, and counsel for the Sahls and Crafts made presentations. The Sahls and Crafts claimed that the expanded motel would obstruct their view of the ocean, and that they would be adversely affected by the additional traffic. The CEO testified that the Hugheses were unaware of the amended ordinance prior to its enactment.
[¶ 6] The ZBA initially voted to affirm the decision of the CEO but to grant the variance. Subsequently, the ZBA reconsidered both decisions. At the reconsideration hearing in March 1999, the ZBA rescinded the variance but granted the appeal, concluding that the CEO erred in requesting that the Hugheses defer building plans. In its findings of fact, the ZBA concluded that the building permit was issued in 1991 and that the permit had no expiration date, that phasing for the construction was approved in 1995 to minimize the impact of the construction on- the Town, and that if construction on Phase II had commenced after the amended ordinance was passed, the Hugheses would not have been able to complete the project within one year. The Sahls and the Crafts appealed the ZBA’s decision to the Superi- or Court pursuant to M.R. Civ. P. 80B.
[¶ 7] In February 2000, the Superior Court entered a judgment vacating the ZBA’s decision to grant the Hugheses’ appeal. The court concluded that: (1) both the Sahls and the Crafts had standing; (2) under the plain language of the ordinance the shoreland permit had lapsed; and (3) the ordinance would not be superseded by the doctrine of vested rights. This appeal followed.
II. STANDING
[¶ 8] Pursuant to Maine law governing appeals from municipal boards, “[a]ny party may take an appeal, within 45 days of the vote on the original decision, to Superior Court from any order, relief or denial in accordance with the Maine Rules of Civil Procedure, Rule 80B.” 30-A M.R.S.A. § 2691(3)(G) (1996). To challenge the decision of a municipal zoning board of appeals, a party must “(1) have appeared before the board of appeals; and (2) be able to demonstrate a particularized injury as a result of the board’s action.”
Sproul v. Town of Boothbay Harbor,
[¶ 9] An abutting owner is “[a]n owner of land which abuts or adjoins. The term usually implies that the relative parts actually adjoin, but is sometimes loosely used without implying more than close proximity.” Black’s Law Dictionary 11 (6th ed.1990). We have applied the “close proximity” definition to an abutting landowner in similar cases.
See Brooks v. Cumberland Farms, Inc.,
[¶ 10] The Sahls and the Crafts own property across the street from the proposed motel expansion." They appeared at the ZBA hearing. They contend that the motel expansion would obstruct their view of the ocean, and that additional traffic would adversely affect them. These factors are sufficient to confer standing.
See Forester v. City of Westbrook,
III. VESTED RIGHTS
[¶ 11] We directly review the decision of a municipal zoning board of appeals when the Superior Court acts as an intermediate appellate court pursuant to M.R. Civ. P. 80B.
See DeSomma v. Town of Casco,
[¶ 12] The Hugheses contend that they have vested rights to complete construction of the motel, and that application of the amended ordinance infringes on those rights. In order for a right to proceed with construction under the existing ordinance to vest, three requirements must be met:
1) there must be the actual physical commencement of some significant and visible construction; 2) the commencement must be undertaken in good faith ... with the intention to continue with the construction and to carry it through to completion; and 3) the commencement of construction must be pursuant to a validly issued building permit.
Town of Sykesville v. West Shore Communications, Inc.,
[¶ 13] Maine law is in accord with this view.
See Thomas v. Zoning Bd. of Appeals of City of Bangor,
[¶ 14] In the present case, there was evidence before the ZBA that: (1) the Hugheses received a shoreland permit, with no expiration date, to allow construction activity at the motel; (2) the Town encouraged and approved phasing of the project in 1995 to minimize the impact of the construction; and (3) the Hugheses began the construction work and completed Phase I in 1995. In November 1997, the Town enacted the amended ordinance requiring that the entire phased project be completed within one year. The CEO testified that the Hugheses were unaware of the amended ordinance prior to its enactment. Thus, the evidence before the ZBA and all reasonable inferences drawn therefrom support a determination that: (1) the Hugheses had a valid permit; (2) they made substantial changes by completing Phase I and incurred substantial expenses in its completion; (3) the construction was undertaken in good faith as supported by the later phasing agreement; and (4) the Hugheses relied upon both the ordinances in existence at the time the 1991 permit was issued and the 1995 agreement to phase the project. Because there was sufficient evidence before the ZBA to support its conclusion that the Hugheses’ right to complete construction of the motel had vested, the Superior Court erred in vacating the ZBA’s decision.
The entry is:
Judgment vacated. Remanded to the Superior Court to affirm the decision of the Town of York Zoning Board of Appeals.
Notes
. The record does not contain the 1991 ordinance requiring the issuance of a shoreland permit prior to the commencement of construction activity.
. The amended ordinance provides that "[fjor all Shoreland Permits issued prior to May 9, 1992, all improvements identified in the approved Shoreland Permit must be completed by November 5, 1998 or the Permit shall lapse and become void on November 6, 1998.” York, Me., Zoning Ordinance § 18.2.8 (Nov. 4, 1997).
