SACRAMENTO MUNICIPAL UTILITY DISTRICT, PETITIONER v. FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT MODESTO IRRIGATION DISTRICT, ET AL., INTERVENORS
No. 04-1171
United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued September 9, 2005 Decided November 1, 2005
Harvey L. Reiter argued the cause for petitioner. With him on the briefs were Glen L. Ortman, Adrienne E. Clair, John E. McCaffrey, and Lucy Holmes Plovnick.
Bill Lockyer, Attorney General, Attorney General‘s Office of the State of California, Mary E. Hackenbracht, Senior Assistant Attorney General, Peter C. Kissel, and Elisa J. Grammer were on the brief for California Department of Water Resources.
Robert H. Solomon, Deputy Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With
Michael E. Ward, Anthony J. Ivancovich, Mark D. Patrizio, Stuart K. Gardiner, E. Gregory Barnes, Michael D. Mackness, and Ellen A. Berman were on the brief for intervenors California Independent System Operator, et al. in support of respondent. Jennifer L. Key and J. Phillip Jordan entered appearances.
Before: SENTELLE, RANDOLPH, and ROGERS, Circuit Judges.
Opinion for the Court filed by Circuit Judge RANDOLPH.
RANDOLPH, Circuit Judge: The Sacramento Municipal Utility District (“Sacramento“) sought an order from the Federal Energy Regulatory Commission compelling the major California utilities1 to continue providing it with long-term firm transmission service. Sacramento asserted a right of first refusal under the Commission‘s “Order No. 888.2 The Commission
Commercial relations between Sacramento and the California utilities are governed by private contractual arrangements made in accordance with public tariffs approved by the Commission. Before 1996, vertically integrated utilities provided bundled electricity generation, transmission, and distribution services to both retail and wholesale customers. See Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 681 (D.C. Cir. 2000). Municipalities and other small utilities often required more electricity to serve their customers than they could generate. Such utilities secured additional power through long-term contracts. In August 1967, Sacramento entered into a power transmission agreement with the California utilities. Like many contracts of its era, the Sacramento agreement provided for long-term firm physical transmission service. Sacramento could demand two hundred megawatts of capacity along a specified transmission path at any time throughout the duration of the contract.3 For municipal governments with stringent quality-of-service obligations to
In 1996, the Commission ordered the national deregulation of electricity transmission services. Order No. 888 required utilities to “unbundle” their electricity generation and transmission services and to file new “open access” tariffs - modeled on a pro forma tariff included in the rulemaking - guaranteeing non-discriminatory access to their transmission facilities by competing generators. See Order No. 888, F.E.R.C. Stats. & Regs. ¶ 31,036 at 31,635-36. The Commission recognized that the transition to an open access regime would have significant implications for long-term contract-holders. See id. at 31,662-63. Municipalities and other customers who required the “certainty and continuity” of long-term firm service, Transmission Access Policy Study Group, 225 F.3d at 735, could have found themselves at a disadvantage in a competitive market. To address these concerns, the Commission included in the pro forma tariff a provision granting all long-term firm transmission customers a right of first refusal to continue taking service upon expiration of their contracts.4 Section 2.2 of the tariff provides that “[e]xisting firm service customers ... have the right to continue to take transmission service ... when the contract expires. ... If at the end of the contract term, the [transmission system] cannot accommodate all of the requests for transmission service the existing firm service customer must agree to accept a contract term at least
Although the order required utilities to file tariffs that contained the “non-rate terms and conditions set forth in the ... pro forma tariff,” Order No. 888, F.E.R.C. Stats. & Regs. ¶ 31,036 at 31,768; see also
As the Commission was implementing Order No. 888, the California legislature and the state‘s Public Utility Commission were radically restructuring California‘s energy markets. A
The Commission found the California ISO tariff consistent with the broad non-discrimination goals of Order No. 888. See Pacific Gas & Elec. Co., 81 F.E.R.C. ¶ 61,122, at 61,435, 61,446 (1997) (“CAISO II“). To manage the transition to a new regulatory regime and a completely new service model, the Commission again declined to abrogate existing contracts and ordered customers to take service under the California ISO tariff upon contract expiration.5 Id. at 61,463-65. The California ISO tariff does not contain a right of first refusal provision. The Commission explicitly approved the absence of such a
The Commission nevertheless found that the California ISO tariff would not provide service “as good as or superior to” that provided under Order No. 888 without some instrument for hedging the risk of congestion charges. CAISO I, 80 F.E.R.C. at 61,427. This was especially so for incumbent customers with previously guaranteed service. Id. (“We are also concerned about potential discrimination between new market participants and participants with existing long-term transmission contracts.“). The California ISO proposed a system of “firm transmission rights” - tradeable financial instruments that protect against significant fluctuations in congestion pricing. See Cal. Indep. Sys. Operator Corp., 87 F.E.R.C. ¶ 61,143, at 61,570 (1999) (“CAISO III“). The Commission conditionally approved the proposal, finding these financial instruments to be a sufficient substitute for firm physical transmission rights. Id. at 61,572; see also Cal. Indep. Sys. Operator Corp., 88 F.E.R.C. ¶ 61,156, at 61,525 (1999) (“CAISO IV“) (“We have determined that [firm transmission rights] need not provide customers with firm physical transmission rights in order for them to secure transmission service that is as good as or superior to the service under the Order No. 888 pro forma tariff.“). Although the Commission had previously noted that a right of first refusal mechanism might be appropriate in the context of a transmission rights proposal, CAISO II, 81 F.E.R.C. at 61,473, the proposal
Shortly before its contract with the California utilities was set to expire, Sacramento informed the companies that it wished to extend the terms of the contract or invoke its right of first refusal under Order No. 888. When the California utilities demurred, Sacramento filed a complaint with the Commission. The Commission declined to order the relief sought, noting that “[Sacramento] would have to take service under the CAISO tariff, the only relevant tariff since the California utilities have turned over operational control of their transmission facilities to the CAISO.” Initial Order, 105 F.E.R.C. at 62,615; see also Rehearing Order, 107 F.E.R.C. at 62,010 (“[T]he Commission-approved CAISO tariff is the relevant tariff here for transmission service and that tariff supersedes the Order No. 888 pro forma tariff.“).
In light of the developments described above, the Commission‘s actions can hardly be said to be “arbitrary” and “capricious.”
There is nothing to Sacramento‘s argument that the Commission‘s orders amount to a new rule promulgated without notice and comment and improperly applied retroactively. For reasons already mentioned, the Commission engaged only in the application of an existing rule; it did not alter any aspect of Order No. 888 or the California ISO orders.
Sacramento ultimately challenges the validity of the California ISO tariff itself, arguing that its system of congestion pricing and firm transmission rights - and the absence of an Order No. 888-style right of first refusal - fails to provide a service that is as good as or superior to that under the Order No. 888 pro forma tariff. See, e.g., Brief of Petitioner at 28-30; Reply Brief at 11-12. But the California ISO tariff is not before us. Section 313(b) of the Federal Power Act,
We therefore deny Sacramento‘s petition for review in part and we dismiss it to the extent that it collaterally attacks the Commission‘s California ISO orders.
So ordered.
